Background of DBW Regulation
Key amendments and how these changes will impact the way of making submissions to LTA
Lodgement Scheme
Effective Date
This document is adapted from an official source and formatted for consistency. While Builtsearch aims to keep it accurate and up to date, please refer to the original source for the most reliable and current information.
Document Version: 26 Aug 2021
Background of DBW Regulation
Key amendments and how these changes will impact the way of making submissions to LTA
Lodgement Scheme
Effective Date
Appointment of qualified persons to carry out supervisory oversight of Development, Building works and engineering works
Non - LTA developments | LTA projects |
|---|---|
Developments with NO BASEMENT and with site boundary located > 20m away from the outermost edge of Rapid Transit System (RTS) structure:
| 1. Covered linkway (without any encroachment into station boundary or interface with RTS structures) 2. Cycling/foot path 3. Minor A&A work within station premises:
|
If non-compliance or false declaration is found during engineering work stage, LTA will
Inform QP that the DP or BP NOA (under lodgement scheme) will be revoked;
Inform QP to make a fresh lodgment for DP & BP;
Reject the engineering work submission (without review or any comments). Engineering work application will only be allowed to be submitted after DP/BP is granted.
End of September – please refer to LTA circular issued on 1 Sept 2021.