Sample Inspection Checklists

INSPECTION OF EROSION CONTROL MEASURES

Date of Inspection:

 

Name of Inspecting Officer:

 

Appointment

 

Date & Time of Site Visit:

 

Weather Condition:

 

 

Project Title:

 

 

 

Location of Site :

 

 

Project Duration:

 

Type of Present Construction Activity:

 

 

PUB Permit Number:

 

 

Owner / Developer:

 

QP for Project:

 

QECP for ECM:

 

ECO:

 

Owner / Developer's Representative on-site:

 

 

 

Date of ECM Plan:

 

Last Date of ECM Plan Review:

 

 

ADDITIONAL INFORMATION

Date & Time of Previous Site Visit:

 

 

Date Of Last Inspection Report:

 

 

Issues Identified In Previous Site Visit:

 

 

 

 

 

 

 

 

 

This site inspection has been certified by:

QP / QECP:

Signature: 

Date:  

 

Contractor:

Signature:

Date:

 

Owner/Developer:

Signature:

Date:

 

Note:

Earth Control Measures is for the treatment of silty water due to rain water. Construction wastewater (slurry, bentonite..etc) due to tunnelling, boring..etc shall be separately treated.

S/N

BEST MANAGEMENT PRACTICES

INSPECTION

COMPLIANCE

ACTIONS

1

Construction Sequence & Scheduling

Clearing of construction areas carried out in phases?

Yes / No / NA

 

2

Stockpiles of Earth Materials

Stockpile location according to ECM plan?

Yes / No / NA

 

3

Stablization through laying of milled waste, lean concrete, turfing …etc

Location according to ECM schedule?

Yes / No / NA

 

Construction according to ECM details?

Yes / No / NA

 

Any signs of damage at lean concrete areas?

Yes / No / NA

 

Any signs of damage at milled waste areas?

Yes / No / NA

 

Any signs of damage at turfed areas?

Yes / No / NA

 

4

Stockpiles of Earth Materials

Stockpile location according to ECM plan?

Yes / No / NA

 

Protected against erosion?

Yes / No / NA

 

Protected against sedimentation?

Yes / No / NA

 

5

Silt Traps

Installation of silt traps including location according to ECM schedule?

Yes / No / NA

 

Installation of silt traps according to ECM plan including no.s & size?

Yes / No / NA

 

Silt Traps damaged?

Yes / No / NA

 

6

Sedimentation Basins / Storage Ponds

Installation of basins / ponds including location according to ECM schedule?

Yes / No / NA

 

Installation of basins / ponds according to ECM plan including no.s?

Yes / No / NA

 

Concentration of TSS in effluent (outlet of discharge) < 50mg/l?

Yes / No / NA

 

Sediment filled to within 300mm of water discharge level of outflow structure?

Yes / No / NA

 

Sedimentation basins inlet / outlet choked?

Yes / No / NA

 

Protected against sedimentation?

Yes / No / NA

 

7

Treatment Units / Polymer Blocks

Treatment unit(s) in operation?

Yes / No / NA

 

Polymer blocks used / adequate?

Yes / No / NA

 

8

Perimeter cut-off drains

Installation of cut-off drains including location according to ECM schedule?

Yes / No / NA

 

Installation of cut-off drains according to ECM plan including lengths?

Yes / No / NA

 

Cut-off drain lined?

Yes / No / NA

 

Any signs of inadequate capacity? (flooding)

Yes / No / NA

 

Any obstruction / sediment?

Yes / No / NA

 

Any signs of damage?

Yes / No / NA

 

9

Wheeled wash areas, entry/exit points

Location according to ECM plan?

Yes / No / NA

 

Construction according to details?

Yes / No / NA

 

Any signs of damage?

Yes / No / NA

 

Run-off (from wheeled wash areas) and overflow / discharge channeled to suitable areas for proper treatment?

Yes / No / NA

 

Any signs of silty water from these areas into public drains (drains / roads / etc)?

Yes / No / NA

 

10

Others

Any areas without/inedequate ECM?

Yes / No / NA

 

Public drains at discharge points silted?

Yes / No / NA

 

Public drains in vicinity of site silted / obstructed?

Yes / No / NA

 

Run-off from site not channeled through silt fences / cut-off drains / silt traps?

Yes / No / NA

 

Any discharge of water into public drains?

Yes / No / NA

 

Earth surfaces / slops adjacent to any drain not turfed, paved or covered?

Yes / No / NA

 

 