Why
Background on work management
What
Classification of works on public streets
How
Policies and processes
This document is adapted from an official source and formatted for consistency. While Builtsearch aims to keep it accurate and up to date, please refer to the original source for the most reliable and current information.
Why
Background on work management
What
Classification of works on public streets
How
Policies and processes
Works on public streets need to be managed because they affect:
function of the road Why?
structural integrity of the road
Public street:
area within the road reserve
includes road, footpath, grass verge
Submission to DBC on method statement and monitoring results is required
Type of works:
Excavation/ boring/ pipe-jacking to lay or repair utility services
Soil investigation
Type of works:
Activities occupying traffic lane e.g. hoisting, painting
External works of developments
Any other construction related works that affect public streets
Classification of works:
Planned
Ad-hoc (Connection/ Development)
Emergency
LTA is empowered under the Street Works Act to control & regulate works on public streets |
Street Works Act
Section 8 - Power to order stoppage of activity causing damage to public street
Section 17 - Powers to control works on public streets
Section 29 - Control utility services works on public streets
Code of Practice for Works on Public Streets
Code of Practice for Traffic Control at Work Zone
Standard Details of Road Elements
Code of Practice for Works on Public Streets March 2008
Submission procedure
Documents required
Duties of contractor and supervisor
Reinstatement standards
Key requirements:
Off-peak hour lane closure only
For peak hours refer to Red, Yellow, and Green Lists in LTA.PROMPT. Generally:
Weekday: 7.30am - 9.30am
5.00pm - 8.00pm
Only one lane can be closed at any one time.
Road no-opening period:
Newly resurfaced road – 1 year
Newly constructed road – 2 years
No opening on expressways
Key requirements:
Lane to lane replacement, or use alternative methods e.g. jacking, steel decking, traffic diversion
Full time supervision by qualified supervisor:
Certificate in Pavement Construction and Maintenance Course
Degree in Civil Engineering
Diploma in Civil Eng. with 5 years experience in road-related work.
2 Stages of reinstatement:
Stage 1: Temporary Reinstatement
Immediately upon completion of work
Before opening to peak hour traffic
Stage 2: Permanent Reinstatement
Within 3 weeks of temporary reinstatement
Full lane width
Code of Practice for Traffic Control at Work Zone
Planning and design
Application of devices
Implementation, operation and closeout.
Typical Example of a Traffic Control
Consult
Apply
Construct
DLP
Handover
Consult us on the following works:
Work proposal that requires Master Plan Committee (MPC) adoption
Improvement or upgrading schemes for utility services
Engineering work with excavation of 4m depth or deeper
Tunnelling works and other engineering works
Consult
Apply
Construct
DLP
Handover
Apply for Permit to Work on Public Streets
Log on to LTA.PROMPT – Permit for Road Occupation PorTal
Register online as a member
Submit documents online:
Site plan
Photographs of existing road and structure
Method statement
Drawing of road markings
Traffic control plan
Processing time: 14 working days
https:\\prompt.lta.gov.sg
Consult
Apply
Construct
DLP
Handover
Register commencement date within 28 days
Ensure the following on your work site:
Full time supervision
Traffic control to comply with the COP
LTA conducts random site checks and reinstatement tests.
Consult
Apply
Construct
DLP
Handover
What to do when job is completed
Apply for Initial Handover through LTA.Prompt
Attend to feedback during Defect Liability Period (DLP)
Consult
Apply
Construct
DLP
Handover
What to do when DLP is completed
Apply for Final Handover through LTA.Prompt
LTA will issue a handover letter
Fine and Demerit Points
Fine and demerit points issued for non-compliance
Suspend contractors with 200 demerit points in a month for 3 months
No. of Suspensions in the past two years | Length of Suspension |
0 - 1 | 3 months |
2 | 6 months |
3 | 24 months |
Increase suspension period if contractor has been suspended before
Not allowed to put up any new application