This document is adapted from an official source and formatted for consistency. While Builtsearch aims to keep it accurate and up to date, please refer to the original source for the most reliable and current information.

Document Version: 2023

Fire Code

3

Structural Fire Precautions

3.1

General

The purpose of this chapter of the Code is to stipulate requirements to minimise the risk of spread of fire between adjoining buildings by separation, prevent the untimely collapse of buildings in the event of fire by the provision of a stable and durable form of construction and prevent the spread of fire between specified parts of the buildings by the division of such buildings into compartments.

Explanations & Illustrations

Structural fire precautions relate to the integrity and stability of building elements during fire for a required period of time. “Structural” does not only apply to the structural elements of buildings but other building components, e.g. doors, shafts, walls/ceiling finishes.

The objectives of structural fire precautions are:

1. to unload the spread of fire between adjoining buildings by adequate separation;

2. to prevent the untimely collapse of building, including walls and floors of each unit in the event of a fire; and

3. to prevent spread of fire from one unit to another within the building envelope by compartmentalising each unit with walls, floors and doors having the requisite fire resistance rating.

3.2

Provision of Compartment Walls and Compartment Floors

Rationale

Clause 3.2

Compartmentation serves to reduce the rate of fire spread to enable safe evacuation and firefighting in buildings. It also serves to isolate high risk areas from other parts of a building.

3.2.1

Compartment size - floor area & cubical extent

Any building other than a building of PG I which has any storey the floor area of which exceeds that specified as relevant to a building of that height in column (2) of Table 3.2A, or a cubic capacity which exceeds that specified as relevant in column (3) of Table 3.2A, shall be divided into compartments by means of compartment walls and compartment floors so that:

  1. no such compartment has any storey the floor area of which exceeds the area specified as relevant to the building in column (2) of the table; and

  2. no such compartment has a cubic capacity which exceeds that specified as relevant in column (3) of the table.

Explanations & Illustrations

Generally, the compartment size of apartment or maisonette unit would not exceed 4000m² or a cubical extent of 15000m³ as given in Table 3.2A which is reproduced below:

3.2A : SIZE LIMITATION OF BUILDING & COMPARTMENT

Compartments

Maximum Floor Area

Maximum Cubical Extent

Compartment below ground level
(No compartment shall comprise more than one storey)

2000m²

7500m³

Compartments between average ground level and a height of 24m
(No compartment shall comprise more than 3 storeys)

4000m²

15000m³

Compartments above a height of 24m from average ground level
(No compartment shall comprise more than one storey)

2000m²

7500m³

However, for non-residential areas in buildings under PG II, such as communal area or car parking area irrespective of location in either upper storeys or basement, there would be a need to apply the size limitation of 4000m² or 15000m³. The above non-residential areas would be dealt with under their respective PG VII & VIII respectively.

Compartment below ground level

  1. Under Table 3.2A no compartment shall comprise more than one storey and exceed floor area of 2000m² and a cubical extent of 7500m³. However, exceptions are allowed in the following situations:

    1. Only 1st basement having a floor area of less than 100m² can form part of the 1st and upper storey compartment under Cl.3.2.5c., provided the building is sprinkler-protected including the basement.

    2. Basement floors can be interconnected for use as car parking, if sprinkler system is provided.

  2. Basement floor or compartment shall not be used for bulk storage of highly inflammable liquids or substances of any explosive nature.

Compartments between average ground level & a height of 24m

No compartment shall comprise more than 3 storeys and floor area greater than 4000m² and cubical extent exceeding 15000m³. However, exceptions are allowed under Cl.3.2.3Cl.3.2.4a. and Cl.3.2.8.

Compartments above a height of 24m from averaged ground level

  1. No compartment shall comprise more than 3 storeys and floor area greater than 4000m² and cubical extent exceeding 15000m³. Every storey above a height of 24m shall be a fire compartment.

    General: In computing the extent of a compartment, protected shafts e.g. lift, staircases etc. and separately compartmented lavatory/locker room can be disregarded. See Cl.1.4.29 for further illustration.

  2. High bay warehouse (HBW) and mechanised car parking buildings are treated differently from normal industrial buildings.

The requirement of restricting the compartment to max. 3 storeys would not be applicable. Such types of buildings are usually not occupied or have very limited people working in the premises.

Automatic sprinkler system and smoke extraction or venting system are required to be provided for high bay warehouses and mechanised car parking buildings which exceed 24m in building height.

Compartments above a height of 24m from averaged ground level

No compartment shall comprise more than one storey and exceed the floor area of 2000m² and cubical extent of 7500m³.

This requirement would not apply to high bay warehouses and mechanised car parking buildings. Prior consent is to be obtained from the SCDF before submission of building plan.

3.2.2

Cubical extent for compartment exceeding 4m in height

  1. In computing the cubical extent of compartments in single storey buildings such as factories, sport halls, markets, food courts, multi-purposes halls, cinemas, concert halls, churches, temples and similar buildings, the height of 4m shall be used where the actual height exceeds that figure.

  2. If any compartment comprises more than one storey or contains mezzanine, galleries or lofts, the full height of the compartment shall be used in computing the cubical extent for each storey, mezzanine, galleries or lofts.

  3. Where two buildings are connected by external open-sided covered walkway or open-sided covered link-bridge, the buildings are considered as separate buildings, if they comply with the following conditions:

    1. There is no commercial activities or other usage that would pose a fire risk within the covered walkway or link-bridge.

    2. The width of the covered walkway or covered link-bridge shall not exceed 5m measured from eave to eave.

Rationale

The 4m in height serve as a relaxation for purpose of computing cubical extent, instead of using the actual height, for single storey buildings of non-warehouse usage. The consideration takes into account that such spaces are meant to facilitate placement of machinery and for purpose of viewing, and are unlikely to have high level storage.

3.2.3

Exemption of compartmentation

Cl.3.2.1 is not applicable if the building:

  1. is fitted throughout with an automatic sprinkler system which complies with the requirements in Chapter 6; and

  2. complies with Cl.3.2.4 Cl.3.2.6Cl.7.4 and  Cl.9.8.3.

Explanations & Illustrations

To avoid providing fire compartmentation in building to comply with the cubical extent and floor area control under Table 3.2A, automatic sprinkler system would be proposed as an alternative. Where automatic sprinkler system is to be provided to a building, compliance with Table 3.2A on max 3 storeys per compartment is still required, unless atrium design is proposed subject to obtaining the SCDF ’s prior approval before submission of building plan.

Note to QP

QPs should consult SCDF for all atrium designs. Requirements provided under Cl.7.5Cl.3.2.6Cl.3.2.4 and Cl.9.8.3 are to be complied with respectively.

3.2.4

Compartmentation by height

  1. In any compartment except those mentioned under Cl.9.1, up to a habitable height of 24m, no compartment shall comprise more than three storeys. This requirement can be relaxed for atrium spaces provided the design of such spaces complies with the conditions stipulated under Cl.3.2.6.

  2. In any building which exceeds 24m in habitable height, no compartment shall comprise more than one storey for compartments at storey level exceeding 24m above average ground level, other than a compartment which is within a residential maisonette which may comprise two storey levels.

Explanations & Illustrations

Clause 3.2.4a. : Compartmentation by height

Figure 3.2.4a.
Figure 3.2.4a.

Where 3 storeys or levels form one compartment, the total floor area shall not exceed 4000m² and the total cubical extent shall not exceed 15000m³, subject to compliance with travel distance requirements under Chapter 2.

In the case of atrium design space, it can go beyond 3 storeys per compartment but shall not exceed habitable height of 24m. in other words, every storey beyond 24m in height is a fire compartment.

Clause 3.2.4b. : Compartmentation by height

Figure 3.2.4b. - 1
Figure 3.2.4b. - 1

In any commercial building which exceeds 24m in habitable height, no compartment shall comprise more than one storey per compartment from storey level exceeding 24m above average ground level. There is a need to keep the fire compartment size small within 2000m² or 7500m³ above that habitable height, as it would otherwise pose difficulties to firefighting and control of fire spread should there be a fire occurrence in one of those high-rise units.

Figure 3.2.4b. - 2
Figure 3.2.4b. - 2

In any residential building which exceeds 24m in habitable height, no compartment shall comprise more than one storey per compartment from storey level exceeding 24m above average ground level. However, for residential maisonette or penthouse unit, maximum two storey levels are allowed to form one compartment. This should be taken as a relaxation. There is a need to keep the fire compartment size small within 2000m² or 7500m³ above that habitable height as it would otherwise pose difficulties to fire fighting and control of fire spread should there be a fire occurrence in one of those high-rise units. In situation where there are maisonette or penthouse units located in non-residential building, fire protection/detection system applicable to the building shall be extended to cover the residential units.

3.2.5

Areas requiring compartmentation

The following situations shall require compartmentation by provision of compartment walls and/ or compartment floors:

  1. PG II buildings

    Any wall and floor separating a residential apartment or maisonette from any other part of the same building, unless permitted (as in the case of an external wall adjoining an external corridor, for provision of window openings).

Explanations & Illustrations

Clause 3.2.5a. : Areas requiring compartmentation

Figure 3.2.5a. - 1 : Compartment walls in PG II building
Figure 3.2.5a. - 1 : Compartment walls in PG II building
Section Figure 3.2.5a. - 2 : Compartment walls & floors in PG II building
Section
Figure 3.2.5a. - 2 : Compartment walls & floors in PG II building
  1. Areas of different purpose groups

    Any wall and floor separating part of a building from any other part of the same building which is used or intended to be used mainly for a purpose falling within a different purpose group, as identified under Table 1.4A, except the following:

    1. ancillary offices located within a building or compartment of PG III, V, VI, VII and VIII, or

    2. rooms or spaces for ancillary usage located within a building or compartment of PG III to VIII as stipulated under Cl.1.4.5, or

    3. rooms or spaces located within a sprinkler-protected building, unless otherwise stated in following Cl.3.2.5 or other clauses in the Code.

Explanations & Illustrations

Clause 3.2.5b. : Areas requiring compartmentation

Figure 3.2.5b. - 1 : Compartment walls separating different PGs
Figure 3.2.5b. - 1 : Compartment walls separating different PGs
Figure 3.2.5b. - 2 : Compartment walls separating different PGs
Figure 3.2.5b. - 2 : Compartment walls separating different PGs
Figure 3.2.5b. - 3 : Compartment walls & floors separating different PGs
Figure 3.2.5b. - 3 : Compartment walls & floors separating different PGs

Compartment walls and floors shall be constructed of non-combustible materials to have minimum 1-hr fire resistance rating under Table 3.3A for any of the compartment.

Figure 3.2.5b. - 4 : Compartment walls separating different PGs
Figure 3.2.5b. - 4 : Compartment walls separating different PGs

In the above diagram, the car park (PG VIII) is fire compartmented from the shopping area. The car park has higher fire risks than shopping and cineplex. Fire separation between cineplex and shopping area is required. This is to safeguard the occupants in the cineplex from any fire occurrence in the shopping area.

Figure 3.2.5b. - 5 : A mixture of different PGs without fire compartment
Figure 3.2.5b. - 5 : A mixture of different PGs without fire compartment

The above diagram shows a typical shopping floor, which has a mixture of different purpose groups without fire compartmentation.

Strictly interpreting the above subclause would mean that in a shopping centre, for example, shop (PG V), office (PG IV), place of public resort (PG VII), commercial school (PG III) would need to be separately compartmented from each other. This would not be practical. In practice, shopping or commercial buildings would have mixture of the uses of different purpose groups.

Under sub-clause (b)(i), an ancillary office which is located within the compartment or floor used as PG V is not required to be separately fire compartmented, provided the measurement of travel distance requirements of PG III shall apply to the ancillary office. Similarly, under sub-clause (b)(ii) , ancillary usage to PG III such as sick/first aid room, reception lobby/area, waiting area, staff lounge/staff recreation room, staff rest room/pantry, staff changing/locker room, meeting room, staff training room, etc. is not required to be separately fire compartmented.

  1. Floor over a basement

    Any floor immediately over a basement for PG II to VIII buildings shall be a compartment floor except for:

    1. a basement with floor area not exceeding 100m², or

    2. PG IV, V and VII buildings with basement floor area exceeding 100m2, provided the following conditions are complied with:

      1. the building is fitted throughout with an automatic sprinkler system in compliance with the requirements in Chapter 6; and 

      2. the first basement shall be compartmented from other basement storeys.

    Note: For PG I buildings, refer to Cl.9.1.1b.(2) for compartmentation of floor over basement requirements.

Explanations & Illustrations

Clause 3.2.5c.(2) : Areas requiring compartmentation

To avoid providing fire compartmentation in building to comply with the cubical extent and floor area control under Table 3.2A, automatic sprinkler system would be proposed as an alternative. Where automatic sprinkler system is to be provided to a building, compliance with Table 3.2A on max 3 storeys per compartment is still required, unless atrium design is proposed subject to obtaining the SCDF ’s prior approval before submission of building plan.

Figure 3.2.5c.(2) - 1 : Floor over basement
Figure 3.2.5c.(2) - 1 : Floor over basement

Where the floor area of the basement exceeds 100m2 it shall be a compartment below ground level and shall not comprise more than one storey. The basement floor shall be provided with sprinkler system under Cl.6.4.1d.(1) and dry riser under Cl.6.2.1b.

Figure 3.2.5c.(2) - 2 : Floor over basement
Figure 3.2.5c.(2) - 2 : Floor over basement

In situation where the basement floor area is not exceeding 100m², the basement and upper storeys may be allowed to be interconnected to form one compartment, subject to max. 3 storeys or levels in a single compartment. It should be noted that  Cl.3.2.5d. prohibits more than one storey below ground level to be connected to form one compartment.

Figure 3.2.5c.(2) - 3 : Floor over basement
Figure 3.2.5c.(2) - 3 : Floor over basement

All basement floors, except those under PG I & II, are required to be provided with automatic sprinkler system under Cl.6.4.1d.(1). Where basement floor, regardless of its area, is interconnected with upper storeys, the automatic sprinkler system required for the basement shall be extended to cover all the upper storeys.

Figure 3.2.5c.(2) - 4 : Floor over basement
Figure 3.2.5c.(2) - 4 : Floor over basement

For buildings under PG IV, V and VII, the first basement floor can be inter-connected with the upper storeys regardless of whether or not it exceeds 100m2, provided sprinkler system and smoke control system are provided.  For atrium design, prior consent from the SCDF should be obtained before making Building Plan submission.  See Cl.3.2.4a..

Cl.3.2.5d. prohibits more than one basement floor to be connected to form one compartment, except in the case of basement used solely for car parking.

  1. Basement floors

    In any compartment below pavement level, no compartment shall comprise more than one storey, except in the case of PG IV, V and VII buildings as permitted under Cl.3.2.5c.(2) and in the case of basement used solely for car parking. No part of a basement storey shall be used for the bulk storage of highly inflammable liquids or substances of an explosive nature.

Explanations & Illustrations

Clause 3.2.5d. : Areas requiring compartmentation

Figure 3.2.5d. - 1
Figure 3.2.5d. - 1

Basement 1, which has a floor area of less than 100m² can be interconnected with 1st storey, provided it is compartmented from basement 2. Sprinkler system and rising mains are required to be provided to the building.

Figure 3.2.5d. - 2
Figure 3.2.5d. - 2

Basement 1 having a floor area of more than 100m² is required to be compartmented from 1st storey. The above clause does not permit more than one basement storey per compartment unless solely used for car parking. Sprinkler system and rising main are required to be provided to basement.

Figure 3.2.5d. - 3
Figure 3.2.5d. - 3

Owing to the special use where ramps or car lifts are needed to connect all the floors, compartmentation is relaxed where sprinkler system and rising main are provided.

  1. Fire Command Centre (FCC)

    The FCC shall be separated from other parts of the same building by compartment walls and floors having at least 2-hr fire resistance rating.

Explanations & Illustrations

Clause 3.2.5e. : Areas requiring compartmentation

The fire resistance rating of the walls and floors shall comply with the elements of structure and shall have minimum period of 2 hours. Any door opening into the Fire Command Centre from the occupancy area shall be minimum 2-hr fire-rated.

  1. Kitchen

    In room/ space where open-flame cooking activities are carried out, except for residential units in PG I and II buildings, the following requirements shall be complied with:

    1. The kitchen shall be separated from other parts of the same building by compartment wall and floor having at least 1-hr fire resistance rating. Separation requirement for kitchen can be exempted under the following conditions:

      1. when all the cooking facilities in the kitchen are fitted with approved extinguishing systems, or

      2. when there are at least 25% of the perimeter walls (excluding air well and void) of an eating establishment open directly to the external of the building, and provided any part of the floor space is within 9m from the nearest opening, or

      3. when there are at least 50% of the perimeter walls (excluding air well and void) of an eating establishment open directly to the external of the building, and provided any part of the floor space is within 12m from the nearest opening, or

      4. when an eating establishment is separated from other parts of the same building by walls and floors having 1-hr fire resistance rating and doors having at least ½-hr fire resistance rating; and provided:

        1. for a sprinkler-protected building, there is no restriction to the floor area of the compartment, or

        2. for a non-sprinkler-protected building, the floor area of the compartment shall not exceed 150m2.

Explanations & Illustrations

Clause 3.2.5f.(1)(a) : Areas requiring compartmentation

Figure 3.2.5f.(1)(a)
Figure 3.2.5f.(1)(a)

The above sub clause allows the kitchen not to be compartmented if the cooking hood or range is installed with an automatic fire suppression system. Automatic fire suppression system shall be of approved type based on international standards such as NFPA 17A. QPs are also reminded to ensure that the premise owners/ operators are aware of the stipulated maintenance regime in the standards.

With this arrangement, there is no need to seek waiver approval from the SCDF.

Clause 3.2.5f.(1)(b) : Areas requiring compartmentation

Figure 3.2.5f.(1)(b) - 1
Figure 3.2.5f.(1)(b) - 1
Figure 3.2.5f.(1)(b) - 2
Figure 3.2.5f.(1)(b) - 2
Figure 3.2.5f.(1)(b) - 3
Figure 3.2.5f.(1)(b) - 3

Clause 3.2.5f.(1)(c) : Areas requiring compartmentation

Figure 3.2.5f.(1)(c) - 1
Figure 3.2.5f.(1)(c) - 1
Figure 3.2.5f.(1)(c) - 2
Figure 3.2.5f.(1)(c) - 2

The 25% and 50% ventilation openings are required for smoke venting and relief of accumulated heat from the area on fire. This exemption cannot be applied in an enclosed air-conditioned environment, where the peripheral walls are fitted with glass panel.

The 25% and 50% ventilation openings are absolute values. Extrapolation of percentage ventilation openings based on depth of the eating establishment is not permitted.

Figure 3.2.5f.(1)(c) - 3
Figure 3.2.5f.(1)(c) - 3

In the above figure the kitchens are not required to be compartmented.

Ventilation openings along the external walls ‘a’, ‘b’, ‘c’ and ‘d’ shall be uninterrupted, having minimum 50% of the perimeter walls of the eating establishment. The openings to the air well shall not be included in this purpose.

The above requirement is more relevant to hawker centre type design.

Clause 3.2.5f.(1)(d) : Areas requiring compartmentation

Figure 3.2.5f.(1)(d) - 1
Figure 3.2.5f.(1)(d) - 1

Under Cl.3.2.5f.(1)(d)(i), the kitchen and dining area can be in one compartment, provided the building is sprinkler-protected and there is no need restricting to the floor area of the compartment

Figure 3.2.5f.(1)(d) - 2
Figure 3.2.5f.(1)(d) - 2

With the provision of sprinkler system, further relaxation is allowed to permit the whole eating establishment to be enclosed with at least 1-hr fire-rated walls and ½-hr fire-rated door. There is no restriction to the accessible floor area of the eating establishments.

Figure 3.2.5f.(1)(d) - 3
Figure 3.2.5f.(1)(d) - 3

Under Cl.3.2.5f.(1)(d)(ii), where the building is not sprinkler-protected, the area of the compartment, kitchen and dining area e.g. (unit A) shall not exceed 150m2.

Rationale

Clause 3.2.5f.(1)

The conditions for exemption of compartmentation for open-flame cooking area ensure that smoke could be readily dispersed via the openings to the external and fire can be contained within the cooking area so as not to affect the escape of occupants.

  1. -

    1. Openings in the compartment wall and floor shall comply with the relevant provisions of Cl.3.9 for protection of openings.

    2. Doors shall have at least ½-hr fire resistance rating and be fitted with an automatic self-closing device.

Explanations & Illustrations

Clause 3.2.5f.(1) to (3) : Areas requiring compartmentation

Figure 3.2.5f.(1) to (3) - 1
Figure 3.2.5f.(1) to (3) - 1

The above figure illustrates a eating establishment without kitchen fire-suppression system.  The clause enables the QP to exercise the option of compartmenting kitchen with open-flame cooking.

Figure 3.2.5f.(1) to (3) - 2
Figure 3.2.5f.(1) to (3) - 2

Kitchen is compartmented from dining area by 1-hr enclosures and ½-hr fire doors. Protection to servery hatch can be a fire-rated roller shutter held in the open position by fusible links.

Section Figure 3.2.5f.(1) to (3) - 3
Section
Figure 3.2.5f.(1) to (3) - 3

As the dumb waiter is connecting 2 storeys, it shall be enclosed in 2-hr protective enclosures with 1-hr fire-rated access door at each storey.

  1. -

    1. Where the flue or duct passes through the compartment wall or floor, the flue or duct shall be encased by non-combustible construction to comply with the requirements of Cl.3.9.5, and the installation of dampers in such flue or duct is prohibited.

    2. LPG cylinders provided for open-flame cooking activities shall not be located at the basement and the installation of LPG cylinders at other areas shall comply with the provisions in the Fire Safety (Petroleum) Regulations.

Explanations & Illustrations

Clause 3.2.5f.(4) : Areas requiring compartmentation

Section Figure 3.2.5f.(4)
Section
Figure 3.2.5f.(4)

Kitchen is required to be compartmented from other areas by 1-hr compartment walls and floors. Doors to the kitchen shall have minimum ½-hr fire resistance rating and shall open outward from the kitchen. Small fires which commonly occur in the kitchen are often caused by overheating of cooking oil on the stove or in a deep pan fryer or by grill. Exhaust ducts in kitchen are usually coated with grease internally over a period of time. Fire in the ducts could be started by sparks or by fire from the stove.

Cooking appliances include – open-flame gas fired oven, charcoal grill and appliances which have open flames located or protected from views.

Fire-rated door to kitchen shall not be wedged open for serving purpose. In circumstances where fire doors are to be kept open, the door shall be fitted with electromechanical device susceptible to smoke under Cl.3.9.2c.. See Cl.1.4.34 for further illustration. 

To qualify for non-provision of fire compartment under Cl.3.2.5f.(1), auto fire suppression equipment should be incorporated into the cooking range. This equipment may consist of fixed pipe carbon dioxide, dry chemical or foam- water sprinkler or spray system. Such auto suppression system to the cooking range shall be listed and approved by a certification body.

Explanations & Illustrations

Clause 3.2.5f. : Areas requiring compartmentation

Section Figure 3.2.5f.
Section
Figure 3.2.5f.

Where ‘open-flame’ cooking is used, the compartment comprising dining and kitchen areas shall not comprise more than one storey:

In the case of eating establishment which comprises 2 storeys, then each storey shall be a fire compartment by itself.

  1. Motor vehicle workshop

    A motor vehicle workshop shall be separated from any other part of the same building by compartment walls and floors having at least 2-hr fire resistance rating, and if located in a basement storey of a building, shall be separated from any other part of the same building by compartment walls and floors having at least 4-hr fire resistance rating.

Explanations & Illustrations

Clause 3.2.5g. : Areas requiring compartmentation

Section Figure 3.2.5g.
Section
Figure 3.2.5g.
  1. Spray painting room

    Areas in which spray painting or other related processes are performed or carried out, shall be separated from other parts of the same building by compartment walls and floors having at least 2-hr fire resistance rating. Where spray painting booths that have built-in vapour extraction system complying with NFPA 33, the fire resistance requirement is not applicable.

    Where a spray painting room or booth is protected by an automatic sprinkler system but not complying with NFPA 33, the fire resistance rating for the fire compartment to the room or booth can be reduced from 2-hr to 1-hr.

Explanations & Illustrations

Clause 3.2.5h. : Areas requiring compartmentation

Figure 3.2.5h.
Figure 3.2.5h.

Spray painting booth or room shall be mechanically ventilated and enclosed in min. 2-hr fire-rated compartment to allow spraying of paint to be carried out. It shall be constructed to prevent the escape of spray and flammable vapour which shall be removed by the exhaust system. 

The exhaust discharge point shall be not less than 5m from the inlet of any mechanical ventilation system.

  1. Store room

    For non-sprinkler-protected buildings, if the area of the store room exceeds 10m², it shall be compartmented from the other parts of the same building by compartment walls and floors having at least 1-hr fire resistance rating. No fire compartmentation is required for a store room which is housed within a sprinkler-protected building. However, store room exceeding 700m2 and 100m2 for above-ground and below-ground respectively are subject to the compartment size requirements stipulated under Cl.9.8.3.

Explanations & Illustrations

Clause 3.2.5i. : Areas requiring compartmentation

Figure 3.2.5i.
Figure 3.2.5i.

Store 1 exceeding 10m² inside a Hotel space will need to be compartmentalised with 1- hour fire rated enclosures.

Store 2 which is less than 10m² still required to be provided with fire door as the store opens into internal corridor, which is pressurised.

The main reason for compartmentation of storeroom is to prevent undetected fire in the storeroom from developing into a big fire.

Compactus

Compactus room which is more than 10m² shall be treated as a compartment under the above sub-clause. The enclosing walls/floor/ceiling/door shall have min. 1-hr fire resistance rating. Irrespective of the location of the compactus storage area, if it is not enclosed in a room, it shall be treated as open storage shelves and not as a store. The main reason is that a fire occurring in a room could be unnoticed, until it becomes too big to be put out by first aid firefighting equipment. An incipient fire occurring in an unenclosed compactus storage area could be easily spotted by occupants and immediate reaction could be taken to put out the fire.

Any store, regardless of its size, shall be compartmented under the above sub-clause if it opens directly into exit passageways and designated protected escape routes, e.g. smoke-stop lobbies, protected staircases.

  1. Areas of special hazard

    1. Areas of special high risk in a building

      Boiler rooms, transformer rooms, generator rooms, storage areas of materials that are highly combustible or flammable, and any other areas of special high risk shall be separated from other parts of the building by compartment walls and floors having at least 2-hr fire resistance rating. If the building is protected by an automatic sprinkler system, the fire resistance rating of the compartment walls and floors can be reduced to one hour.

    2. Room housing transformer that uses flammable liquid shall be located at ground level against an external wall.

    3. Diesel fuel tank for generator need not be located against an external wall.

Explanations & Illustrations

Clause 3.2.5j. : Areas requiring compartmentation

Section Figure 3.2.5j.
Section
Figure 3.2.5j.

Transformer and generator rooms that contain flammable liquids should be located against an external wall for external ventilation and explosion relief.

Transformer room

Transformers could be dry type or oil cooled type. Oil cooled type is to be located against an external wall above ground level to allow for external ventilation and explosion relief. Adequate precautions should be taken by the provision of a suitable catch pit or other means to prevent the spread of fire resulting from leakage and ignition of oil.

Generator rooms

Generator sets shall be located in clean, dry locations within fire-rated compartments. They may be placed outdoors if they are of purpose built type, provided proper separation from unprotected openings of the building is maintained. Generator rooms shall be located against an external wall above ground level to allow for external ventilation and explosion relief.

Storage areas of highly combustible or flammable materials

Where possible, oil storage tanks should be installed in open air at ground level at least 6m from adjacent buildings and in accordance with CP 40. A max. capacity of 700 litres of diesel oil is permitted to be stored in the generator room. The oil drum(s) shall be located within a bunded area, capable of containing 100% spillage from the drum(s).

Prior approval is to be obtained from the SCDF for storage of combustible or flammable liquids, other than in the generator room, before building plan submission.

Rationale

Clause 3.2.5j.(2) & (3)

Rooms for housing dry transformer, transformer using non-flammable liquids or generator needs not be located against an external wall. 

Diesel fuel tank within a generator room is also not required to be placed against an external wall as the flash point of diesel fuel is high enough to be. non-flammable in most environments. However, it still required careful storage and safety precautions.

3.2.6

Provision for atrium spaces

The requirements of Cl.3.2.1Cl.3.2.4a. and Cl.3.2.4b. of this Code are not applicable for atrium spaces provided the following conditions are complied with:

  1. The minimum plan area of the atrium void shall be not less than 93m² and no horizontal dimension between opposite edges of the floor opening is less than 6m wide.

  2. The atrium space is not of high hazard occupancy as stated in Cl.1.4.68

  3. The atrium is open and unobstructed in a manner such that it can be assumed that a fire in any part of the space will be readily obvious to the occupants before it becomes a hazard.

  4. The building is fitted throughout with an automatic sprinkler system to comply with the requirements in Chapter 6.

  5. The building is fitted with an engineered smoke control system in accordance with Cl.7.4.5.

  6. Provision of openings and enclosures, and the planning of means of escape shall be subject to the approval of the SCDF.

Explanations & Illustrations

Section Figure 3.2.6 - 1
Section
Figure 3.2.6 - 1
  1. The above clause allows the SCDF  to vary the max. floor area/cubical extent of fire compartment to allow more than 3 storeys to be interconnected. The critical points for consideration would include the size and configuration of atrium void and the provision of sprinkler system and engineered smoke control system.

  2. QPs should consult the SCDF  in cases of all atrium designs before making building plan submission. The vetting will confine only to looking at the concept and the layout and profile of atrium void in the building proposal only. Calculations for the engineered smoke control system shall be submitted separately by M&E QPs.

  3. Where a compartment in a building has a total floor area and cubical extent greater than that allowed under Table 3.2A, but the number of floor interconnected by void does not exceed 3 floors, QPs should consult the SCDF whether there is a need to provide engineered smoke control system, before making building plan submission. Similarly, if a compartment in a building has a total floor area and cubical extent greater than that allowed under Table 3.2A and the number of floor interconnected by void is more than 3 floors, QPs should consult the SCDF before making building plan submission. The consultation would confine to vetting of requirements mentioned in sub-clause 2. above.

Section Figure 3.2.6 - 2
Section
Figure 3.2.6 - 2

Atrium design allows multiple floors to be connected beyond 3 storeys per compartment but limit to a  habitable height of 24m. The design would require the provision of engineered smoke control system and sprinkler system. The above clause allows atrium design in buildings, but prior approval from the SCDF must be obtained before building plan submission can be made. See Cl.1.4.13.

3.2.7

Buildings of high hazard occupancy

  1. The compartment of buildings of high hazard occupancy shall not exceed one half of the sizes given in Table 3.2A and each compartment shall comprise one storey only.

  2. No storey of a building, the habitable height of which is more than 24m, shall be used for the bulk storage of goods or substances of highly combustible nature unless the building is provided with a sprinkler system to comply with Chapter 6.

  3. The type of storage materials or substances shall not include the following:

    1. materials with an auto-ignition temperature lower than 200°C; and

    2. combustible/ highly flammable materials which include those highlighted in sub-clauses a.b.c. and d. of Cl.1.4.68.

  4. For buildings not listed in Table 1.4A, including but not limited to buildings used for the manufacture and/ or storage of highly combustible substances and/ or flammable liquids, etc., the requirements shall be consulted with the SCDF.

Explanations & Illustrations

Section Figure 3.2.7
Section
Figure 3.2.7
  1. Warehouse compartments A, B & C, as shown in above figure, shall not exceed 2000m² and 7500m³. Each compartment shall comprise one storey only. The materials to be stored in the warehouses shall exclude those listed under Cl.3.2.7c.(1) & (2).

  2. Buildings with habitable height not exceeding 24m are allowed to be used for bulk storage of goods or substances of highly combustible nature, except those listed under Cl.3.2.7c.(1) &  (2). However, if the above mentioned warehouse buildings exceed the habitable height of 24m, the whole building must be protected with automatic sprinkler system. Irrespective of the building height, Cl.3.2.7a. shall be complied with.

  3. Materials as listed under Cl.3.2.7c.(1) &  (2) are not allowed to be stored in any multi-storey building, regardless of the habitable height.

3.2.8

Exemption on size limitation of compartment

The requirements of Cl.3.2.1 for car parking decks can be exempted if both the following are complied with:

  1. The car parking decks shall be open-sided with not less than 50% of the sides permanently open and unobstructed. Such openings shall be evenly distributed along each of the perimeter walls and on every individual floor/deck, excluding perimeter walls to air well, so as to provide cross ventilation to all parts of the car parking decks.

  2. No part of the floor space shall be more than 12m from the openings on the perimeter walls of the building or air well. Air well where provided for this purpose shall have a superficial plan area of not less than 10m², or 0.1m² for every 300mm of height, whichever is greater, and have a minimum dimension on plan of 2m, open vertically to the sky for its full height.

Explanations & Illustrations

Section Figure 3.2.8 - 1
Section
Figure 3.2.8 - 1

As the habitable height is less than 24m, automatic sprinkler system is not required. The clear width of the air well shall not be less than 2000mm to prevent fire from a car from spreading vertically between split levels. Provision of fire alarm system shall be in accordance with Table 6.3A of the Fire Code.

Openings such as grille, fixed louvre types are considered acceptable. In determining the openings for the grille, obstacle should be deducted to obtain the nett openings. As for fixed louvres, only free area should be taking into account. Provision of sliding windows is not acceptable. The minimum 50% openings in the external walls shall be permanently open and such openings shall be evenly distributed to provide cross ventilation so as to prevent smoke logging.

Section Figure 3.2.8 - 2
Section
Figure 3.2.8 - 2

Situation 1 – Car park is integrated with office/shop building

The attached multi-storey car park is required to be protected by sprinkler system. Cl.3.2.8a. would not apply as there is free access between car park area and the shop/office floor area. There could be sharing of common escape staircases by occupants in the car park area and the shop/office floor area.

Situation 2 – Attached multi-storey car park is an independent building

Attached multi-storey car park would qualify for exemption on size limitation of compartment under Cl.3.2.8a., provided there is no access opening in the continuous vertical compartment wall that separates car park building from shop/office building and no sharing of escape staircases. Each building is self-sufficient in its provision of means of escape. Multi-storey car park shall comply fully with Cl.3.2.8a. on the provision of permanent ventilation openings for cross-ventilation.

Rationale

The minimum ventilation requirements stipulated for open-sided carpark are to ensure effective cross ventilation so as to minimise smoke logging in the event of a fire in the car park. The dimensions have been validated through a fire engineering study.

With effective ventilation, the compartment size limitation for a non-sprinkler protected car park can be exempted.

3.2.9

Separation of area undergoing addition & alteration works

For additions and alterations to existing buildings, the areas undergoing such works shall be separated from other occupied areas of the building in accordance with Cl.3.15.16.

Explanations & Illustrations

For the benefit of clarification, the Code has introduced this clause to clarify that the separation material for spaces undergoing additions and other occupied spaces need not be fire-rated construction. Instead, non-combustible partition used for separation between the undergoing A&A works and other occupied areas shall suffice.

3.3

Fire Resistance of Elements of Structure

3.3.1

Interpretation and application

The interpretation and application of Cl.3.3 shall be as follows:

  1. Subject to the provisions of Cl.3.3.1b. and any other expressed provision to the contrary, any reference to a building of which an element of structure forms a part means the building or (if the building is divided into compartments) any compartment of the building, for which the element forms a part.

Explanations & Illustrations

Section Figure 3.3.1a.
Section
Figure 3.3.1a.

Any reference to a building, which is divided into compartments, of which an element of structure forms a part, means that compartment of the building (Building A).

Any reference to a building of which an element of structure forms a part means the building (Building B). It is important to note that any element carrying another element of structure must have at least the same fire resistance as the element it is supporting.

  1. Any reference to height means the height of a building, but if any part of the building is completely separated throughout its height both above and below ground from all other parts by a compartment wall or compartment walls in the same continuous vertical plane, any reference to height in relation to that part means the height solely of that part.

Explanations & Illustrations

Section Figure 3.3.1b.
Section
Figure 3.3.1b.

The continuous vertical compartment wall divides the building into 2 parts. For building A, any reference to height means the building height (A). For building B, any reference to height means the building height (B).

  1. If any element of structure forms part of more than one building or compartment and the requirements of fire resistance specified in Table 3.3A, in respect of one building or compartment, and differs from those specified in respect of any other building or compartment of which the element forms a part, such element shall be so constructed as to comply with the greater or greatest of the requirements specified.

Explanations & Illustrations

Section Figure 3.3.1c. - 1
Section
Figure 3.3.1c. - 1

The diagram above shows a shopping podium and an office tower. The fire resistance of the elements of structure at the interface between the podium and tower shall be the higher of the two purpose groups (shops or offices).

The elements of structure referred to include compartment floor and also the columns going through the podium to support the structural frame of the office tower.

Section Figure 3.3.1c. - 2
Section
Figure 3.3.1c. - 2
Section Figure 3.3.1c. - 3
Section
Figure 3.3.1c. - 3

In the above figures, the continuous vertical compartment wall forms part of more than one building or compartment. The compartment wall shall be constructed to have higher fire resistance rating of the two buildings or compartments.

  1. If any element of structure is required to be of non-combustible construction, the measure of fire resistance rating shall be determined by the part which is constructed wholly of non-combustible materials. (With the exception of fire protecting suspended ceilings, surface materials for walls and ceilings and floor finishes can be combustible, if they are not relied on to contribute to the fire resistance of the wall or floor).

Explanations & Illustrations

Axonometric Section Figure 3.3.1d. - 1
Axonometric Section
Figure 3.3.1d. - 1

The above figure shows the construction of a non-load-bearing fire-rated compartment wall. If the C-channel or horizontal channel supports are replaced with timber members, the construction would not meet the requirement of the above subclause, as timber members are combustible. However, combustible finish if added to the surface of the wall would be considered as acceptable, provided it complies with Cl.3.13.

Section Figure 3.3.1d. - 2
Section
Figure 3.3.1d. - 2

The above figure shows the addition of timber floor finish to the R.C floor. The combustible floor finish is not to be considered as contributing to the fire resistance of the floor.

For fire protection to suspended ceilings see Cl.3.3.5. The above clause is also not applicable to buildings under preservation or conservation where structural timber members are required to be retained. See also Cl.9.1.1b. and  Cl.9.9.1.

3.3.2

Minimum periods of fire resistance

Subject to any expressed provision to the contrary, any element of structure shall be constructed of non-combustible materials and is required to have fire resistance for not less than the relevant period specified in Table 3.3A, with regards to the purpose group of the building of which it forms a part and the dimensions specified in that table, provided that:

  1. any separating wall shall have at least 1-hr fire resistance rating; and

  2. any compartment wall or compartment floor which separates a part of a PG II or III buildings, from any other part of the building of a purpose group other than PG II or III shall have at least 1-hr fire resistance rating.

3.3.3

Exemption for non-load-bearing external walls

The requirement on fire resistance in Cl.3.3.2 for non-load-bearing external walls shall not apply to:

  1. any part of any external wall which is non-load-bearing and can, in accordance with Cl.3.5 be an unprotected area, or

  2. steel structures of a standalone car park for passenger vehicles of Class 3 and below (unladen weight not exceeding 2500kg) provided the following conditions are fulfilled:

    1. Each storey shall be provided with cross ventilation by the provision of uninterrupted openings evenly distributed around the perimeter walls, excluding perimeter walls to air well. The area of the openings shall not be less than 50% of all external walls or 15% of the footprint per storey, whichever is greater. This condition is not applicable if a sprinkler system is installed throughout the car park.

    2. No point on any storey shall be more than 12m from the external air or air well. An air well, where provided for this purpose, shall have a superficial plan area of not less than 10m², or 0.1m² for every 300mm of height, whichever is greater, and have a minimum dimension on plan of 2m, open vertically to the sky for its full height. This condition is not applicable if a sprinkler system is installed throughout the car park.

    3. All floor beams shall be designed as a composite structure with the floor slab.

    4. The building is not more than 24m in habitable height, and there shall not be any basement storeys;

    5. No other usages, other than the electrical services that serve only the car park, are permitted;

    6. Steel structures shall meet the specifications of SS EN 1993-1-2 and SS EN 1994-1-2.

Explanations & Illustrations

Axonometric view Figure 3.3.3
Axonometric view
Figure 3.3.3

Any part of a non-load-bearing external wall which constitute the unprotected opening in pursuance to Cl.3.5, is not required to have any fire resistance. In the above diagram, the non-load-bearing external wall facing the public road need not have fire resistance as it meets Cl.3.5 on set-back requirement, measured from the centre of the public road to the external wall.

3.3.4

Exemption for single storey buildings

In the case of a single storey building or a building consisting of a first storey and one or more basement storeys, the requirement on fire resistance in Cl.3.3.2 shall not apply to any element of structure which forms part of the first storey and consists of:

  1. a structural frame or a beam or column, provided that any beam or column (whether or not it forms part of a structural frame) which is within or forms part of a wall, and any column which gives support to a wall or gallery, shall have fire resistance of not less than the minimum period, if any, required by this Code for that wall or gallery, or

Explanations & Illustrations

Section Figure 3.3.4a.
Section
Figure 3.3.4a.

The above exemption applies to all single storey buildings. However, in cases where the floor area of the building exceeds 4000m², prior consultation with the SCDF is required.

  1. The structural frame or beams and columns of a single storey building need not have fire resistance under Table 3.3A, unless otherwise specified by the SCDF. The QPs shall, before making building plan submission, consult the SCDF as to the need for protection of beams and columns in the following situations :

    1. Single storey factory or warehouse involving high hazard materials;

    2. Single storey factory or warehouse having an extensive footprint; and

    3. Single storey warehouse exceeding a building height of 10m.

  2. However, any beam or column which is within or forms part of a compartment wall, separating wall or external wall (which requires fire resistance under Cl.3.5) shall be required to have the same fire resistance rating as the wall in which such beam or column forms part of.

  3. Any column or beam which gives support to a wall or gallery, shall have the same fire resistance as that required for the wall or gallery, e.g. column and beam supporting the external wall or mezzanine floor shall have the necessary fire resistance rating.

  1. an internal load-bearing wall or a load-bearing part of a wall, unless that wall or part of it forms part of a compartment wall or a separating wall, or forms part of the structure enclosing a protected shaft or supports a gallery, or

Explanations & Illustrations

Section Figure 3.3.4b.
Section
Figure 3.3.4b.

An internal load-bearing wall or a load-bearing part of a wall is not required to have fire resistance under Table 3.3A, provided the wall is not:

  1. forming part of or a compartment or separating wall,

  2. forming part of the structure enclosing a protected shaft e.g. exit staircase, or

  3. supporting a gallery.

  1. part of an external wall which does not support a gallery and which may, in accordance with Cl.3.5 be an unprotected area.

Explanations & Illustrations

Section Figure 3.3.4c.
Section
Figure 3.3.4c.

External wall which does not support a gallery and has adequate setback from the boundary in accordance with Cl.3.5 to be an unprotected area need not have fire resistance under Table 3.3A.

Explanations & Illustrations

Clause 3.3.4 : Exemption for single-storey building

Axonometric Section Figure 3.3.4 : Single-storey building with or without basement
Axonometric Section
Figure 3.3.4 : Single-storey building with or without basement

Exemption for Single Storey Buildings

Irrespective of floor area, the minimum period of fire resistance rating for elements of structures is 1 hour. However, Cl.3.3.4 of the current Fire Code provides exemption for single storey buildings which need not comply with 1 hour fire resistance rating for the structural frame or beam or column subject to:

  1. the beams or columns are not supporting a wall or gallery;

  2. the beams or columns are not forming part of the separating wall between houses;

  3. the external walls including the supporting beams or columns which are not supporting a gallery or in  accordance with Cl.3.5 be an unprotected area.

3.3.5

Suspended ceiling

In determining the fire resistance of floors, no account shall be taken of any fire resistance attributable to any suspended ceiling unless the ceiling is constructed specifically as a fire protecting suspended ceiling, and the construction complies with the requirements under Table 3.3B for Limitations on Fire Protecting Suspended Ceilings.

Explanations & Illustrations

Section Figure 3.3.5 - 1
Section
Figure 3.3.5 - 1
Section Figure 3.3.5 - 2
Section
Figure 3.3.5 - 2

The suspended ceiling is to be treated as the soffit as the floor system or assembly consists of the timber boarding, joists and the suspended ceiling to achieve the necessary fire resistance rating. 

Therefore the concealed space in the floor system or assembly is to be treated differently from concealed spaces mentioned under Cl.3.11. The main different is that concealed spaces in floor system or assembly are not permitted to have services such as air-con ducts, cables, pipes etc.; even if these services are housed in fire-rated enclosures.

Axonometric Section
Axonometric Section
Section Figure 3.3.5 - 3
Section
Figure 3.3.5 - 3

The implications of Cl.3.3.5 are that the normal type of suspended ceiling consisting of separate tiles cannot be counted as contributing to the fire resistance of the floor in buildings over 15m high where the period required is 1 hour; or in buildings of any height where the period required is more than one hour. In these circumstances only jointless ceilings can be considered as contributing

The above figure shows a protective ceiling being added to the underside of a timber floor, shall apply only to buildings under conservation where retention of the timber floor is required, and in buildings under PG I & II for the construction of attic. In addition to the four grades of ceiling given in Table 3.3B, other ceiling construction to tested prototype listed in the product listing scheme would be considered as acceptable.

The ceiling shown in Figure 3.3.5 - 1, shall be constructed specifically as a fire protecting membrane and comply with Table 3.3B on limitation of fire protecting suspended ceiling. As the ceiling is intended as a protecting membrane, the concealed ceiling space shall not be used for recessed lighting and other service, such as air-con ducts, cables, pipes etc., even if these services are housed in fire-rated enclosures.

Suspended ceilings which are contributing to the fire resistance rating of the floor under Table 3.3B.

Section
Section
Compartment floor requiring less than 1 hour fire resistance rating
Compartment floor requiring less than 1 hour fire resistance rating
Compartment floor requiring 1 hour fire resistance rating
Compartment floor requiring 1 hour fire resistance rating
Figure 3.3.5 - 4 : Height of building less than 15m
Figure 3.3.5 - 4 : Height of building less than 15m
Section
Section
Compartment floor requiring 1 hour or less fire resistance rating
Compartment floor requiring 1 hour or less fire resistance rating
Non-compartment floor requiring 1 hour or less fire resistance rating Figure 3.3.5 - 5 : Height of building - 15m or more
Non-compartment floor requiring 1 hour or less fire resistance rating
Figure 3.3.5 - 5 : Height of building - 15m or more
Section
Section
Non-compartment floor requiring 1 hour or less fire resistance rating
Non-compartment floor requiring 1 hour or less fire resistance rating
Compartment floor requiring more than 1 hour fire resistance rating Figure 3.3.5 - 6 : Height of building - any height
Compartment floor requiring more than 1 hour fire resistance rating
Figure 3.3.5 - 6 : Height of building - any height

The foregoing figures illustrate the intent of the clause which basically deals with the contribution by suspended ceilings to the fire resistance of floors. The provision of suspended ceilings for the protection of the floors shall be treated differently from that provided for the protection of structural steel works in the ceiling space.

Where the space above a suspended ceiling is protected by an automatic sprinkler system it shall be exempted from the requirements for non-combustibility and surface spread of flame classification as specified in the above Table, provided the ceiling is not situated over an exit passageway, protected lobby or other required protected means of escape, and that the ceiling space is not used as an air plenum.

3.3.6

Fire-rated board

  1. Fire-rated boards are permitted to be used for protection to structural steel beams, columns and as wall construction in building if all of the following are complied with:

    1. The fire-rated boards shall be non-combustible (BS 476 Part 4 or Part 11).

    2. They shall have fire resistance for not less than the relevant period specified in Table 3.3A, with regards to the purpose group of the building of which it forms a part and the dimensions specified in that table.

    3. They shall meet the criteria, in terms of water absorption and bending strength performance, when subject to the test standards of BS EN 520 (for gypsum plaster board) or ISO 1896 (for calcium silicate or cement board).

    4. Fire-rated boards used to make dry walls shall, in terms of impact & deflection performance, meet the partition grade specified under BS 9999 (Test for partitions) in accordance with BS 5234-2.

    5. They shall not be used to protect structural steel in areas which are subject to explosion risk, as the boards may be displaced by the force of the blast.

    6. In buildings under PG VI and VIII, where the presence of corrosive atmosphere may affect the effectiveness of fire-rated boards for protection to structural steel members of buildings, such proposals shall be subject to evaluation of the SCDF.

  2. Incorporation of services within fire-rated drywall construction shall comply with the following:

    1. The installations shall meet the fire performance test requirements set out in BS 476 Part 22 and shall not incorporate services beyond the case scenario for which it has been successfully tested.

    2. Electrical cables shall be housed in metal conduits within the dry construction.

    3. Gas pipe installation are prohibited in fire-rated dry construction.

Note to QP

Clause 3.3.6b

  1. Design stage

    Individual supplier shall conduct fire tests for their entire product ranges, i.e. different fire ratings for similar types of dry construction material, same fire rating for different types of dry construction material, etc.. However, it would be acceptable for the Test Laboratory to carry out an assessment for similar product ranges with the same fire rating for the dry construction assembly (with services within) with one that had been tested subject to product assessment requirements of Test Laboratory. However, where a dry wall construction differs in terms of fire rating, services layout and configuration etc., separate fire test(s) need to be conducted.

  2. Commissioning stage

    Under the Product Listing Scheme (PLS), it is a requirement for supplier to submit DoC for the project to a Certification Body (CB) for audit purposes. However, DoC shall now also be included as a mandatory document for QP to submit to SCDF for issuance of TFP. The requirement will mandate QP to check on the quality of fire-rated dry construction on site and ensure that the supplier diligently checks the quality of work before submitting the DoC for the project.

  3. Post installation stage

    Addition & Alteration (A&A) works which were carried out on fire-rated dry construction may contravene design criteria such as puncturing the board for mounting of additional services and thereby undermining its fire integrity and insulation. Therefore, the QP shall comply with the following administrative requirements for subsequent A&A works on fire-rated dry construction:

    1. The building owner shall endorse on plans that where any subsequent A&A works involving fire-rated dry construction are to be carried out, a QP shall be engaged.

    2. For easy identification of fire-rated dry construction within the building, the QP shall indicate the locations of fire-rated dry construction on

      1. a zone chart in accordance with the requirements stipulated in SS CP 10; and

      2. the A&A building plan for approval by the SCDF.

Explanations & Illustrations

Clause 3.3.6 : Fire rated board

Running of services in the space between the steel structure and fire-rated boards should be discouraged, unless it is unavoidable.

Services shall be limited to cables only and shall not include duct, gas pipes, fuel oil pipes, etc.

3.4

Tests of Fire Resistance

3.4.1

Fire resistance

Performance for the fire resistance of elements of structure and other forms of construction shall be determined by reference to the methods specified in BS 476: Part 20 to 23, which specify tests for stability, integrity and insulation.

Specific requirements for each element in terms of the three performance criteria of stability, integrity and insulation are given in Table 3.4A.

Explanations & Illustrations

In conjunction with Part 20, methods of test are provided for – Beams, columns, floors, flat roofs and walls (Part 21); Partitions, door sets and vertical shutter assemblies, ceiling membranes and glazed elements (Part 22); and Suspended ceilings protecting steel beams and  intumescent seals for use in conjunction with single acting latched timber fire-resisting door assemblies (Part 23).

Part 20 specifies standard heating conditions based on a temperature/time curve (Figure 3.4.1 - 2) which furnaces are required to follow; the temperature at defined locations close to the exposed face of the specimen under test rising to 821°C after 30 minutes and 1133°C after four hours.

Figure 3.4.1 - 1
Figure 3.4.1 - 1
Figure 3.4.1 - 2 : Standard temperature vs Time curve
Figure 3.4.1 - 2 : Standard temperature vs Time curve

The specimen to be tested should be either full size or, where the element exceeds the size that can be accommodated by the furnace, it must have the following minimum dimensions.

Non-separating elements: Vertical 3m high Horizontal 4m span

Separating elements: Vertical 3m high X 3m wide Horizontal 4m high X 3m wide

Specimens are normally heated to simulate their exposure in a fire, e.g. walls from one side, floors from beneath and columns from all sides.

Elements of building construction are required to satisfy various criteria according to their designed function in the event of fire. These are:

  1. “Stability” or “Load-bearing capacity”: the ability of a load-bearing element to support its test load without excessive deflection.

  2. “Integrity”: the ability of a separating element to resist collapse, the formation of holes, gaps or fissures through which flames and/or hot gases could pass, and the occurrence of sustained flaming on the unexposed face (the side of the specimen remote from the furnace).

  3. “Insulation”: the ability of a separating element to resist an excessive rise in temperature on its unexposed face.

The criterion of “stability” or “load-bearing capacity” is applied only to load-bearing elements. For floors, flat roofs and beams, allowable vertical deflection is limited to 1⁄20 clear span.

Loss of “integrity” in the context of the formation of holes, gaps or fissures is judged by ignition of a cotton fibre pad. Where this test is not suitable, failure is deemed to have occurred if either a 25mm diameter gauge can penetrate into the furnace through a gap at any point, or a 6mm diameter gauge can penetrate into the furnace through an opening and can be moved for a distance of at least 150mm.

Loss of “insulation” occurs when the temperature on the unexposed face (the side of the specimen remote from the furnace) increases by more than 140°C (mean) or by more than 180°C at any point. Loss of “integrity” also constitutes loss of “insulation”.

Columns and beams have to satisfy only the criterion of “load-bearing capacity”; glazed elements are normally required to satisfy only “integrity”; and floors and walls have to satisfy all three criteria. It is pertinent to note that under Table 3.4A, doors are only required to satisfy “integrity”, leaving aside “insulation” as it is assumed unlikely that combustible materials would be stored against them. However, doors to protected lobbies, exit staircases and exit passageways should be provided with insulation against transmission of heat by radiation from the fire floor into the protected enclosures which occupants use for evacuation.

It is important to note that fire-rated glass door shall not be used in fire lift shaft, exit staircases and exit passageways. In other areas such as protected lobbies, separating and compartment walls, the use of fire-rated glass is permitted, provided the building is sprinkler-protected. See Cl.3.15.13 for more details.

3.4.2

“Deem to satisfy” provisions

An element of structure or other part of a building shall be deemed to have the requisite fire resistance if:

  1. it is constructed to the same specification as that of a specimen exposed to test by fire in accordance with the method and procedure under BS 476: Part 20 to 23, and satisfied the requirements of that test for the three performance criteria of stability, integrity and insulation for not less than the specified period, or

  2. in the case of a wall, beam, column, stanchion or floor to which Annex 3A to Cl.3.4 relates, it is constructed in accordance with one of the specification set out in that Annex and the notional period of fire resistance given in that Annex as being appropriate to that type of construction and other relevant factors is not less than the specified period.

Explanations & Illustrations

Cl.3.4.2b. provides the alternative to complying with the specification of tested prototype under BS 476 Part 20 to 23. Specification set out in Annex 3A to Cl.3.4 could be used and there is no need to obtain separate testing. However, on completion of the building works, the QP concerned is to forward to the RIs his/her certificate of supervision that the relevant specification listed in Annex 3A to Cl.3.4 had been complied with on site when applying for TFP or FSC.

3.5

External Wall

3.5.1

Requirements of external walls

The requirements of external walls are as follows:

  1. Any external wall of a building or a separated part of a building which constitutes or is situated within a distance of 1m from any point on the relevant boundary, or is a wall of a building or a separated part of a building which exceeds 15m in height shall:

    1. be constructed wholly of non-combustible materials apart from any external wall finishes which complies with Cl.3.5.4 or any internal lining which complies with Cl.3.13.4

    2. be so constructed as to attain the fire resistance required by this chapter; and

  2. any beam or column forming part of an external wall, and any structure carrying an external wall which is required to be constructed of non-combustible material, shall comply with the provisions of Cl.3.5.1a..

Explanations & Illustrations

Clause 3.5.1 : Requirements of external walls

Figure 3.5.1a. - 1: Buildings of any height situated at 1m or less from relevant boundary
Figure 3.5.1a. - 1: Buildings of any height situated at 1m or less from relevant boundary
Figure 3.5.1a. - 2
Figure 3.5.1a. - 2

Where the external wall of a building which exceeds 15m in building height or is within 1m of the relevant boundary, the entire external wall shall be constructed wholly of non-combustible materials, apart from any external combustible cladding under  Cl.3.5.4 or internal combustible lining under Cl.3.13.4.

The external wall of building which is sited less than 1m from the relevant boundary, shall be imperforate, free of any unprotected area and have the necessary fire resistance rating, both inside and outside. The required fire resistance shall be achieved by the non-combustible part alone.

The external wall shall have the necessary fire resistance rating as required of the elements of structure of the building or compartment, in which the wall is located, in accordance with Table 3.3A, Part 1.

Any part of the external wall which is to be treated as unprotected area in accordance with Tables to Part II of Annex 3B to Cl.3.5, need not have fire resistance.

If the entire external wall is to be treated as unprotected area, the separation distance between the external wall and the relevant boundary shall comply with Tables to Part II of Annex 3B to Cl.3.5.

External walls, which are more than 1m from the boundary, need to resist the effect of fire from the inside only.

In cases where the external walls of buildings are situated less than 1m from relevant boundary, the external walls shall be treated as separating walls. The requirements under Cl.3.6 shall be fully complied with.

Clause 3.5.1b. : Requirements of external walls

Any beam or column forming part of an external wall and any structure carrying an external wall shall be constructed of non-combustible materials and have the necessary fire resistance rating of elements of structure, apart from any external cladding which complies with Cl.3.5.4 or any internal lining which complies with Cl.3.13.4. The required fire resistance shall be achieved by the non-combustible part alone.

3.5.2

Exceptions on external wall construction

  1. The requirements of Cl.3.5.1a.(1) for non-combustibility of external walls need not apply to the external wall of a building or part of a building separated as described in Cl.3.3.2b., if that wall is situated 1m or more from the relevant boundary and it is:

    1. of PG I or II building of not more than three storeys, or

Explanations & Illustrations

Figure 3.5.2a.(1) - 1 : PG I / PG II building
Figure 3.5.2a.(1) - 1 : PG I / PG II building
Figure 3.5.2a.(1) - 2 : Separated part of PG I / PG II building
Figure 3.5.2a.(1) - 2 : Separated part of PG I / PG II building

Part of a PG II building (not exceeding 3 storeys – building B in Figure 3.5.2a.(1) - 2, separated from the other parts (building A) by vertical compartment wall. Exemption would also apply to the building in Figure 3.5.2a.(1) - 1 which shall not exceed 3 storeys in height and be situated 1m or more from the relevant boundary.

  1. -

    1. of single storey construction and not exceeding 15m in height and floor area not exceeding:

      1. 3000m2 for PG III, IV, VII buildings, or

      2. 2000m2 for PG V, VI buildings, or

      3. 500m2 for PG VIII buildings, or

Explanations & Illustrations

Figure 3.5.2a.(2)
Figure 3.5.2a.(2)

Single storey health care occupancy, schools, old folk’s home, etc. (PG III) need not comply with non-combustibility of external wall, if it complies with the requirements under Cl.3.5.2a.(2).

  1. -

    1. of other than single storey buildings, but not exceeding 7.5m in height and the compartmented floor area not exceeding:

      1. 250m2 for PG IV, V, VII buildings, or

      2. 150m2 for PG VI, VIII buildings.

Explanations & Illustrations

Figure 3.5.2a.(3) - 1
Figure 3.5.2a.(3) - 1
Figure 3.5.2a.(3) - 2
Figure 3.5.2a.(3) - 2

Cl.3.5.2a.(3) is applicable to separated part of building as described in Cl.3.3.4b., which is illustrated in Figure 3.5.2a.(3) - 2.

Part A of the building comprising shops which is separated from other parts of the same building by a continuous vertical compartment wall would qualify for exemption of non-combustibility of external construction if:

  1. the entire external wall does not exceed 7.5m in height, measured from the outside ground; and

  2. the external wall is situated 1m or more from the relevant boundary.

  1. The requirements of Cl.3.5.1a.(2) for fire resistance of external walls need not apply to the external wall of a building or part of a building separated as described in Cl.3.3.2b., if that wall is situated 1m or more from the relevant boundary and it is:

    1. of a single storey building of a purpose group other than PG VI and VIII and not exceeding 15m in height, or

    2. of a single storey PG VI or VIII building not exceeding 15m in height and floor area not exceeding 2000m² or 500m² respectively.

3.5.3

Unprotected areas in any side of a building

Unprotected areas in any side of a building shall comply with all of the following:

  1. Any relevant requirements relating to the permitted limits of unprotected areas specified in Annex 3B, unless the building is so situated that such side can in accordance with Annex 3B, consist entirely of any unprotected area.

Explanations & Illustrations

Unprotected areas in relation to a side or external wall of a building means:

  1. a window, door or other opening, and

  2. any part of the external wall which has less than the relevant fire resistance required in Cl.3.5, and

  3. any part of the external wall which has combustible material more than 1mm thick attached or applied to its external face whether for cladding or any other purpose

The extent of unprotected areas in the external wall in relation to the setback from relevant boundary or lot boundary shall be in accordance with Annex 3B to Cl.3.5. The further the building is setback from the relevant boundary, the greater the amount of unprotected areas would be permitted.

An example on calculations of unprotected openings/setback from relevant boundary is given in page 56. The intensity of the heat produced by a fire within a building which can reach the relevant boundary will depend upon the extent of the “unprotected areas” in the external walls and the distance between these walls and the relevant boundary. The heat flux at the relevant boundary shall be less than that normally required for pilot ignition of combustible material after a period of exposure.

In situations where the extent of unprotected areas in external walls do not comply with Annex 3B, the QP has 4 alternatives. These are:

  1. reduce the total unprotected area, or

  2. increase the distance from the relevant boundary, or

  3. introduce compartmentation within the building to break up the size of enclosing rectangle, or

  4. introduce automatic sprinkler system so that the unprotected areas can be doubled or the distance from the relevant boundary can be reduced by half.

  1. The extent of unprotected openings in an external wall of a building/compartment, in relation to its distance from the lot boundary, can be doubled that of Annex 3B, provided the building/ compartment is fitted throughout with an automatic sprinkler system in compliance with the requirements in Chapter 6.

  2. As an alternative to Cl.3.5.3b. above, the distance between the external wall of a building and the relevant boundary can be half that specified in Annex 3B, if the building is fitted throughout with an automatic sprinkler system in compliance with the requirements in Chapter 6.

  3. The extent of unprotected openings in an external wall of a building/ part of building used for car parking in relation to its distance from the lot boundary/ relevant boundary can be based on the floor having the largest extent of unprotected openings to comply with Table 1 of Annex 3B.

Explanations & Illustrations

Clause 3.5.3c. : Unprotected areas in any side of a building

The above clause is to provide an alternative for buildings protected with sprinkler system. QP/Building owner shall decide which option, Cl.3.5.3b. or  c. i.e. either double the unprotected openings or half the separation distance between the building and the relevant boundary, whichever is relevant to the building.

Clause 3.5.3d. : Unprotected areas in any side of a building

Section Figure 3.5.3d. - 1
Section
Figure 3.5.3d. - 1

The above clause treats car park building differently by allowing the floor having the largest extent of unprotected openings to be used for the purpose of complying with Table 1 of  Annex 3B. This clause grants special relaxation in relation to its distance from the lot boundary for the purpose of complying with Table 1 of  Annex 3B.

In the above figure, the enclosing rectangle would apply to 1st storey elevation facing the relevant boundary, instead of the whole building, which forms one compartment.

Section Figure 3.5.3d. - 2
Section
Figure 3.5.3d. - 2

The above clause treats car park building differently by allowing the floor having the largest extent of unprotected openings to be used for the purpose of complying with Table 1 of  Annex 3B. This clause grants special relaxation in relation to its distance from the lot boundary for the purpose of complying with Table 1 of  Annex 3B.

In the above figure, the enclosing rectangle would apply to 1st storey elevation facing the relevant boundary, instead of the whole building, which forms one compartment.

3.5.4

External wall finishes

Finishes on external walls shall comply with the following:

  1. Homogenous cladding on external walls shall be constructed of material of at least limited combustibility tested in accordance with BS 476 Part 11 or approved equivalent. For buildings not within PG VI and VIII, any part of such cladding below a height of 15m from the ground, and situated at least 1m away from the relevant boundary can consist of:

    1. timber of not less than 9mm finished thickness, or

    2. a material having a surface which achieves at least:

      1. Class 0 flame-spread rating tested in accordance with BS 476 Part 6 & 7, or

      2. Class B rating classified under EN 13501-1.

  2. Composite panels used as cladding on external walls shall comply with Cl.3.15.13.

Rationale

This clause stipulates the requirements for cladding materials on the exterior of buildings. It also provides clarity on the rating and classification of that part of the building below 15m in height, and on the use of composite panels as cladding material.

3.5.5

Reference to Part I & II of Annex 3B

Any reference to Annex 3B shall be construed as referring to the provisions of Part I of that Annex together with the provisions of Part II.

3.5.6

Buildings on land in common occupation

If two or more detached buildings are erected on land in common occupation, for any external wall of such a building facing the external wall of an adjacent building, the relevant boundary shall be a notional boundary passing between those buildings. This notional boundary shall be positioned to enable the external walls of those buildings to comply with the requirements of Cl.3.5.3.

Explanations & Illustrations

Figure 3.5.6
Figure 3.5.6
  1. It is necessary to assume a notional boundary when two or more detached buildings are erected on land in common occupation.

  2. The notional boundary is taken to exist in space between the buildings and is positioned so that the external walls of building A and B facing the notional boundary comply with the separation distance requirement in accordance with Tables of  Annex 3B, based on the percentage of unprotected area and the purpose group of the compartment/floor.

  3. Unprotected openings shall be assessed for each building separately. The separation distance between the two buildings shall be not less than the sum of the distance each building would require to a relevant boundary i.e. “a” is equal to or greater than the separation distance to the boundary for building A and “b” is equal to or greater than the separation distance to the relevant boundary for building B.

  4. The notional boundary can be shifted next to external wall of building A or B, if the external wall has no unprotected areas and is constructed of non-combustible materials having the requisite period of fire resistance rating as the elements of structure of the storey compartment.

3.5.7

Vertical fire spread

  1. For high and low parts of different compartments of a building abutting each other, either one of the following requirements shall be complied with to prevent spread of fire between the distinct parts:

    1. the roof-over of the lower part of the building shall be fire-rated in accordance with the element of structure for minimum 1 hr for a distance of 5m measured horizontally from the external wall of the higher part of building; or

    2. the external wall of the higher part of the building overlooking the roof below shall have the necessary fire resistance rating in accordance with the element of structure for minimum 1 hr for a vertical height of not less than 9m measured from the roof of the lower part of the building.

Explanations & Illustrations

Clause 3.5.7a.(1) : Vertical fire spread

Section Figure 3.5.7a.(1)
Section
Figure 3.5.7a.(1)

The entire roof projection over the lower part of the building if less than 5m, then the entire roof projection shall be fire-rated with minimum 1-hr fire resistance rating. A fire occurring in the 3rd storey would spread vertically to 4th storey via the roof and windows. To prevent the fire spread vertically, the roof of 3rd storey should be fire-rated for minimum. 1 hour for a distance of 5m measured horizontally from the external wall of 4th storey abutting the roof of 3rd storey. The above requirement to fire rate the roof of 3rd storey will not be applicable if the building or lower part of the building is sprinkler-protected.

Clause 3.5.7a.(2) : Vertical fire spread

Section Figure 3.5.7a.(2) - 1
Section
Figure 3.5.7a.(2) - 1
Section Figure 3.5.7a.(2). - 2
Section
Figure 3.5.7a.(2). - 2

Providing fire rated wall with unprotected opening is an alternative to fire rating the roof under Cl.3.5.7a..

The above 2 figures show the 2 ways of preventing fire spread vertically from the lower floor to the upper floors.

  1. The above requirements shall not be applicable to:

    1. buildings or lower parts of the building which are sprinkler-protected;

    2. the buildings under the conservation programme of the authority having jurisdiction, or buildings built before 1969;

    3. covered car porches intended solely for the purpose of the boarding and alighting of passengers;

    4. open-sided/ covered walkways/ linkways not exceeding 5m in width with no commercial activities or storage; and

    5. canopies of depth not exceeding 2m over private enclosed spaces or balconies in PG II buildings, provided that the canopy is constructed of non-combustible material.

Rationale

Clause 3.5.7

The purpose of providing high/low separation is to ensure fire will not spread from the lower compartment to the abutting higher different compartment of the building.

3.5.8

Non-sprinkler-protected roof

For non-sprinkler-protected roof within 4m from the boundary (excluding boundary abutting public street, canal or river), the portion of the roof within this 4m zone shall be 1-hr fire-rated. This requirement is exempted for areas stated under Cl.3.5.7b..

Rationale

This fire safety requirement is to prevent fire from spreading through an unprotected roof to an adjacent building located outside the boundary.

The 4m setback stipulated is consistent with the minimum horizontal 5m protection required under Cl.3.5.7a.(1) to prevent vertical fire spread, taking into consideration a minimum 1m setback of the adjacent building from the boundary.

3.5.9

Separation of residential floor facade

Separation of PG II residential floor façade shall be in accordance with Cl.9.2.1b.(3).

Rationale

The fire-rated spandrel and horizontal projection from building facade are to serve as an effective fire barrier to slow down or prevent vertical fire spread. The dimensions have been validated through a fire engineering study.

3.5.10

External sun-breakers/ weather features

External sun-breakers or weather features which will result in the channelling of flame upwards during a fire are not permitted.

3.6

Separating Walls

3.6.1

Requirements of separating walls

  1. Every separating wall shall:

    1. form a complete barrier in the same continuous vertical plane through the full height between the buildings it separates, including roofs, basements, air-con ledges and balconies, and shall be without openings except where permitted Cl.3.6.2;

    2. have the appropriate fire resistance to comply with the requirements of Cl.3.3;

    3. be constructed of non-combustible materials, together with any beam and column which form part of the wall and any structure which it carries; and

    4. not include glass fire-resisting walls.

Explanations & Illustrations

Clause 3.6.1a.(1) : Requirements of separating walls

Section Figure 3.6.1a.(1) - 1 : Separating wall with flat roof
Section
Figure 3.6.1a.(1) - 1 : Separating wall with flat roof

Separating wall is the common wall that separates one house from another, as in the case of semi-detached or terraced houses. It is to prevent the spread of fire from house to house. The separating wall shall have the appropriate fire resistance rating as the elements of structure of the adjoining house having the larger floor area or cubical extent as the case may be. It shall not include fire-resisting glass.

Axonometric view Figure 3.6.1a.(1) - 2 : Separating wall with pitched roof
Axonometric view
Figure 3.6.1a.(1) - 2 : Separating wall with pitched roof

Door opening in the separating wall is to provide communication between 2 houses is not acceptable, unless the 2 houses are under single ownership and occupied by a single family. Owner is required to furnish an undertaking to the SCDF that should one of the houses is to be sold, the door opening in the separating wall shall be bricked-up to have the necessary fire resistance as the adjoining wall.

3.6.1.b
  1. Exception

    1. Cl.3.6.1a.(1) shall not apply to wall between car porches of PG I buildings or wall between canopies over private enclosed spaces located on the grade level of PG II buildings. This exception shall not apply if the unprotected opening of the car porches/ canopies fails to comply with the setback distance requirements from the other lot boundary.

    2. Cl.3.6.1a.(1) shall not apply to any sun screen or ledge that protrude from edge of the floor level.

Explanations & Illustrations

Clause 3.6.1b. : Requirements of separating walls

Figure 3.6.1b. - 1 : Scenario 1
Figure 3.6.1b. - 1 : Scenario 1

Walls between car porches (annotated by dash line) need not be separating walls provided the car porches are set back (annotated as ‘x’ above) adequately from their respective unit side boundaries.

Figure 3.6.1b. - 2 : Scenario 2
Figure 3.6.1b. - 2 : Scenario 2

Walls between car porches need to be separating walls (annotated by dash line) if the canopies span across the car porches and unit side boundaries.

Figure 3.6.1b. - 3 : Scenario 3
Figure 3.6.1b. - 3 : Scenario 3

Boundary no. 1 need not be a separating wall if the extended canopy can comply with set back to the unit side boundary as reflected above. Conversely, boundary nos. 2 & 3 need to have separating walls since the extended canopies cannot comply with set back from their respective side boundaries.

3.6.2

Openings in separating walls

A separating wall shall have no openings except for:

  1. a door required to provide a means of escape in the event of a fire, having the same fire resistance as that required for the wall and complying with Cl.3.9.2, or

  2. a door provided for the purpose of public circulation and permitted by the SCDF, having the same fire resistance as that required for the wall and complying with Cl.3.9.2, or

  3. an opening for the passage of a pipe complying with the relevant provisions of Cl.3.9.3.

Explanations & Illustrations

Clause 3.6.2b. : Openings in separating walls

Figure 3.6.2b. - 1 : Basement plan 1
Figure 3.6.2b. - 1 : Basement plan 1
Figure 3.6.2b. - 2 : Basement plan 2
Figure 3.6.2b. - 2 : Basement plan 2

Doors are provided in separating walls to connect 2 buildings for public circulation. Prior approval shall be obtained before building plans are submitted for approval. The above provision for the purpose of public circulation shall not be taken to qualify for the requirements for the provision of area of refuge.

Explanations & Illustrations

Clause 3.6.2 : Openings in separating walls

  1. Opening in the separating wall shall comply with the following conditions:

    1. QPs shall obtain prior approval from the SCDF before submission of building plan.

    2. If the adjoining unit or building is under different ownership; written consent from the owner shall be obtained for submission to the SCDF.

    3. Owners are to submit a written undertaking to the SCDF that should the opening in the separating wall is no longer required, it shall be restored to its original imperforate state.

  2. Cl.3.6.2b. is not applicable to PG VI & VIII buildings.

    Door opening between 2 industrial units is not acceptable, unless the units are owned by one owner and occupied by a single company. In such a case the door opening in the separating wall shall be used solely for providing communication between the units and shall not be taken as means of escape during fire emergency, unless otherwise allowed. The owner is to furnish an undertaking to the SCDF that should one of the units be sold, the door opening in the separating wall shall be bricked-up to have the necessary fire resistance as the adjoining wall.

3.6.3

Roof junction

A separating wall shall be either extended up to form a close joint with the underside of a pitched roof of non-combustible covering or extended up above the level of such roof covering. The junction between such separating wall and roof shall be properly fire-stopped so as not to render ineffective the resistance of such separating wall to prevent the spread of fire.

Explanations & Illustrations

Section Figure 3.6.3
Section
Figure 3.6.3

Separating wall is carried right up above the roof coverings to act as a barrier to prevent fire spread over the roof level. The above clause addresses the concern at the junction of separating walls with roofs and other elements of structure to prevent fire from spreading through cracks and gaps at such junctions.

3.6.4

External wall junction

If any external wall is extended across the end of a separating wall, such external wall and separating wall shall be bonded together or the junction of such walls shall be fire-stopped to comply with the requirements of Cl.3.12.

3.6.5

Prohibition of combustible materials in separating walls

No combustible material shall be built into, extended through, across the ends of, or over the top of separating walls in such a way as to render ineffective the resistance of such separating walls to prevent the spread of fire.

Explanations & Illustrations

Section Figure 3.6.5 - 1
Section
Figure 3.6.5 - 1
Section Figure 3.6.5 - 2
Section
Figure 3.6.5 - 2

Combustible materials built into separating wall would weaken the fire resistance integrity of the wall. Separating wall must be constructed of wholly non-combustible materials, including the beam, column or other structure carrying the wall. Exception is allowed for internal linings under Cl.3.13. However, for building under conservation, it would be acceptable if the original method of construction of floor is required to be retained.

3.7

Compartment Walls and Compartment Floors

3.7.1

Requirements of compartment walls or compartment floors

Every compartment wall or compartment floor shall be required to:

  1. form a complete barrier to fire between the compartments it separates;

  2. have the appropriate fire resistance to comply with the requirements of Cl.3.3, except for compartment which is abutting a common circulation space and not more than 3m from the eaves of the building;

  3. be constructed of non-combustible materials (together with any beam or column which forms part of the wall or floor, and any structure which it carries); and

  4. shall not have fire-resisting glass components, unless permitted under Cl.3.15.14.

Explanations & Illustrations

Section Figure 3.7.1
Section
Figure 3.7.1

The provision of compartment floor would apply to separate basement from upper storeys in the case where the building has 4 or more upper storeys or levels and a basement. Under such situation, Cl.3.2.5d. shall be complied with i.e. the compartmentation between basement and 1st storey shall not be penetrated by any openings or services even if:

  1. such openings are provided with fire doors; and

  2. the services are in protected shafts.

Compartment walls and floors are to be totally imperforate except for the following permitted openings:

  1. doors

  2. protected shafts

  3. ventilation ducts

  4. pipes

  5. chutes e.g. refuse, linen

Compartment walls and floors are to be constructed wholly of non-combustible materials, including any beam or column which forms part of the wall or floor and any structure which it carries. The walls and floors shall be constructed to have the necessary fire resistance of min. 1 hour to comply with the requirements of Cl.3.3. See Cl.3.2.5 on the provision of compartment walls and floors to apartment/maisonette unit. Provision of fire resisting glass in compartment wall or floor separating residential units is not allowed.

3.7.2

Openings in compartment wall or compartment floor

A compartment wall or compartment floor shall have no openings in it, except for

  1. a door which has the same fire resistance rating as the compartment wall and complies with the relevant requirements of Cl.3.4, unless permitted by other provisions of the Code, or

  2. a protected shaft which complies with the requirements of Cl.3.8, or

  3. the passage of a pipe or ventilation duct.

Such openings in the compartment wall or compartment floor shall be protected to comply with the relevant provisions of Cl.3.9.

Explanations & Illustrations

Figure 3.7.2 - 1 : Door opening in compartment wall
Figure 3.7.2 - 1 : Door opening in compartment wall
Section Figure 3.7.2 - 2 : Protected shaft opening in compartment floor
Section
Figure 3.7.2 - 2 : Protected shaft opening in compartment floor
Figure 3.7.2 - 3 : Fire damper opening in compartment wall
Figure 3.7.2 - 3 : Fire damper opening in compartment wall
Section Figure 3.7.2 - 4 : Pipe penetration in compartment wall
Section
Figure 3.7.2 - 4 : Pipe penetration in compartment wall

It is a common practice to provide ½-hr fire resistance entrance door to flat or maisonette from common space, e.g. lobby. The fundamental reasons are that entrance doors are subject to normal everyday usage and that it is generally accepted that no combustible materials would be placed behind the doors.

In other situation, the door within compartment wall shall have the same fire resistance as the compartment wall. This is applicable to trap doors in floors.

Compartment walls and floors are required to be totally imperforate except for the above mentioned openings to permit movement of people, air, services etc. in the building.

Other provisions in the code which allow fire door to have ½ the fire resistance rating of the adjoining compartment wall are:

  1. doors to protecting structure under Cl.3.8.6;

  2. exit doors opening into an internal and external exit passageway under Cl.2.3.2b.(3) and  Cl.2.3.2c.(2) respectively; and

  3. exit doors opening into protected lobby under Cl.2.2.13b..

Doors to protected shafts are required to have ½ the period of the fire resistance rating of the protecting structure surrounding the opening. The main reasons for the above relaxation are:

  1. Exit doors if required to have the same period of fire resistance rating as the surrounding wall would be quite heavy. Occupants escaping into the protected staircase would need to push hard to open the doors. Besides having to overcome the weight of the doors, additional force would be required to deal with the self-closing device fitted to the doors and in certain cases, the force imposed by the staircase pressurisation system. This would slow down the evacuation process;

  2. A fire that breaks into the shaft at one level would need to break out again at another level. The aggregate rating of the 2 doors, each at different level, would be considered as acceptable.

  3. Door openings in protecting structures would be limited in size, hence the potential source of weakness in the overall integrity of the shaft is limited.

In other situation, the door within compartment wall shall have the same fire resistance as the compartment wall. This is applicable to trap doors in floors.

3.7.3

Openings

  1. Junction with other structures

    Where a compartment wall or compartment floor forms a junction with any structure comprising any other compartment wall, or any external wall, separating wall or structure enclosing a protected shaft, such structures shall be bonded together at the junctions or the junctions shall be fire-stopped to comply with the requirements of Cl.3.12.

  2. Opening in curtain walling

    The opening occurring at the junction between the edge of a structural floor and the curtain walling shall be sealed to prevent the spread of smoke and flame from the lower floor to the upper floor via the opening. Materials to be used for sealing the opening shall have the requisite fire resistance rating as the elements of structure.

Explanations & Illustrations

Clause 3.7.3a. : Openings

Section Figure 3.7.3a.
Section
Figure 3.7.3a.

Clause 3.7.3b. : Openings

Figure 3.7.3b. - 1 : Details at junction of curtain walling at floor
Figure 3.7.3b. - 1 : Details at junction of curtain walling at floor
Figure 3.7.3b. - 2
Figure 3.7.3b. - 2
3.7.4

Compartment wall - roof junctions

Where a compartment wall forms a junction with a roof, such compartment wall shall be extended up to form a close joint with the underside of the roof and shall be properly fire-stopped or shall be extended up above the level of the roof covering and the junction between such compartment wall and roof shall be properly fire-stopped so as not to render ineffective the resistance of such compartment wall to the effects of the spread of fire.

Explanations & Illustrations

Section Figure 3.7.4 - 1
Section
Figure 3.7.4 - 1

Compartment wall is carried right up above the roof coverings to act as a barrier to prevent fire spread over the roof level. The above clause addresses the concern at the junction of compartment walls with roofs and other elements of structure to prevent fire spreading through cracks and gaps at such junctions.

Axonometric view Figure 3.7.4 - 2
Axonometric view
Figure 3.7.4 - 2

Compartment wall shall be brought up to the underside of the roof coverings, including jack roof to complete the fire separation and to prevent fire spread from compartment to compartment. See also Cl.3.6.3 (separating wall – roof junction)

3.7.5

Prohibition of combustible materials

No combustible material shall be built into, extended through or extended across the ends of any compartment wall or compartment floor or extended over the top of any compartment wall in such a manner as to render ineffective the resistance of such wall or floor to the effects of the spread of fire.

3.7.6

Non-combustibility of compartment walls or floors

Every compartment wall or compartment floor shall be constructed of non-combustible materials, unless permitted by the SCDF.

Explanations & Illustrations

Construction of compartment walls and floors is to be entirely of non-combustible material, except for compartment walls or floors in buildings which are required to be retained by URA under the conservation programme. The exemption was an understanding between the SCDF and URA. As a general guide, QPs are required to seek prior consultation with the SCDF before making BP submission. There are also certain other exceptions:

  1. floor finishes

  2. wall or ceiling linings complying with Cl.3.13

  3. suspended ceilings under Cl.3.3.6

Any structural members carrying compartment walls or floors must also comply with the requirement of non-combustibility. Apart from the contribution made by suspended ceilings under Cl.3.3.6, the fire resistance of the structural members must be attained without assistance from any combustible material (with the exception of buildings designated for conservation).

3.7.7

Use of fire shutter

  1. General

    A fire shutter is permitted to be used as compartment wall, except for the fire compartmentation to comply with the requirements of Cl.3.2.4b., Fire Command Centre (FCC) and means of escape, which include exit staircases, smoke-free lobbies/ fire lift lobbies, internal exit passageways, etc.

  2. Fire resistance

    The fire shutters, which are used to protect openings in compartment wall/ floor, shall have the necessary fire resistance including thermal insulation, not less than that of the compartment wall/ floor. However, fire shutters, which are installed at the edge of atria, voids such as escalator void areas and between floors, and door way, need not have thermal insulation.

Explanations & Illustrations

Clause 3.7.7a. : Use of fire shutter

Figure 3.7.7a.
Figure 3.7.7a.

The employment of fire shutter to substitute compartment wall is now permitted provided the fire shutter in-lieu of compartment wall meet stability, integrity and insulation provisions when tested to BS 476: Part 20-23. Do note that placement of combustible items around fire-rated shutter is not allowed.

Clause 3.7.7b. : Use of fire shutter

Figure 3.7.7b
Figure 3.7.7b

The fire shutters, which are installed at the edge of atrium, void facing escalator and at door way are intended as relaxation. The reason for not requiring insulated fire shutter at door way is because the opening width is basically not overly big. The conventional fire door need not be tested to conform to insulation criterion. Hence, vertical fire shutter to substitute fire door will not be required to subject to insulation provision. All habitable spaces enclosed by the fire shutter are to be provided with exit for the occupants to escape either via a side door or a wicket door.

  1. Operation

    The commonly used shutters such as vertical, horizontal and lateral fire shutters shall comply with SS 489 and the following:

    1. Vertical fire shutter operated by gravity during a fire

      Upon activation by a fire alarm system or fusible link, the operating mechanism of curtains/leaves of the vertical fire shutter shall be released. The curtain/ leaves shall descend under gravity at a controlled rate.

    2. Electrically-operated vertical, lateral and horizontal fire shutter (fusible link is not required)

      Upon activation by fire alarm system, the electrical motor shall drive the curtains/ leaves to descend and shall be backed up by emergency power supply.  The power and signal cables shall be fire-rated.

    3. Activation time and closing speed

      1. For vertical fire shutter with height not exceeding 6m, the maximum time for full closure of the fire shutter shall not exceed 30 secs from time of activation, with a descending speed not exceeding 0.2m/sec.

      2. For vertical fire shutter with height exceeding 6m and not more than 12m, the maximum time of full closure of the fire shutter shall not exceed 60 secs from time of activation, with a descending speed not exceeding 0.2m/sec.

  2. Mode of activation

    The mode of activation for fire shutters at different locations shall be as follows:

    1. Fire shutters as separating wall between two buildings (if allowed in accordance with Cl.3.6.2)

      1. Two buildings separated by a common fire shutter:

        Both gravity-operated and electrically-operated fire shutters shall be linked to the fire alarm systems of both buildings and shall be activated by the fire alarm system of either building. Activation solely by fusible link is not permitted.

      2. Two buildings separated by two separate fire shutters:

        Both gravity-operated and electrically-operated fire shutters shall be activated by the fire alarm system of its own building. Activation solely by fusible link is not permitted.

    2. Fire shutters as compartment wall/ floor for limiting compartment area and cubical extent

      Fire shutters as compartment wall/ floor for limiting compartment areas and cubical extent, as compartment between different purpose groups, as compartment of special rooms such as kitchen, electrical room, store room, etc., and as compartment of basement passenger/ goods lift lobby:

      1. For gravity-operated vertical fire shutters, activation by fusible link is acceptable.

      2. For electrically-operated fire shutters, activation shall be by local smoke detectors.

    3. Fire shutters as compartmentation at atrium/ voids or between floors (being part of the engineered smoke control design)

      Only electrically-operated fire shutters are permitted. The signal to operate the respective fire shutter shall be from a dedicated smoke detector installed at the respective smoke zone.

3.7.8

Fire safety signage for fire shutter and smoke curtain

  1. Exit directional signage marked with an arrow and the word “EXIT” shall be prominently painted/ pasted on fire shutters/ smoke curtains to redirect building occupants to the nearest exits if the activated shutters visually obscure the building exit and/ or directional signs. The sign shall be reflective and the letters at least 100mm in height. 

  2. Signage for alerting persons not to impede the operation of fire shutters/ smoke curtains shall be permanently displayed at prominent locations and suitable intervals close to the descending paths of the fire shutters/ smoke curtains. The lettering of the sign shall be at least 25mm high in a colour contrasting with the background and states the following where applicable:

    1. “FIRE SHUTTER – KEEP CLEAR”

    2. “SMOKE CURTAIN – KEEP CLEAR”

Rationale

The additional exit directional signage on the fire shutters/smoke curtains is to guide occupants to the nearest exits as the lowered fire shutters/smoke curtains may block the building exit and/or directional signs during an fire emergency.

3.7.9

Emergency generator room

  1. An emergency generator room shall be compartmented as stipulated under Table 6.4A.

  2. An emergency generator can be located in an external space provided:

    1. the setback distance between the outdoor emergency generator from other surrounding hazards except water tank shall be at least 3m; and

    2. if there is more than one outdoor emergency generator, each outdoor emergency generator shall be separated from the other by a dividing wall of masonry construction for the full length and height of the adjacent outdoor emergency generator.

Rationale

The requirements is to ensure that emergency generators located outdoors are adequately protected from by any nearby fire which may affect their operation during an fire emergency.

3.8

Protected Shafts

3.8.1

Purpose of protected shaft

A protected shaft shall not be used for any purpose additional to those given as defined under Cl.1.4.85. All services such as, pipe/duct installation shall not be located inside a protected staircase,unless otherwise permitted in Cl.3.8.7. Likewise, no washroom is allowed to be located inside an exit staircase.

Explanations & Illustrations

The purposes of providing protected shaft are to delay or prevent the spread of fire between compartments through which staircases or other shafts pass directly and to enable people or things or air to pass between compartments. The purpose of each shaft are as follows:

  1. The staircase shaft is a vertical shaft which enables the passage of
    movements of people.

  2. The service shaft enables the passage of cable, building service ducts/pipes.

  3. The lift shaft enables the movements of lift cars.

“Protected Shafts” include staircase, lift shafts, chutes, ducts or any other shaft enabling movement of people, goods, air, pipes, etc..

Protecting structures shall be treated as elements of structure for the purpose of determining the period of fire resistance rating.

Construction of compartment walls and floors shall be constructed entirely of non-combustible material. However, there were exceptions specially allowed for under the conservation programme. The exemption was an understanding between the SCDF and URA. As a general guide, QPs are required to seek prior consultation with the SCDF before making formal building plan submission.

Any structural members carrying compartment walls or floors must also comply with the requirement of non-combustibility. Apart from the contribution made by suspended ceilings under Cl.3.3.5, the fire resistance of the structural members must be attained without assistance from any combustible material (with the exception of buildings designated for conservation).

3.8.2

Requirements of protected shaft

Every protected shaft shall be required to:

  1. form a complete barrier to fire between the different compartments which the shaft connects;

  2. have the appropriate fire resistance to comply with the requirements of Cl.3.3; and

  3. be constructed of non-combustible material (together with any beam or column which forms part of the enclosure and any structure which carries it).

Explanations & Illustrations

Figure 3.8.2 - 1
Figure 3.8.2 - 1

Protected shafts penetrate across compartments or floors in a building. They can be shafts carrying utilities (piping, electrical and telecommunication cables etc.) or service shafts carrying lifts and exit staircases. The enclosing walls and floors to the protected shaft shall be constructed of non-combustible materials, including any beam or column, which forms part of the enclosure.

In the above figure, a protected shaft is enclosed at the top by roof slab, the sides by fire-rated walls and the bottom by the ground floor slab. The protecting structures to the shaft would exclude the roof slab, which is exposed to the external, the ground floor slab, which is in contact with the ground and any compartment wall, which separates one compartment from another.

Figure 3.8.2 - 2
Figure 3.8.2 - 2

Protected shaft is enclosed by internal walls, ceiling and floor. Protecting structures will include the walls and slab above; and the floor at the base of shaft is excluded, because it is a compartment floor.

Figure 3.8.2 - 3
Figure 3.8.2 - 3

Protected shaft is located against an external wall. The protecting structures will include internal walls, which are not compartment or separating wall.

Where the protection afforded to a compartment is penetrated to allow the movement of people, goods or anything else between compartments by means of e.g. a staircase, lift or duct, the protection to the compartment must not be lowered or diminished. This is achieved by enclosing the means of transportation from one compartment to another in a protected shaft which is so constructed that any penetration of the enclosures to the shaft poses no direct or indirect threat to the compartments connected by the shaft. Hence, the term “protected shaft” and “protecting structure” for the structure enclosing such a shaft. The elements enclosing the shaft (unless formed by adjacent external walls) are compartment walls and floors.

The above figure illustrates a shaft, which is enclosed by compartment or separating wall, external wall and internal walls called protecting structure. The fire resistance of the compartment or separating wall should be based on the size of the floor area or cubical extent of the adjoining larger compartment and shall not be less than 1 hour.

The fire resistance of the external wall would be determined by the separation distance requirements under Cl.3.5. The external wall is not a protecting structure and could be fully unprotected areas having no fire resistance. The remaining 2 walls of the shaft are protecting structure which must be imperforate except for certain permitted openings, e.g. inspection doors which need to have fire resistance equivalent to half that of the protecting structure. All protecting structure shall be constructed of non-combustible material except for surface linings, which shall comply with Cl.3.13. The fire resistance of the protecting structures shall be that for the elements of structure of the building.

Protecting structures exclude external wall. External walls need not have fire resistance rating, subject to complying with Cl.3.5 to be unprotected areas.

3.8.3

Openings in protected shaft

  1. A protected shaft shall have no openings in its enclosure, except in the case of any part of the enclosure:

    1. which is formed by a separating wall, any opening which complies with the requirements of Cl.3.6 for separating walls, or

Explanations & Illustrations

Clause 3.8.3a.(1) : Openings in protected shaft

Figure 3.8.3a.(1)
Figure 3.8.3a.(1)

Protected shaft bounded on three sides by protecting structure and fourth side by an external wall. Permitted opening to each unit shall be protected by a door of at least one half of the fire resistance rating of the enclosing wall, or half an hour, whichever is the greater. The aggregate fire resistance of the 2 doors shall not be less than the fire resistance of the protecting structure.

  1. -

    1. which is formed by a compartment wall or a compartment floor, any opening which complies with the requirements of Cl.3.7 for compartment wall or compartment floor, or

    2. which is formed by the protecting structure:

      1. a door which has the appropriate fire resistance to comply with the requirements of Cl.3.4 for test of fire resistance, or otherwise permitted by provision of Cl.3.8.6, or

      2. the passage of a pipe, excluding protecting structure to exit staircase and exit passageway, or

      3. inlets to and outlets from and opening for the duct, if the shaft contains or serves as a ventilation duct.

Explanations & Illustrations

Clause 3.8.3a.(3) : Openings in protected shaft

Figure 3.8.3a.(3) - 1
Figure 3.8.3a.(3) - 1
Figure 3.8.3a.(3) - 2
Figure 3.8.3a.(3) - 2
Figure 3.8.3a.(3) - 3
Figure 3.8.3a.(3) - 3

Fire resisting doors to comply with Cl.3.9.2 and shall have ½-hr fire resistance or half the resistance of the enclosing walls, whichever is the greater:

  1. Any opening in compartment floor/wall would constitute a break in compartmentation. Therefore even small service pipes, strictly speaking must be enclosed in protected shaft.

  2. However, Cl.3.9 allows pipe size not greater than those sizes provided in Table 3.9A to be unprotected, provided the pipes are to be spaced at min. 50mm apart or half the diameter of the larger pipe, whichever is larger. This is to avoid clustering of pipes which would weaken the compartment floor or wall

  3. Openings in compartment floors to accommodate staircases, lifts and services form a vertical shaft which can become a ready means of passage of fire from one storey to another, accentuated by the flue effect created by a fire.

  4. Hence, protected shafts are needed to maintain the overall fire integrity of the building. However, these shafts need to have door openings for movement of people, e.g. staircase,  lifts and maintenance purposes in the case of shafts containing services. All the door openings to protected shaft are considered the sources of weakness in the integrity of the shafts and they must be protected.

  5. Door openings

    Doors in protected shaft must have at least ½-hr fire resistance rating or half the fire resistance of the protecting structure whichever is greater.

    Such a relaxation from the full standard of fire integrity is reasonable as it is expected that combustible materials would not be placed next to the door and that a fire has to break into the shaft and break out again at the upper level. Also if the top of the shaft is adequately ventilated, the tendency for lateral spread is considerably reduced.

  6. The primary purpose of protecting structure is to provide the compartmentation between floors. As such the structure shall have full fire resistance as the elements of structure. The relaxation on fire resistance accorded to fire doors shall not be extended to the protecting structure i.e. halve the fire resistance of the elements of structure. The main reason is that by halving the fire resistance of protecting structure, the threat of failure and collapse of the enclosing walls would be greater in times of fire emergency and should the walls collapse, large opening would be created in the shaft to permit the spread of fire and smoke, which is not acceptable. As to door openings in protected shaft, the eventual failure of the fire door is considered acceptable owing to the limited door opening size. See illustrations (c) and (d) [Figure 3.8.3a.(3) - 3].

  7. Ventilation ducts

    Ventilation ducts are usually constructed of sheet metal, which do not have fire resistance and therefore should a fire occur, they will quickly distort and collapse leaving a hole in any wall through which they pass. Conversely, a fire occurring in the duct could also cause collapse.

    Therefore, where the duct penetrates the protected shaft, a fire damper should be fitted at the opening of the protecting structure. The fire damper shall be capable of sealing the opening in the protecting structure and be installed independently of the duct trunking. In this way, the fire damper would not be affected by collapse of duct work and be able to maintain the fire integrity of the shaft. See illustration (a) [Figure 3.8.3a.(3) - 1].

  8. Pipes

    Where pipes are contained within a protected shaft, the problem of maintaining the integrity of the fire compartment is made simple, irrespective whether the pipes are made of UPVC or combustible materials. However, for gas pipes or pipes containing combustible liquids, they shall be located in separate shafts.

  9. The construction of gas pipes shaft is different from other shafts owing to the need to provide through or external ventilation. Gas pipe shaft shall comply fully with SS CP 51. See illustration (b) [Figure 3.8.3a.(3) - 2].

  10. General

    In order to maintain the level of integrity of protected shafts, openings in protected shafts shall be restricted to the following:

    1. Openings for pipe

    2. Door openings to lift shaft, staircase

    3. Openings for ventilation ducts

    4. Access openings for electrical cables shaft

    5. Openings for chutes, linen or refuse

  1. Such openings in the protected shaft shall be protected to comply with the relevant provisions of Cl.3.9 for protection of openings.

3.8.4

Non-combustibility of protecting structures

Every protecting structure shall be constructed wholly of non-combustible materials except that floor, wall and ceiling finishes which do not contribute to the fire resistance of such protecting structure are not be required to comply with the requirements for non-combustibility.

Explanations & Illustrations

The requirement that all protecting structure shall be constructed of non-combustible materials is also spelled out under Cl.3.8.2. As to the provision of combustible finishes to floor, wall and ceiling, it must be observed that such provision will not be permitted inside protected shafts that are used for the passage of people such as exit staircases and exit passageways under Cl.3.10.4 and Cl.3.13.6.

3.8.5

Ventilation of protected shaft

Ventilation of protected shaft shall comply with the following:

  1. A protected shaft used for the passage of people, such as exit staircases, shall be ventilated to comply with the relevant provisions of the Code.

  2. A protected shaft containing a pipe conveying gas shall be adequately ventilated directly to the outside air or have other modes of ventilation allowed under SS 608.

Explanations & Illustrations

Protected shaft used for passage of people, such as exit staircases shall be provided with adequate natural ventilation by fixed openings in the external walls. Such openings shall have an area of not less than 10 percent of the floor area per floor of the staircase. Alternatively, the staircase can be mechanically ventilated under Cl.2.3.3d.(7). However, for internal exit staircase serving more than 4 storeys, the supply air shall be mechanically conveyed via a vertical duct extending through the staircase height and discharging from outlets distributed at alternate floor. Where the internal exit staircase exceeds 24m in height without provision for natural ventilation, the staircase shall be pressurised in accordance with Cl.2.3.3d.(8).

The mechanical ventilation system to internal staircase serving more than 4 storey and the pressurisation system to internal exit staircase exceeding 24m shall be connected to emergency power supply. In addition, a remote manual start-stop switch shall be make available to firefighters at the fire command centre, or at the fire indicating board where there is no FCC. The start-stop switch provides the firefighter a quick means to shut-off the fans should it be detected that smoke had been drawn into the staircase by the fresh air supply fan.

A protected shaft conveying piped flammable gas should be adequately ventilated directly to the outside air by ventilation openings at high and low level in the shaft or comply with the modes of ventilation allowed in SS 608. All gas pipe installations shall be vetted and approved by acceptable organisation (e.g. Powergas) before any works can be carried out on site.

3.8.6

Doors in protecting structures

  1. Any door fitted to an opening in protecting structure shall have fire resistance for not less than half the period required by other provisions of the Code for the protecting structure surrounding the opening.

  2. Exception

    1. Any door fitted to an opening in protecting structure of a shaft containing services, such as electrical cables, pipes (including gas pipe in separate shaft), ducts etc., is not required to have the fire resistance rating if the door is located along the wall facing the external corridor.

    2. Any metal door fitted to an opening in protecting structure of a rubbish/ bin chute is not required to have the fire resistance rating if:

      1. the thickness of the rubbish/ bin chute door is at least 1.5mm;

      2. the rubbish/ bin chute door is sealed with rubber gasket; and

      3. the rubbish/ bin chute door shall be self-closing type.

  3. Any door fitted to an opening in protecting structure of a shaft containing services, such as electrical and telecommunication cables, pipes (including gas pipe in separate shaft), ducts etc., is not required to comply with the requirements in Cl.2.3.9d.(2) if it is fitted with a self-closing device. Rising mains and hose reel doors shall not be fitted with self-closing device and shall comply with the stipulated corridor width when the door is in its fully opened position. Areas within the swing paths of the rising mains and hose reel doors shall be clear of any obstruction/ storage at all times.

Explanations & Illustrations

Figure 3.8.6 - 1
Figure 3.8.6 - 1

As the doors in the electrical and pipe shafts are opening into an external corridor which is naturally ventilated, there is no need to fire rate the doors.

Protected shaft A serves 2 compartments. Compartment A could be a common area e.g. lounge and compartment B in factory/warehouse unit.

Door A1 is opening in the direction of exit travel, whereas door A2 is the entrance door of the factory/warehouse unit, which swings inward. The number of exit door openings in a protected shaft containing an exit staircase shall not exceed two per floor. This is to prevent additional openings from weakening the integrity of the protecting structure.

The aggregate fire resistance of door A1 and A2 shall not be less than the compartment wall or the protecting structures to the shaft. This is to ensure that the fire resistance between compartment A and B is not reduced at the door openings.

Door A1 can be held in the open position provided it is fitted with electromagnetic or electromechanical device. See Cl.1.4.34.

All doors in shaft A & B shall have the fire resistance rating of half that of the enclosing protecting structures to the shafts, but shall never be less than half hour. See also Cl.3.8.3 for further explanation.

Figure 3.8.6 - 2
Figure 3.8.6 - 2

Protected shaft A serves 2 compartments. Compartment A could be a common area e.g. lounge and compartment B in an office unit.

All doors in shaft A & B shall have the fire resistance rating of half that of the enclosing protecting structures to the shafts, but shall never be less than half hour. See also Cl.3.8.3 for further explanation.

Door A1 is opening in the direction of exit travel, whereas door A2 is the entrance door of the health care occupancy unit, which swings inward. The number of exit door openings in a protected shaft containing an exit staircase shall not exceed two per floor. This is to prevent additional openings from weakening the integrity of the protecting structure.

The aggregate fire resistance of door A1 and A2 shall not be less than that of the compartment wall or the protecting structures to the shaft. This is to ensure that the fire resistance between compartment A and B is not reduced at the door openings.

Door A1 can be held in the open position provided it is fitted with electromagnetic or electromechanical device. See Cl.1.4.34.

3.8.7

Protected shaft containing exit staircase

  1. A protected shaft which contains an exit staircase shall not contain any services e.g. pipes, cables, ducts, etc., that are not solely serving the same exit staircase (even if the services are protected with fire-rated dry construction), except for:

    1. cut-off sprinkler and pipe for that staircase;

    2. UPVC or cast iron rain water downpipes serving the roof directly above the exit staircase, and not routed through anywhere outside the staircase;

    3. rising mains;

    4. metal water supply pipe and water tap not exceeding 50mm in nominal diameter; and

    5. access control systems (comprising facial recognition camera, manual override mechanism, CCTV, etc.) installed inside naturally ventilated exit staircase for the exit door to allow restricted access to the roof level shall comply with all of the following:

      1. Cables shall be housed in metal conduits.

      2. Electrical components installation in accordance with SS 638.

Explanations & Illustrations

Clause 3.8.7a. : Protected shaft containing exit staircase

Figure 3.8.7a.
Figure 3.8.7a.

A fire lift and fire lift lobby in a building, which exceeds 24m in habitable height, have to be complemented by an exit staircase adjacent to them. Separate ventilation shafts are required to be provided for the staircase and fire lift lobby as depicted in Cl.7.1.10.

Exit staircases serving any building irrespective of the height, shall be devoid of combustible wall, floor and ceiling finishes. Building services which are not solely serving the exit staircase shall not be allowed to be routed through or inside the staircase. This is to prevent any possibilities of a fire occurring inside the staircase and the spread of fire into the staircase via the services such as electrical cables, ducts, combustible pipes, etc.. Cl.6.2.2 of the Fire Code allows vertical stack of rising main and landing valve to be located inside the staircase as a last resort where smoke-stop lobby and common area outside the staircase are not available. SS CP 10 allows sub-alarm panels to be located in the exit staircase provided there is no fire lift lobby or smoke-stop lobby in the building. The fire alarm cables shall be in metal conduit or trunking. This relaxation shall not apply to buildings which are more than 4 storeys in height where provision of smoke-stop lobby is a requirement.

The exit staircases are the means of escape in fire emergencies. All occupants must use the staircases to evacuate safely from any storey level to the final exits at ground level. The time taken to descend a staircase in a high-rise buildings could be more than an hour. With the staircase fully packed with evacuating occupants during an emergency, the staircase must be maintained safe from smoke, heat and fire throughout the fire resistance period of the enclosing protecting structures to the staircase. An exception is allowed under Cl.3.8.9d. for maximum 4 storey residential building.

  1. The protecting structure shall be constructed of masonry, or drywall. If drywall construction is used, all of the following conditions shall be complied with:

    1. the drywall shall be non-combustible;

    2. the drywall shall have fire resistance rating for not less than the relevant period specified in Table 3.3A having regard to the purpose group of the building of which it forms a part and the dimension specified in that table;

    3. the drywall shall, in terms of impact & deflection performance, meet the partition grade specified under BS 9999 (Test for partitions) in accordance with BS 5234-2;

    4. the drywall shall meet the criteria, in terms of water absorption and bending strength performance, when subject to the test of BS EN 520 or ISO 1896; and

    5. the building shall have at least two independent exit staircase shafts (scissors exit staircases are considered single shaft).

Explanations & Illustrations

Clause 3.8.7b. : Protected shaft containing exit staircase

Figure 3.8.7b. - 1
Figure 3.8.7b. - 1

Building designed with single exit staircase shall have the protecting structure constructed of masonry, which is more solid and stable than fire-rated dry walls. The main concern is that if the protecting structure, which is constructed of dry wall is damaged, smoke and heat would get into the staircase to affect the evacuees making their way down. Single exit staircase shall have its protected structure constructed of masonry.

Figure 3.8.7b. - 2
Figure 3.8.7b. - 2

Where two independent staircases are provided, the protecting structure to each of the staircase can be constructed of drywall.

Figure 3.8.7b. - 3
Figure 3.8.7b. - 3

Where a building is designed with a pair of scissors staircases to meet the provision of exit requirements, the scissors staircases shall be considered as within a common shaft if drywall is used for the construction of the protecting structure. The main reason is that if one of the shaft is damaged, the other shaft is likely to be affected, thereby causing smoke to get into both staircases. This would render the pair of scissors staircases inaccessible. In addition, the drywall enclosures are prone to other damages, thus affecting the effectiveness and integrity of the protected shafts. However, for the purpose of exit computation, the pair of scissors staircases shall literally be taken as 2 staircases though it could only qualify as a single shaft.

Figure 3.8.7b. - 4 : Drywall construction
Figure 3.8.7b. - 4 : Drywall construction

Non-combustible steel studs, insulation materials and fire-rated boards shall be used for the construction of drywall.

3.8.8

Lift shaft

A protected shaft which contains a lift shall comply with the following:

  1. It shall not contain any pipe conveying gas or combustible liquid, other than those in the mechanism of a hydraulic lift.

Explanations & Illustrations

Clause 3.8.8a. : Lift shaft

Section Figure 3.8.8a. - 1 : Protected shaft for electrical lift
Section
Figure 3.8.8a. - 1 : Protected shaft for electrical lift

Lift shaft which is not located at the edge of atrium floors or at the external wall outside the building shall be constructed of masonry.

Cl.3.8.8a. specifically permits combustible liquid in the mechanism of hydraulic lift. The liquid is concealed in vessels and forms part of the mechanical system to permit the homing of the lift during an emergency. The liquid has a high flash point of over 400°C.

Section Figure 3.8.8a. - 2 : Protected shaft for hydraulic lift
Section
Figure 3.8.8a. - 2 : Protected shaft for hydraulic lift

Lift shaft, which is not located at the edge of atrium floors or at the external wall outside the building, shall be constructed of masonry.

Cl.3.8.8a. specifically permits combustible liquid in the mechanism of hydraulic lift. The liquid is concealed in vessels and forms part of the mechanical system to permit the homing of the lift during an emergency. The liquid has a high flash point of over 400°C.

  1. The protecting structure shall be constructed of masonry, or drywall. If drywall construction is used, the conditions stipulated under Cl.3.8.7b.(1) to (5) shall be complied with. The drywall shall also meet the criteria of cyclic loading and dynamic test as specified under Cl.3.3 of the National Construction Code of Australia C 1.8.

  2. Where a lift is either located at the edge of atrium floors or at the external wall and outside the building, the lift shall be considered as not enclosed within a protected shaft.

Explanations & Illustrations

Clause 3.8.8c. : Lift shaft

Section Figure 3.8.8c. - 1
Section
Figure 3.8.8c. - 1

In the above figure the lift is unenclosed and being located within the atrium void. There is no penetration of any compartment floor and smoke migration caused by the ‘piston-effect’ of lift movement is no longer a concern. Smoke from a fire in any occupancy floor will flow from the ceiling layer into the atrium void where it will tend to rise upwards due to its natural buoyancy. A smoke control system would eventually extract the smoke out of the building.

Section Figure 3.8.8c. - 2
Section
Figure 3.8.8c. - 2

The lift is sited outside the external wall of the building. There is no concern of smoke and heat being transferred from floor to floor. Hence it is not required to be enclosed in a protected shaft. This type of lift is commonly known as ‘bubble lift’ or ‘sky lift’.

Section Figure 3.8.8c. - 3
Section
Figure 3.8.8c. - 3

The above figure shows that the lift is located away from the atrium void. As the lift punctures through the compartment floors, it must be enclosed in a protected shaft to prevent the spread of smoke and heat from floor to floor.

  1. The protected shaft shall be vented in accordance with SS 550. The vents shall be so arranged as to induce exhaust ventilation of the shaft. Where vents cannot be provided because of the location of the lift shaft, a ventilation duct protected by drywall complying with Cl.3.8.7b. serving as ventilation of the shaft may be provided instead.  If the duct is not fire-rated, fire dampers shall be provided to the duct at the wall of the lift shaft, provided such relaxation shall not apply to shafts containing a fire lift.

  2. Openings for the passage of lift cables into the lift motor room located above or at the bottom of the shaft shall be as small as practicable.

Explanations & Illustrations

Clause 3.8.8d. : Lift shaft

Figure 3.8.8d. - 1
Figure 3.8.8d. - 1
Figure 3.8.8d. - 2
Figure 3.8.8d. - 2

All lift shafts shall be vented at the top in accordance with SS 550. In situations, where the lift shafts could not be brought above the roof as shown in Figure 3.8.8d. – 2, horizontal fire rated duct could be used to provide air relief to the lift shaft. If the duct is not fire rated, appropriate fire damper could be provided in the wall of the protected lift shaft as shown ‘A’ in the above diagram. The above relaxation shall not be applicable to fire lift.

  1. Fire resistance

    1. A transom panel above the lift entrance shall be considered as part of the protecting structure and shall therefore conform to the fire resistance requirements of the protecting structure.

    2. In the case of motor-room-less lifts, the lift control panel enclosure located at the lift lobby shall not affect the fire resistance requirements of the protecting structure.

Explanations & Illustrations

Clause 3.8.8f. : Lift shaft

Section Figure 3.8.8f.
Section
Figure 3.8.8f.

Floor indicator panel should be surface mounted. If it is built into the transom panel, care should be taken to ensure that the fire resistance of the panel is not lowered. It is a common mistake to puncture the transom panel to receive the floor indicator panel without giving consideration to the fire integrity of the panel. Such practice contravenes the above requirement, as Cl.3.8.2 requires that the protecting structure, including the transom panel, forms a complete barrier and should have the appropriate fire resistance rating.

  1. If it serves any basement storey, it shall be enclosed by  a protected lobby with walls having 1-hr fire resistance rating and fire door of ½-hr fire resistance rating. If the protected lobby also acts as a smoke-free lobby required under Cl.2.2.13, it shall be mechanically ventilated in accordance with Cl.7.1.10.

    Exception:

    1. Where the lift landing area is adjoining an air well or external space of minimum clear area 10m² and minimum width of 3m, the distance between the nearest edge of lift door opening to the air well shall not exceed 3m.

    2. Where the basement storey forms part of a building under PG I or a single household cluster housing compartment within a PG II development and has a basement area not exceeding 100m².

Explanations & Illustrations

Clause 3.8.8g. : Lift shaft

Figure 3.8.8g. - 1
Figure 3.8.8g. - 1

Lift opening into basement and not adjoining a void that opens to the sky or any external spaces, shall be provided within a smoke-stop lobby having 1-hr fire-rated enclosures and ½-hr fire door.

The smoke-stop lobby acts as a buffer zone to prevent smoke from being drawn into the lift shaft through the ‘piston-effect’ of the movement of the lift.

Figure 3.8.8g. - 2 : Basement floor plan
Figure 3.8.8g. - 2 : Basement floor plan

Lift opening into basement storey and adjoining a void opening to the sky or any external spaces does not require a smoke-stop lobby. Smoke occurring in the vicinity of the lift would be drawn into the void and vented upward into the open space. This provision would help to reduce the chance of smoke being sucked into the lift shaft.

  1. Private lift

    A private lift that is provided for the exclusive use of occupants in residential buildings under PG II shall comply with all of the following requirements:

    1. A smoke detector shall be provided at the lift landing area. The activation of any of the smoke detectors at the lift landing area shall cause the lift to home to the designated floor.

    2. Emergency power supply from a standby generating plant shall be provided to home the lift to the designated floor when there is a power failure in the building.

    3. An alternate designated floor (e.g., any other floor with common lobby) shall be identified. The lift shall be brought to the alternate designated floor in the event that there is a fire at the 1st storey designated floor. For buildings without an alternate designated floor, the lift shall return to the last called floor in the event that the designated floor is on fire.

    4. The lift shall not serve as a fire lift.

    5. Private lifts shall comply with SS 550.

Explanations & Illustrations

Clause 3.8.8h. : Lift shaft

Figure 3.8.8h. - 1 : Private lift
Figure 3.8.8h. - 1 : Private lift
Figure 3.8.8h. - 2
Figure 3.8.8h. - 2

Rationale

Clause 3.8.8h.(3)

This requirement is to ensure that a private lift will not home to the designated floor if it is on fire. For residential buildings having private lifts and are unable to provide an alternate designated floor, the lift control has to be programmed to bring the passengers to a safe floor, normally the last called floor, for egress if the fire is on the designated floor.

3.8.9

Protected shaft containing other services installations

A protected shaft used for the enclosure of services shall comply with the following:

  1. The protecting structure for a protected shaft, containing mechanical ventilation ducts serving areas specified in Cl.5.2.1g.(1) and Cl.5.2.1h. or kitchen exhaust ducts, which pass through floor slabs, shall be of masonry construction. Such a shaft shall be completely compartmented from the rest of the shaft space containing other ducts or any other services installations. A protected shaft containing ducts serving other areas which pass through floor slabs can be constructed of drywall. If the protected shaft is of drywall construction, the conditions stipulated in Cl.3.8.7b. shall be complied with.

Explanations & Illustrations

Clause 3.8.9a. : Protected shaft containing other services/installations

The protecting structure for protected shaft containing kitchen exhaust duct and mechanical ventilation ducts which pass through one or more floors and serving areas such as:

  1. Exit staircases and exit passageways

  2. Smoke-stop and fire lift lobby

  3. Areas of refuge within the same building

  4. Emergency generator

  5. Engine driven fire pump

shall be constructed in masonry. Each shaft shall be separately compartmented from one another. Protected shaft containing ducts serving other areas not mentioned above and which pass through two or more floors can be constructed of fire-rated materials, instead of masonry.

Figure 3.8.9a. - 1
Figure 3.8.9a. - 1
Section Figure 3.8.9a. - 2
Section
Figure 3.8.9a. - 2

Kitchen exhaust duct shall be in a separate compartment from that for a mechanical ventilation duct. Kitchen exhaust ducts serving different kitchens shall be in separate shafts. Mechanical ventilation duct serving the area of refuge shall be in different shaft from that serving the pump room. The main reason for separate shafts is to prevent smoke and fire spread from shaft to shaft.

Figure 3.8.9a. - 3
Figure 3.8.9a. - 3
  1. In the above figure, the roof is not considered a floor slab, as it is exposed to the external air. Hence, the flue or duct does not pass through the floor. (See Kitchen 2)

  2. When the flue or duct passes through one or more floors (any floor), it shall be encased in masonry material to ensure stability and prevent mechanical damage. (See Kitchen 1)

Figure 3.8.9a. - 4
Figure 3.8.9a. - 4

Kitchen exhaust shaft for each kitchen is completely separated. The horizontal run of the exhaust from kitchen 1 is protected with fire-rated material.

Figure 3.8.9a. - 5
Figure 3.8.9a. - 5

If a flue, or duct containing flues or appliance ventilation duct(s), passes through a compartment wall or compartment floor, or is built into a compartment wall, each wall of the flue or duct should have a fire resistance of at least half that of the wall or floor in order to prevent the by-passing of the compartmentation.

  1. Cavity barriers

    A protected shaft used for the enclosure of electrical power services shall be interrupted at every floor level with at least ½-hr fire resistance cavity barriers. Protected shaft used for the enclosure of telecommunications services shall be interrupted by at least ½-hr fire resistance cavity barriers at vertical intervals not exceeding 15m. The cavity barriers within trunking enclosing electrical and telecommunication cables can be exempted if the following conditions are met:

    1. the cables shall be flame retardant type complying with IEC 60332;

    2. the floor within the shaft shall be sloped upward with an angle of at least 45° to the floor level; and

    3. the fire doors to the protected shaft are installed with self-closing devices.

Explanations & Illustrations

Clause 3.8.9b. : Protected shaft containing other services/installations

Section Figure 3.8.9b. - 1
Section
Figure 3.8.9b. - 1

Protected shaft containing electrical cables shall be interrupted at every floor with cavity barrier having min. ½-hr fire rating to prevent vertical spread of fire and smoke. The main concern is that cables are a source of fuel and ignition. The presence of fire stopping at every floor would help to confine fire to a single storey or segment of the shaft.

Section Figure 3.8.9b. - 2
Section
Figure 3.8.9b. - 2

Protected shaft containing telecommunications cables including cable TV lines is provided with cavity barrier at vertical intervals not exceeding 15m or 3 storeys whichever is the shorter. The cables are mainly of low voltage and hence of a lower risk when compared to electrical cables.

Rationale

Clause 3.8.9b

Owing to the difficulty in fire-stopping the gaps within the trunking running through multiple floor levels within a protected shaft, this requirement was exempted provided additional fire safety requirements are complied with. These requirements include the use of flame retardant cables to reduce the possibility of fire from occurring/spreading, sloping of the floor within the shaft upwards at an angle of at least 45° to prevent illegal storage of any combustible materials, and the provision of self-closing devices to the fire resisting doors to ensure that the doors are closed at all times to prevent fire from spreading.

  1. Self-closing devices

    Automatic self-closing devices are not required to be installed on fire resisting doors opening into protected shafts which are interrupted by at least ½-hr fire resistance cavity barriers at every floor level, or protected shafts containing sanitary pipes or water pipes, provided that the fire resisting doors are kept closed and locked at all times.

Explanations & Illustrations

Clause 3.8.9c. : Protected shaft containing other services/installations

Figure 3.8.9c.
Figure 3.8.9c.

Provision of self-closing device for the inspection door of a protected shaft, which is interrupted by barriers having ½-hr fire resistance at every floor, is not required. The above relaxation is also applicable to telecommunication cable shafts, provided they are interrupted by  barriers with fire resistance of at least ½ hour at every floor level.

An important point to note is the depth of the shaft which shall not exceed 750mm. If it exceeds 750mm, the shaft would be considered as a room and provision of self-closing device for the fire door becomes a necessity. The above relaxation is based on the understanding that it is unlikely that a shaft would be converted to a store if  its depth is less than 750mm and that the door would normally be kept in the locked position when workmen are not carrying out servicing work. Also, maintaining the door in locked position is the responsibility of the management corporation of the estate.

  1. Siting of protected shafts

    All protected shafts containing services shall not be located within an exit staircase except for the case of residential apartment/ maisonette development under PG II not exceeding 4-storey where smoke-free lobby is not required

Explanations & Illustrations

Clause 3.8.9d. : Protected shaft containing other services/installations

Figure 3.8.9d. - 1
Figure 3.8.9d. - 1
Figure 3.8.9d. - 2
Figure 3.8.9d. - 2

Protected shafts such as for lift, TAS/Elect/Water/Cables are permitted to be located within a protected shaft containing an exit staircase for buildings under PG II, provided:

  1. that building does not exceed 4 storeys where provision of smoke-stop lobby is not a requirement; and

  2. that no shaft shall contain pipes carrying gas or combustible liquids. The above exception is only applicable to low-rise buildings where provision of smoke-stop lobby is not a requirement and that the staircase would be naturally ventilated. However, where there is availability of common area, such services shall be located outside the staircase shaft, see Figure 3.8.9d. – 2.

Figure 3.8.9d. - 3
Figure 3.8.9d. - 3

A factory or warehouse building which does not require the provision of smoke-stop lobby to exit staircase by virtue of its height shall be required to comply fully with the above requirement. All protected shafts containing services are located in a common lobby adjoining the exit staircase.

Figure 3.8.9d. - 4
Figure 3.8.9d. - 4

Although the services are enclosed in protected shafts, they are not permitted to be located in exit staircase. The main reasons are:

  1. Within the protected shaft, the combustible materials e.g. Cables PVC pipes are source of fire risk. A fire could originate from these combustible materials and spread into the exit staircase enclosure.

  2. Exit staircase is a dedicated route for escape of occupants, services which are not serving the staircase shall not be located inside the enclosure.

3.9

Protection of Openings

3.9.1

Application

The provisions of this Clause concern the protection of openings permitted in elements of structure or other forms of fire resisting construction, which are required to act as a barrier to fire and smoke.

Explanations & Illustrations

For functional purposes, openings in compartment walls, floor etc. are required in buildings to allow movement of people and the installation of services such as pipes, ventilation ducts etc.. To prevent the spread of fire and smoke, such openings shall be appropriately protected.

3.9.2

Fire doors

  1. Fire doors shall have the appropriate fire resistance as required by relevant parts of the Code.

Explanations & Illustrations

Clause 3.9.2a. : Fire doors

Figure 3.9.2a. - 1
Figure 3.9.2a. - 1

The two 1-hr fire door arrangement is deemed to satisfy compartmention and be equivalent to the fire resistance rating of the compartment wall (2 hours).

Figure 3.9.2a. - 2
Figure 3.9.2a. - 2

The provision of fire doors shown in the above figure usually occur in separating walls, compartments e.g. hotel guestrooms or protecting structures / dormitories, hostel bedrooms or protecting structures. The 2 doors shall be independent of each other and having its own door frame. However, the 2 doors may share the same door frame only if that set of door is tested to achieve the required rating. This arrangement shall not form part of the escape exit route.

  1. All fire doors shall be fitted with an automatic self-closing device which is capable of closing the door from any angle and against any latch fitted to the door. The omission of a self-closing device to the bolted door leaf of a two-leaf door is acceptable if the door is the entrance door to a residential unit under PG II.

Explanations & Illustrations

Clause 3.9.2b. : Fire doors

All fire doors are required to be fitted with an automatic self-closing device which shall not include rising butt. Self-closing device is not required to be fitted to doors of protected shafts having a depth of not more than 750mm under Cl.3.8.9c..

Fire resisting door to exit openings of apartment/maisonette units, protected staircases, protected lobbies, exit passageway, compartment walls etc. shall have minimum half hour fire resistance. Doors to exit facilities shall not be fitted with any locking device. However, doors to exit openings of apartment/maisonette units would be fitted with locking devices for security reasons. As fire door is to protect the openings in exit facilities, it should always remain in the closed position to prevent the spread of smoke and heat. The main function of the self-closing device is to return the door to its closed position after being opened for movement of occupants, goods etc.. The passage latch fitted to the door is to hold the fire door in closed position to counteract the pressure differential between the door in a fire situation.

Many private residential apartment/maisonette buildings have card key access or automatic locking devices fitted to doors of exit staircases to prevent unauthorised access by outsiders. 

To gain entry into the staircase or to exit from it into any floor, the occupants need to key in a code number or use a card key access to unlock or release the locking device to the door. In times of power failure or activation of fire alarm system, if available, the locking device would be unlocked by itself and all the exit doors could be opened manually. Prior approval should be obtained from the SCDF before any door to exit facility is fitted with any form of locking device.

When the door to the exit facilities consists of double leaves or multiple leaves,  all the leaves shall be fitted with self-closing device and sequential closer.

Where the entrance door of the apartment or maisonette unit  consists of large and small leaves, self-closing device shall be required to be provided to the large leaf, provided the clear width of the opening of the large leaf when open at an angle of 90° is not less than 850mm. The smaller leaf is not to be taken into consideration as it would usually be bolted-shut, unless there is a need to open it for movement of large furniture, etc.. If the door opening has 2 leaves of equal width for use as exit to meet the minimum clear width of opening under Cl.2.2.9b., both leaves shall be fitted with self-closing device and sequential door closer. 

Self-closing device to fire door shall be properly maintained regularly. Faulty device shall be repaired immediately to prevent fire door being left in the open position.

  1. Where a self-closing device would be considered a hindrance to the normal use of the building, fire doors can be held open as follows:

    1. by a fusible link, or

    2. by electromagnetic or electromechanical devices which can be activated via smoke detector and/or the building alarm system.

  2. Any hinge on which a fire door is hung shall be of the approved type, complying with SS 332.

  3. Any fire door fitted in an opening which is provided as a means of escape:

    1. shall be capable of being opened manually, without the use of key, tool, special knowledge or effort for operation from the inside of the building;

    2. shall not be held open by any means other than by an electromagnetic or electromechanical device which can be activated via smoke detector and/ or the building alarm system, except in the case of fire doors opening into pressurised exit staircases; and

    3. shall open in the direction of exit travel in accordance with Cl.2.3.9.

  4. Fire doors, where required, shall be constructed and installed to comply with specifications stipulated under SS 332.

Explanations & Illustrations

Clause 3.9.2f. : Fire doors

Axonometric view Figure 3.9.2f.
Axonometric view
Figure 3.9.2f.

All fire doors are required to be listed under a recognised certification body. It is important to note that fire door opening into pressurised exit staircases shall not be fitted with electromagnetic or electromechanical device. This is to ensure that the integrity of the pressurised exit staircase is maintained at all times.

3.9.3

Pipes

Fire doors for protection of openings shall comply with all of the following:

  1. Pipes passing through a separating wall, compartment wall or compartment floor shall be kept as small as possible and be fire-stopped around the pipe. The nominal diameter of the pipe shall not be more than the respective dimension given in Table 3.9A. These pipe penetrations are permitted only for conveying non-hazardous & non-combustible substances such as air, water, etc., and approved fire-stopping material shall be applied around the pipe penetration. The clear spacing between pipes shall be at minimum 50mm or half the diameter of the largest pipe, whichever is larger.

  2. The following pipes of nominal diameter larger than 150mm, subject to the conditions listed under Cl.3.9.3c. below, are permitted to penetrate through a separating wall, compartment wall or compartment floor:

    1. emergency standby diesel generator steel exhaust pipes connected directly to the external space;

    2. pipes of non-combustible material (such as cast iron or steel) with pipe wall thickness of at least 5mm, and melting point of at least 1200ºC; and

    3. thermal insulated pipes with pipe wall thickness of at least 5mm and combustible insulation in compliance with Cl.7.1.2c.(1). The metal sheath for insulation material shall be at least 0.6mm thick galvanised steel with the melting point, including pipe support, of at least 1200ºC.

Rationale

Clause 3.9.3b

Other than the maximum sizes allowed under Table 3.9A, larger pipes such as chilled water pipes can also be permitted to penetrate through a separating wall, compartment wall or compartment floor. This is because the conditions stipulated in Cl.3.9.3c. will help to minimise the risk of fire spreading across different compartments.

  1. The following conditions shall be complied with for penetration of pipes stipulated under Cl.3.9.3b.:

    1. For non-sprinkler-protected area, pipe supports within 3m from the pipe penetration shall be strengthened such that the tensile stress generated on the supports shall not exceed 10N/mm2 and will not be softened or fracture when exposed to temperature of 750ºC. For sprinkler-protected area, the pipe supports and pipe penetrations shall be protected by the sprinkler system;

    2. Combustible materials or services (e.g., pipe or ductwork) are not permitted to be placed within 1m before and after the penetration [except for those thermal insulated pipes constructed under Cl.3.9.3b.(3) For the purpose of this sub-clause, fire-rated materials are deemed as non-combustible; and

    3. The penetration shall not pass through fire-rated wall/ floor of exit staircase, fire lift lobby, smoke-free lobby, electrical switch room, transformer room, generator room, battery room and fan room serving fire protection system, fire pump room, FCC, fuel tank room, and areas handling hazardous materials. Except for exit staircase, the penetration of pipes through the abovementioned rooms/ spaces is permitted if the pipes are fully enclosed by fire-rated enclosure with the same fire-rating as the fire-rated walls/ floors it passes through

  2. In addition to Cl.3.9.3a., fuel and vent pipes for emergency standby diesel generators and fuel tanks located outside the room they served shall be enclosed in construction having at least 2-hr fire resistance rating. They shall not be located in intakes/ fresh air vent shafts.

  3. Routing of gas pipes in basements

    1. All gas pipes that are routed in basement shall be API pipes with welded joints. These joints shall be 100% radiography checked in accordance with SS 608. The gas pipes are not required to be fire-rated if they are running outside essential areas such as an exit staircases, smoke-free or fire lift lobby, fire pump room, generator room, FCC, etc.. If gas pipes run pass through an essential area, they are required to be encased in masonry.

    2. For mechanically ventilated basement, the gas pipes shall be provided with pipe sleeves to vent the gas pipes. One end of the sleeve shall be exposed to the external space in accordance with SS 608.

    3. For naturally ventilated basement that complies with Cl.6.4.1d.(2)(b)(ii), the provision of pipe sleeve is not required.

Explanations & Illustrations

Clause 3.9.3 : Pipes

Top figure : Axonometric view Bottom figure : Section Figure 3.9.3 - 1
Top figure : Axonometric view
Bottom figure : Section
Figure 3.9.3 - 1

The clustering of pipes without proper spacing would further weaken the integrity of the fire resisting walls in times of fire emergency.

Section Figure 3.9.3 - 2 : Penetration of elements of structure by pipes
Section
Figure 3.9.3 - 2 : Penetration of elements of structure by pipes
Section Figure 3.9.3 - 3
Section
Figure 3.9.3 - 3

External corridor would be well ventilated. Hence fire risk is lower and the threat of spread of fire and smoke from floor to floor is very much reduced.

3.9.4

Ventilation ducts

A ventilation duct which passes directly through a compartment wall or compartment floor shall comply with the following:

  1. Where the ventilation duct does not form a protected shaft or is not contained within a protecting structure,

    1. the duct shall be fitted with a fire damper where it passes through the compartment wall or compartment floor; and

    2. the opening for the duct shall be kept as small as practicable and any gap around the fire damper shall be fire-stopped.

  2. Where the ventilation duct forms a protected shaft or is contained within a protecting structure, the duct shall be:

    1. fitted with fire dampers at the inlets to the shaft and outlets from it; and

    2. constructed and lined with materials in accordance with the requirements in Chapter 7.

  3. The installation of ventilation ducts and fire dampers shall comply with the requirements in Chapter 7.

Explanations & Illustrations

Clause 3.9.4a. : Ventilation ducts

Section Figure 3.9.4a.
Section
Figure 3.9.4a.

Proper fire stopping around the duct where it penetrates the compartment floor/wall and provision of fire damper at the compartment wall/floor would help to prevent fire and smoke spread from compartment to compartment.

Clause 3.9.4b. : Ventilation ducts

Section Figure 3.9.4b.
Section
Figure 3.9.4b.

The provision of fire damper at the entry to the protected shaft would help to complete the compartmentation to prevent fire or smoke from being drawn into the protected shaft via ventilation duct.

3.9.5

Flues

Ducts encasing one or more flue pipes which pass through a compartment wall or compartment floor shall be of non-combustible construction, having fire resistance of not less than half the minimum period of fire resistance required for the compartment wall or compartment floor through which it passes, except for kitchen flue pipes when the fire resistance shall be as required for the compartment wall or compartment floor.

Explanations & Illustrations

Section Figure 3.9.5 - 1
Section
Figure 3.9.5 - 1

Separate kitchen exhaust shaft enclosed in masonry or drywall construction shall be provided for Kitchen (1) and (2). This is to prevent fire and smoke from spreading from one compartment to another. The wall enclosing the shaft shall have the same fire resistance as the compartment wall or floor.

Section Figure 3.9.5 - 2
Section
Figure 3.9.5 - 2

The enclosing walls to the duct serving the laboratory are required to be constructed of non-combustible materials, instead of masonry, and need to have not less than ½ the minimum period of fire resistance rating of the compartment walls or floor through which the duct passes.

3.9.6

Services passing through FCC, fire pump room, emergency generator room and smoke control fans room

Air ducts, sanitary pipes, gas pipes, electrical conduits/ cable tray and other services that are likely to permit the passage of flame or smoke in the event of a fire shall not be permitted to pass through any of the following spaces:

  1. FCCs

  2. Fire pump rooms

  3. Emergency generator rooms

  4. Smoke control fans rooms

    except where such services are required for the operation of the equipment in these areas.

Explanations & Illustrations

Services not forming part of the FCC, Fire Pump Room, Emergency Generator Room and Smoke Control Fans Rooms but routed inside the mentioned spaces are disallowed. In the case of site constraint, the services not required for the operation of the mentioned system shall be separated and  encased with masonry construction.

3.9.7

Services running inside and/or passing through fire lift lobby and smoke-free lobby

  1. Air ducts, sanitary pipes, gas pipes, electrical conduits/ cable trays, and other services, e.g., fan coil units, ventilation fans (essential or non-essential) are permitted to locate, run inside and/ or pass through a fire lift or smoke-free lobby provided all these services are protected with a 1-hr fire resistance rating enclosure, or separated with a 1-hr fire resistance ceiling from the said lobby. 

  2. For cablings/ pipings of firefighting or fire protection systems serving or running through the above lobbies, and for other services that are required for operation of the above lobbies during fire emergency, e.g., lighting, mechanical ventilation systems, these need not be separately protected. 

  3. Exception

    1. Services running inside and/ or passing  through an external  corridor.

    2. Metal water supply pipe and water tap not exceeding 50mm in nominal diameter.

    3. CCTV systems provided it complies with Cl.3.8.7a.(5).

Explanations & Illustrations

Clause 3.9.7 : Services passing through FCC, fire pump room, emergency generator room & smoke control fans room

Where the services need to be routed inside fire lift lobby and smoke-stop lobby, adequate protection must strictly be adhered to. The unprotected services are required to be protected with 1-hr fire resistance enclosure, or separated with 1-hr fire resistance ceiling from the protected lobby space.

3.9.8

Gas pipes running inside an internal corridor/lobby

Gas pipes running inside an internal corridor/lobby without fire resistance enclosure shall be encased with a pipe duct/sleeve vented to an external space.

3.10

Exit Staircases

3.10.1

Non-combustibility of structure

Every exit staircase, including the treads/ risers and landing, shall be constructed of non-combustible materials. The exception is for buildings under PG I, where only the stringer or structures supporting the treads/ risers and landing shall be constructed of non-combustible materials.

3.10.2

Compartmentation

The exit staircase shall be separated from other parts of the building by a masonry structure or drywall complying with Cl.3.8.7b. which shall have fire resistance for not less than the period required by Cl.3.3 for elements of structure. The flight, landing and supporting structures of the exit staircase shall comply with Cl.3.10.1 and fire resistance rating is not required.

Explanations & Illustrations

The exit staircase shall be separated away from all unprotected spaces and openings. For more details of separation distance for unprotected openings, refer to Cl.2.3.3.

3.10.3

Exit doors

Doors opening into the exit staircase shall have at least ½-hr fire resistance rating and fitted with an automatic self-closing device.

3.10.4

Finishes

Finishes to the ceilings/ walls and floors of exit staircase shall be of non-combustible materials.

Explanations & Illustrations

Figure 3.10.4
Figure 3.10.4

The protecting structure, excluding the external wall, to the staircase shall be constructed of non-combustible materials. Ceiling/wall and floor finishes shall be of non-combustible materials to ensure that the level of safety in the staircase is maintained at all times. The only exception allowed is the handrail material.

3.11

Concealed Spaces

3.11.1

General provision

Concealed spaces in a building, such as those within suspended ceilings or raised floors, shall be sub-divided by construction of cavity barriers to restrict the spread of smoke and flames.

Explanations & Illustrations

Section Figure 3.11.1 - 1
Section
Figure 3.11.1 - 1
Section Figure 3.11.1 - 2
Section
Figure 3.11.1 - 2

Concealed spaces or cavities in building provide a ready route or flue for smoke and flame to spread undetected for quite some time, thus increasing the risk to life safety of occupants in the building. This is particularly so in the case of void spaces above a suspended ceiling or in a roof space or in a raised floor system. Provisions are available in the Fire Code to reduce the risk of concealed smoke and flame spread by the introduction of cavity barrier when the area or linear dimensions of cavities exceed the limits as per Table 3.11A. Cavity barriers shall be constructed of non-combustible materials and shall have at least ½-hr fire resistance.

Rationale

Concealed spaces or cavities in a building provide a ready route or flue for smoke and flame to spread undetected, thus increasing the risk to life safety of occupants in the building. This is particularly so in the case of void spaces above a suspended ceiling, in a roof space or in a raised floor system. Therefore, cavity barriers constructed of fire-rated materials shall be provided to prevent the spread of smoke and fire in the concealed spaces.

3.11.2

Closing the edges of cavities

Cavity barriers shall be used to close the edges of cavities, edges around openings through a wall, floor and any other part of the construction which contains a cavity and to separate any cavity in a wall, floor or any other part of the construction from any other such cavity.

Explanations & Illustrations

Figure 3.11.2 - 1
Figure 3.11.2 - 1
Section Figure 3.11.2 - 2
Section
Figure 3.11.2 - 2

“Cavity barrier” means any construction provided to close a cavity against, or restrict the spread of smoke and flame within it.

In Figure 3.11.2 - 1 above, cavity barriers are used to close the edges around the window opening. Similar application is provided to window in external cavity wall in Figure 3.11.2 - 2.

3.11.3

Interrupting cavities

If a fire-resistant barrier (such as a compartment wall, floor, ceiling or roof) abuts a cavity (including a roof space), such a barrier shall be extended to sub-divide the cavity to form a complete fire resistant barrier. Such cavity barriers shall be of fire resisting construction at least equal to the provision for that required of the fire resisting barrier.

Explanations & Illustrations

Figure 3.11.3 - 1
Figure 3.11.3 - 1

Cavities must be closed where the fire barrier elements (compartment walls) abut the cavity (including the frame of a door).

Section Figure 3.11.3 - 2
Section
Figure 3.11.3 - 2

Cavity in the walls shall be closed where the compartment floor abuts it.

Figure 3.11.3 - 3
Figure 3.11.3 - 3

Any cavity within an element, or at the junction of two elements, must be closed by a cavity barrier.

Section Figure 3.11.3 - 4
Section
Figure 3.11.3 - 4

It is a common practice to bring the compartment wall right-up to the underside of the structural slab above. The cavity barrier above the compartment wall shall be treated as an extension of the compartment wall below.

Section Figure 3.11.3 - 5
Section
Figure 3.11.3 - 5

The roof space over a protected staircase must be separated by either a cavity barrier at (a) having the same fire rating as the wall of the staircase below, or a fire-rated ceiling at (b). See Cl.1.4.18 for further illustration. Extending the masonry wall right up to the underside of the roof coverings at (a) would meet the requirement under Cl.3.10 of having masonry enclosure to exit staircase.

3.11.4

Sub-division of extensive cavities

Cavities, including roof spaces, unless otherwise permitted, shall be sub-divided so that the maximum distance between cavity barriers shall not exceed the relevant dimensions given under Table 3.11A.

3.11.5

Fire resistance and fixing of cavity barriers

Cavity barriers shall be:

  1. constructed to provide at least ½-hr fire resistance rating; and

  2. tightly fitted to rigid construction or the junctions shall be fire-stopped to comply with the requirements of Cl.3.12.

Explanations & Illustrations

Section Figure 3.11.5 - 1
Section
Figure 3.11.5 - 1

Cavity barriers must be tightly fitted to rigid construction and mechanically fixed in position wherever possible. Where this is not possible (for example, in the case of a junction with slates tiles, corrugated sheeting or similar materials) the junction should be fire-stopped to prevent the spread of fire and smoke in the concealed space.

Cavity barriers must also be fixed so that performance will not be made ineffective by:

  1. movement of the building due to subsidence, shrinkage or temperature change; 

  2. collapse in fire of any services penetrating them;

  3. failure in fire of fixings; and

  4. failure in fire of any material or construction which they may abut. For example, if a suspended ceiling is continued over the top of a fire-resisting wall or partition, and direct connection is made between the ceiling and the cavity barrier above the line of the wall or partition, premature failure of the cavity barrier can occur when the ceiling collapses. However, this does not arise if the ceiling is designed to provide fire protection of 30 minutes or more.

failure in fire of any material or construction which they may abut. For example, if a suspended ceiling is continued over the top of a fire-resisting wall or partition, and direct connection is made between the ceiling and the cavity barrier above the line of the wall or partition, premature failure of the cavity barrier can occur when the ceiling collapses. However, this does not arise if the ceiling is designed to provide fire protection of 30 minutes or more.

Section Figure 3.11.5 - 2
Section
Figure 3.11.5 - 2

The main purposes of extending the compartment walls into the ceiling space are to complete the compartmentation to each apartment unit and to prevent smoke and fire spread via the concealed ceiling space.

Section Figure 3.11.5 - 3
Section
Figure 3.11.5 - 3

Compartment walls should be carried right up to the full storey height, to a compartment floor above or to the roof coverings, as appropriate. The walls in the ceiling above the common corridor shall not be treated as cavity barriers. They shall be treated as extension of the compartment walls below.

The main purposes of extending the compartment walls into the ceiling space are to complete the compartmentation to each apartment unit and to prevent smoke and fire spread via the concealed ceiling space.

3.11.6

Openings in cavity barriers

A cavity barrier shall have no opening except for:

  1. a door which has the same fire resistance rating as the cavity barrier, and are kept closed all the times;

  2. a pipe which complies with the provision under Cl.3.9.3;

  3. a cable or conduit containing one or more cables;

  4. a duct which is fitted with suitably mounted automatic fire damper where it passes through the cavity barrier; and

  5. other openings fitted with a suitably mounted fire damper.

Explanations & Illustrations

Figure 3.11.6 - 1
Figure 3.11.6 - 1
Figure 3.11.6 - 2
Figure 3.11.6 - 2

Penetrations of cavity barriers shall be restricted to those illustrated above. All openings through cavity barriers must be no larger than necessary and be fire stopped. The fire stopping shall not restrict thermal movement.

3.11.7

Raised floors for fixed stages and display platforms

The construction of raised floors for fixed stages and display platforms shall comply with the following requirements:

  1. the concealed space between the structural floor and raised floor shall not be used for storage;

  2. no services or installation shall be permitted within the concealed space other than electrical wiring in conduit in compliance with the requirements of SS 638;

  3. all sides of the raised floor shall be properly sealed; and

  4. the concealed space shall be subdivided by cavity barriers in compliance with the requirements of Cl.3.11.4 and Table 3.11A.

Explanations & Illustrations

Figure 3.11.7 - 1 : Raised floor with exposed surfaces in cavity having Class '0' flame spread
Figure 3.11.7 - 1 : Raised floor with exposed surfaces in cavity having Class '0' flame spread

The space between the floor and the raised floor or platform shall not be used for storage purpose. Electrical wiring in the space shall be in conduit in accordance with SS CP 5. Under Table 3.11A, cavity barrier is to be provided at 20m dimension in any direction. Sleeper walls, which are provided for support to the floor or platform, act as a cavity barrier in the concealed space.

Figure 3.11.7 - 2 : Raised floor with exposed surfaces in cavity having other than Class '0' flame spread
Figure 3.11.7 - 2 : Raised floor with exposed surfaces in cavity having other than Class '0' flame spread

The space between the floor and the raised floor or platform shall not be used for storage purpose. Electrical wiring in the concealed space shall be in conduit in accordance with SS CP 5. Under Table 3.11A, cavity barrier is to be provided at 8m dimension in any direction. As such, ½-hr fire-rated cavity barriers are provided to sectionalise the concealed space.

3.11.8

Raised floors with or without accessible panels

The construction of raised floors with or without accessible panels shall comply with all of the following requirements:

  1. The supporting structure shall be constructed of non-combustible materials having a melting point of at least 750°C.

  2. The concealed space between the structural floor and raised floor shall not be used for storage.

  3. No services or installations shall be permitted within the concealed space other than:

    1. electrical wiring in metal conduit and metal trunking in compliance with the requirements of SS 638;

    2. communication cables for computer equipment; and

    3. fire protection installations serving the area.

  4. Where the raised floor is used as a plenum, requirements in Cl.7.1.4 shall be satisfied.

  5. Decking of the raised floor shall be constructed of non-combustible material. Where combustible material is used as core material, if allowed in the case of sprinkler-protected buildings, the top, bottom, all sides and cut edges shall be covered with material with surface property complying with Class 0 (excluding materials for floor finishes).

Explanations & Illustrations

Clause 3.11.8e. : Raised floors with or without accessible panels

Figure 3.11.8e. - 1
Figure 3.11.8e. - 1

Non-combustible raised floor panels and supports are allowed to be used in non-sprinkler or sprinkler-protected buildings.

Figure 3.11.8e. - 2
Figure 3.11.8e. - 2

Raised floor panel constructed of combustible core, e.g. chipboard, shall only be allowed to be used in buildings protected by sprinkler system and that the underside of the raised floor is adequately covered by the sprinkler system.

  1. In the case of raised floors with accessible panels, access sections or panels shall be provided such that all concealed spaces between the structural floor and raised floor are easily accessible.

  2. Openings in the raised floor for entry of electrical cables shall be effectively closed to prevent entry of debris or other combustible material into the concealed spaces.

  3. All sides of the raised floor shall be properly sealed.

  4. the concealed space shall be subdivided by cavity barriers such that the maximum unobstructed area within the concealed space does not exceed 930m2.

  5. Where the concealed space is fitted with an automatic sprinkler system which complies with the requirements in Chapter 6, cavity barriers are not required.

Explanations & Illustrations

Clause 3.11.8g. to j. : Raised floors with or without accessible panels

Figure 3.11.8g. to j.
Figure 3.11.8g. to j.

The provision of cavity barriers shall comply with Table 3.11A of the Fire Code.

Non-sprinkler protected building

Cavity barriers shall be provided in accordance with Table 3.11A. The height of concealed space (H), measured between the finished floor level and the underside of the raised floor decking shall not exceed 400mm. The concealed space shall be fitted with smoke detection system in accordance with SS CP 10 Code of Practice for the Installation and Servicing of Electrical fire Alarm Systems. SS CP 10 also allows that smoke detector system is not required to be provided in concealed space which does not exceed 150mm in height. Automatic smoke detection system is applicable if the height of concealed space exceeds 400mm.

Sprinkler protected building

Cavity barriers shall be provided in accordance with Table 3.11A. Where the height of the concealed space does not exceed 400mm, smoke detection system complying with SS CP 10 shall be provided. The height of concealed space may exceed 400mm if the space is fitted throughout with sprinkler system. Where sprinkler system is provided inside the concealed space, cavity barriers are not required to be provided – Cl.3.11.8j..

  1. For a non-sprinkler-protected building, if the height of the concealed space measured between the top of the structural floor and underside of the raised floor decking exceeds 150mm, it shall be fitted with an automatic smoke detection system complying with requirements of SS 645. For a sprinkler-protected building, the concealed space shall be fitted with an automatic smoke detection system as above if its height is between 150mm to 400mm, and automatic sprinkler system if it exceeds 400mm; and

  2. Where the height of concealed space measured between the top of the structural floor and the underside of the raised floor decking is less than 50mm, the requirements on provision of cavity barriers shall not be applicable.

3.11.9

Provision for concealed spaces between floor or roof and suspended ceilings

Provision of cavity barriers within the concealed spaces of suspended ceiling can be exempted provided all of the following requirements are complied with:

  1. The concealed space shall not be used for storage.

  2. The supporting elements shall be constructed of non-combustible material.

  3. The exposed surfaces within the concealed space is of Class 0 flame spread (excluding surfaces of any pipe, cable, conduit or insulation of any pipe).

  4. In the case of a detector protected building:

    1. if the concealed space does not exceed 800mm in depth, or

    2. if the concealed space is fitted with detectors which comply with the requirements of Chapter 6.

Explanations & Illustrations

Clause 3.11.9d. : Provision for concealed spaces between floor or roof & suspended ceilings

Figure 3.11.9d. : Detector protected building (non-sprinkler protected)
Figure 3.11.9d. : Detector protected building (non-sprinkler protected)

Provision of cavity barriers in concealed ceiling space may not required if the following requirements are complied with:

  1. the space is not used for storage purpose; 

  2. the supporting elements eg. ceiling hangers or supports are constructed of non-combustible material; 

  3. the exposed surfaces within the concealed space is of Class 0 flame spread (excluding surfaces of any pipe, cable, conduit or insulation of any pipe or duct); and

  4. concealed space does not exceed 800mm in depth; if exceeds 800mm, it shall be fitted with smoke or heat detectors.

  1. In the case of a sprinkler-protected building:

    1. if the concealed space does not exceed 400mm in depth, or

    2. if the concealed space exceeds 400mm and does not exceed 800mm in depth and no combustible material is used within the concealed space, or

    3. if the concealed space is fitted with an automatic sprinkler system which complies with the requirements of Chapter 6.

Explanations & Illustrations

Clause 3.11.9e.(1) : Provision for concealed spaces between floor or roof & suspended ceilings

Figure 3.11.9e.(1). : Sprinkler-protected building - Depth of ceiling space does not exceed 400mm
Figure 3.11.9e.(1). : Sprinkler-protected building - Depth of ceiling space does not exceed 400mm

Provision of cavity barriers in the concealed ceiling space may not required if the following are complied with:

  1. the space is not used for storage purpose;

  2. the supporting elements eg. ceiling hangers or supports are constructed of non-combustible material;

  3. the exposed surfaces within the concealed space is of Class 0 flame spread (excluding surfaces of any pipe, cable, conduit or insulation of any pipe or duct); and

  4. concealed space does not exceed 400mm in depth.

Clause 3.11.9e.(2) : Provision for concealed spaces between floor or roof & suspended ceilings

Figure 3.11.9e.(2) : Sprinkler-protected building - Depth of ceiling space exceeds 400mm but not exceeding 800mm
Figure 3.11.9e.(2) : Sprinkler-protected building - Depth of ceiling space exceeds 400mm but not exceeding 800mm

Provision of cavity barriers in the concealed ceiling space may not required if the following are complied with:

  1. the space is not used for storage purpose;

  2. the supporting elements e.g. ceiling hangers or supports are constructed of non-combustible material;

  3. the exposed surfaces within the concealed space is of Class 0 flame spread (excluding surfaces of any pipe, cable, conduit or insulation of any pipe or duct); and

  4. no combustible material is used within the concealed space. However, where the combustible content is small in quantity, the SCDF may, at its discretion grants exemption, provided the space is protected by sprinklers installed on the extended basis under SS CP 52 (whole coverage to be extended to the ceiling).

Clause 3.11.9e.(3) : Provision for concealed spaces between floor or roof & suspended ceilings

Figure 3.11.9e.(3) : Concealed space is sprinkler-protected in accordance with Chapter 6
Figure 3.11.9e.(3) : Concealed space is sprinkler-protected in accordance with Chapter 6

Provision of cavity barriers in the concealed ceiling is not required. See also Cl.3.11.10 for further relaxation.

  1. In the case of other buildings, the concealed space shall not exceed 800mm in depth.

Explanations & Illustrations

Clause 3.11.9f. : Provision for concealed spaces between floor or roof & suspended ceilings

Figure 3.11.9f. : Other building which neither requires detector nor sprinkler system
Figure 3.11.9f. : Other building which neither requires detector nor sprinkler system

Provision of cavity barriers in the concealed ceiling space may not required if the following are complied with:

  1. the space is not used for storage purpose;

  2. the supporting elements e.g. ceiling hangers or supports are constructed of non-combustible material;

  3. the exposed surfaces within the concealed space is of Class 0 flame spread (excluding surfaces of any pipe, cable, conduit or insulation of any pipe or duct); and

  4. concealed space does not exceed 800mm in depth; if exceeds 800mm, it shall be fitted with smoke or heat detectors.

3.11.10

Exemption of cavity barriers in ceiling space

Where the concealed space of suspended ceiling is fitted with an automatic sprinkler system which complies with the requirements in Chapter 6,

  1. the concealed space can be exempted from provision of cavity barriers; and

  2. combustible materials can be used for the supporting elements and exposed surfaces of materials within the concealed space, provided the ceiling is not situated over an exit passageway, smoke-free lobby or other designated means of escape facilities.

Explanations & Illustrations

  1. Where the concealed ceiling space is protected by automatic sprinkler system, the above clause allows the following:

    1. Provision of cavity barrier is exempted;

    2. Combustible materials such as hardwood timber hangers for ceiling; and

    3. Exposed surfaces within the ceiling space may be of any class other than Class 0 flame spread ie. timber members.

  2. The above relaxation shall not apply if the above ceiling construction is situated over an exit passageway or other designated means of escape facilities.

3.11.11

Suspended ceiling over protected areas

The concealed spaces of a suspended ceiling over an exit passageway, smoke-stop lobby, exit staircase or other designated means of escape facilities shall comply with the following:

  1. the ceiling supporting elements and the ceiling shall be constructed of non-combustible materials.

  2. the exposed surfaces within the concealed space shall be of Class 0 surface flame spread; and

  3. where sprinkler system is installed within the concealed spaces at smoke-free lobby/ fire lift lobby, the ceiling supporting elements and its exposed surface may have a surface spread of flame not lower than Class 2.

Explanations & Illustrations

Section Figure 3.11.11
Section
Figure 3.11.11

The main concern is that spaces meant for safe escape of occupants shall be kept free of combustible materials. Common corridors are treated as escape routes. The exposed surfaces within ceiling space shall have a flame spread rating of Class ‘0’.

3.11.12

Exemption

Buildings under PG I are not required to comply with the requirements on the provision of cavity barriers in concealed spaces. Residential units in buildings under PG II need not comply with requirements on the provision of cavity barriers in concealed floor and ceiling spaces.

3.12

Fire Stopping

3.12.1

General provision

Openings for pipes, ducts, conduits or cables which pass through any part of a compartment (except for a part which does not serve as a fire resisting barrier) or cavity barrier, shall be:

  1. kept as few in number as possible;

  2. kept as small as practicable; and

  3. all gaps shall be filled with fire-stopping materials.

Rationale

Clause 3.12.1c

Fire-stopping materials will ensure the integrity of the fire compartment is maintained when penetrated by utility lines or pipes.

Explanations & Illustrations

Clause 3.12.1. : General provision

Figure 3.12.1 : Fire stopping to a pipe in a compartment wall
Figure 3.12.1 : Fire stopping to a pipe in a compartment wall

Fire stopping is concerned with ensuring that the fire-resisting capability of a component, i.e. separating wall, compartment wall/floor, cavity barrier is not diminished or impaired when penetrated by services for example, a pipe, ducts, etc..

Therefore whenever gaps are created by the penetration of such pipes, ducts in the fire-rated wall/floor, they must be kept as few as possible. The spacing and internal diameter of pipes passing through any elements of structure or cavity barrier shall comply with Cl.3.9.3 and Table 3.9A.

3.12.2

Fire-stopping

Materials for fire stopping shall have the necessary fire resistance when tested to BS 476: Part 20 or other acceptable standards.

3.12.3

Materials for fire-stopping

Suitable fire-stopping materials include:

  1. Fire-stopping and sealing systems (including those designed for service penetrations) which have been shown by test to maintain the fire resistance of the wall or other element.

  2. Other fire-stopping materials include:

    1. cement mortar;

    2. gypsum-based plaster;

    3. cement or gypsum-based vermiculite/ perlite mixes;

    4. glass fibre, crushed rock, blast furnace slag or ceramic based products (with or without resin binders); and

    5. intumescent mastics.

The method of fire-stopping and choice of materials shall be appropriate to the situation and its application.

Explanations & Illustrations

Clause 3.12.3 : Materials for fire stopping

To prevent displacement, materials used for fire stopping should be reinforced with (or supported by) materials of limited combustibility in the following circumstances:

  1. in all cases where the unsupported span is greater than 100mm, and

  2. in any other cases where non-rigid materials are used (unless they have been shown to be satisfactory by test)

Preference should be given to proprietary fire stopping and sealing system.

When cement mortar or gypsum board plaster or cement or gypsum based vermiculite/perlite mixes is used as fire stopping material, care should be exercised to ensure that workmen properly fill up the entire gaps with the appropriate fire stopping material instead of carrying cosmetic application by just filling up the gaps superficially.

3.13

Classification of Spread Of Flame

3.13.1

Requirements for Class 0

Any reference to a surface being Class 0 shall be construed as a requirement that:

  1. the material of which the wall or ceiling is constructed shall be non-combustible throughout, or

  2. the surface material (or, if it is bonded throughout to a substrate, the surface material in conjunction with the substrate) shall have a surface of Class 1 when tested to BS 476 Part 7 and if tested in accordance with BS 476: Part 6 shall have an index of performance (I) not exceeding 12 and a sub-index (i1) not exceeding 6.

Explanations & Illustrations

BS 476: Part 6 refers to a standard fire test for propagation of products.

Under this test, there is a means of comparing the contribution of combustible building materials to the growth of a fire by providing a measure of the rate of heat evolution of the samples, exposed in a small combustion chamber.

The performance of each sample is expressed as a numerical index from 0 to 100 or more. Low values of the indexes indicate a low rate of heat release. Three to five specimens are tested.

Index of performance I = i1 + i2 + i3 where sub-index i1 is derived from the first three minutes of test, i2 from the following seven minutes, and i3 from the final ten minutes. A high index i1 indicates an initial rapid ignition and heat release.

3.13.2

Class other than Class 0

Any reference to a surface being of a class other than Class 0, shall be construed as a requirement that the material which the wall or ceiling is constructed shall comply with the relevant test criteria relating to surface spread of flame, which is specified in relation to that class in BS 476: Part 7.

Explanations & Illustrations

BS 476: Part 7 refers to a standard fire test for the classification of the surface spread of flame of products. This test is able to determine the tendency of surfaces of flat material to support the spread of flame across their surfaces and specifies a method of classification appropriate to wall and ceiling linings. Class 0 represents the best performance, followed in descending order by Class 1, Class 2, Class 3 and Class 4. This clause is rephrased for clarity.

3.13.3

Order of classification

Class 0 shall be regarded as the highest class (based on BS 476 Part 6 & 7), followed in descending order by Class 1, Class 2, Class 3 and Class 4 (based on BS 476 Part 7), as set hereunder:

  1. Class 0 - Surface of no flame spread. Such surfaces shall conform to the requirements of Cl.3.13.1.

  2. Class 1 - Surface of very low flame spread. This refers to surfaces on which during the first 1½ mins of test, the spread of flame does not exceed 165mm and the final spread of flame does not exceed 165mm under the relevant test conditions.

  3. Class 2 - Surface of low flame spread. This refers to surfaces on which during the first 1½ mins of test, the spread of flame does not exceed 215mm and the final spread of flame does not exceed 455mm under the relevant test conditions.

  4. Class 3 - Surface of medium flame spread. This refers to surfaces on which during the first 1½ mins of test, the spread of flame does not exceed 265mm and the final spread of flame does not exceed 710mm under the relevant test conditions.

  5. Class 4 - Surface of rapid flame spread. This refers to surfaces on which the spread of flame exceeded the limit of Class 3.

Explanations & Illustrations

The reason for having Class 0 is that Class 1 covered too wide a range of performance for use in critical areas. Where a higher degree of protection is required, for example in exit staircases, exit passageways (which constitute the escape route), Class 0 is specified.

3.13.4

Class of flame spread to be not lower than specified

The surface of a wall or ceiling in a room/space shall be of a class not lower than specified as relevant in the Table 3.13A, provided that

  1. Where an automatic sprinkler system is fitted throughout in the building in compliance with the requirements in Chapter 6, there is no control on the surface of flame rating in rooms/spaces, except for the following occupancies/usage:

    1. healthcare facilities, including hospital, and nursing homes for handicapped, disabled, aged or persons with mental and/or mobility impairments;

    2. detention facilities; and

    3. exit staircases, exit passageways and smoke-free/fire lift lobbies.

  2. Where a building is not protected by an automatic sprinkler system, surfaces of the walls and ceilings can be of a surface class not lower than Class 3 to the extent permitted by Cl.3.13.5a. and Cl.3.13.5b. respectively.

  3. If timber is used as the surface material for the walls along the side gangways of an auditorium which is not sprinkler-protected, the requirements of this regulation pertaining to the requisite class of flame spread can be relaxed only in respect of those parts of such wall surfaces provided the aggregate area of such parts does not exceed 50% of the whole surface area of the side walls of the auditorium.

Explanations & Illustrations

Clause 3.13.4c. : Class of flame spread to be not lower than specified

Figure 3.13.4c.
Figure 3.13.4c.

In the design of the auditorium, there is a need to meet the acoustic requirements. Timber was then considered as a preferred material for use. The above clause provides the relaxation for the use of timber as wall linings, provided the aggregate area of the timber linings does not exceed 50% of the whole surface area of the side walls of the auditorium. The other reason for the above relaxation is that each auditorium is required to be constructed as a fire compartment.

Clause 3.13.4 : Class of flame spread to be not lower than specified

Figure 3.13.4
Figure 3.13.4

Wall, ceiling and floor finishes to exit staircase (including exit passageway) shall be of non-combustible materials or Class 0 (sprinkler-protected). For rooms, the extent of wall and ceiling finishes shall comply to Cl.3.13.5a. and  b. respectively.

Where a building is protected by automatic sprinkler system, the surfaces of the walls and ceilings of the circulation space (corridor) and institutional occupancy area can be downgraded by 2 classes subject to Class 3 being the lowest.

3.13.5

Where class of flame spread can be of any class not lower than Class 3

  1. Any part of the surface of a wall in a room or compartment can be of any class not lower than Class 3 if the area of that part (or if there are two or more such parts, the total area of those parts) does not exceed the following

    1. in the case of a building or compartment of PG III, 20m2, or

    2. in any other case, 60m2.

Explanations & Illustrations

Clause 3.13.5a.(1) : Where class of flame spread can be of any class not lower than Class 3

Section Figure 3.13.5a.(1)
Section
Figure 3.13.5a.(1)

The linings to internal surfaces of a wall in a room or compartment are permitted to have any Class as permitted under Table 3.13A.

Clause 3.13.5a.(2) : Where class of flame spread can be of any class not lower than Class 3

Figure 3.13.5a.(2) - 1
Figure 3.13.5a.(2) - 1

Computation of 60m² will be based on total surface areas of walls in a room having not lower than Class 3. In the above diagram, the total surface area of the 4 walls, if finished with Class 3 materials shall not exceed 60m².

Figure 3.13.5a.(2) - 2
Figure 3.13.5a.(2) - 2

In the above diagram there are two compartments. Each compartment can have a total of 60m² of combustible wall finishes of not lower than Class 3. Subsequently, if the compartment wall is removed, there is a need to review the provision of wall finishes, subject to the total wall finishes to the whole floor shall not exceed 60m². Area of wall finishes in excess of 60m² is required to be removed.

Figure 3.13.5a.(2) - 3
Figure 3.13.5a.(2) - 3

In the above diagram, if subsequently the compartment wall as shown in dotted lines is removed, the overall 60m² shall be based on total floor area of compartment A.

Figure 3.13.5a.(2) - 4
Figure 3.13.5a.(2) - 4

In situation where multiple floors are interconnected to form one compartment by atrium design, waiver application is required to vary the max. 60sq.m

For Class 3 wall finishes, the total area of 60sq.m excludes :

  1. door frames and unglazed parts of doors;

  2. window frames and frames in which glazing is fitted;

  3. architraves cover moulds, picture rails, skirtings and similar narrow members; and

  4. fitted furniture.

  1. Any part of the surface of a ceiling can be of any class not lower than Class 3 if that part of the surface is the face of a layer of material the other face of which is exposed to the external air (skylight included) and complies with any one of the following:

    1. The ceiling is that of a room in a building or compartment of PG III, IV, V or VII, or is that of a circulation space excluding a smoke-free lobby, exit staircase or exit passageway in a building or compartment of any purpose group, and

      1. the area of that part does not exceed 2.5m²; and

      2. the distance between that part and any other such part is not less than 3.5m.

Explanations & Illustrations

Clause 3.13.5b.(1) : Where class of flame spread can be of any class not lower than Class 3

Reflected ceiling plan Figure 3.13.5b.(1) - 1
Reflected ceiling plan
Figure 3.13.5b.(1) - 1

Ceilings of living room, dining room, kitchen and bedrooms are permitted to have combustible finishes of class not lower than Class 3. The control is based on the size and spacing of the ceiling material.

Reflected ceiling plan Figure 3.13.5b.(1) - 2
Reflected ceiling plan
Figure 3.13.5b.(1) - 2

The above clause is intended for lighting diffuser Any part of a ceiling to circulation space e.g. corridor can have not lower than Class 3 flame spread, provided each part shall not exceed 2.5m² and is separated from other such part by minimum 3.5m.

  1. -

    1. The ceiling is that of a room in a building or compartment of PG VI or VIII, and

      1. the area of that part does not exceed 5m²;

      2. the distance between that part and any other such part is not less than 1.8m; and

      3. that part and all other such parts are evenly distributed over the whole area of the ceiling and together have an area which does not exceed 20% of the floor area of the room.

Explanations & Illustrations

Clause 3.13.5b.(2) : Where class of flame spread can be of any class not lower than Class 3

Axonometric view Figure 3.13.5b.(2)
Axonometric view
Figure 3.13.5b.(2)
  1. Factories and warehouses are usually provided with translucent roof sheets or sky light for natural lighting.

  2. Any part of ceiling which is combustible shall have an area not exceeding 5m² and a class not lower than Class 3 flame spread. It shall be separated from any such part by at least 1.8m.

  3. The aggregate area of such part of ceiling shall not exceed 20% of the floor area.

  1. -

    1. The ceiling is that of a balcony, verandah, open car porch, covered way or loading bay which (regardless of its floor area) has at least one of its longer sides wholly and permanently open.

Explanations & Illustrations

Clause 3.13.5b.(3) : Where class of flame spread can be of any class not lower than Class 3

Figure 3.13.5b.(3) - 1
Figure 3.13.5b.(3) - 1
Figure 3.13.5b.(3) - 2
Figure 3.13.5b.(3) - 2

Unenclosed loading/unloading platform

Figure 3.13.5b.(3) - 3
Figure 3.13.5b.(3) - 3

Covered linkway connecting 2 buildings

In-addition to the above, ceilings to balcony, verandah, open carport are also allowed to have not lower than Class 3 flame spread. The above relaxation is allowed as the ceilings are located at the periphery of the building where smoke and heat could easily be dispersed into the exterior air.

Any material, including gypsum board or plaster board, which satisfies the requirements under Cl.1.4.71 as non-combustible material is to be treated as acceptable under the above clause, regardless of the presence of the 0.5mm thick paper facing.

  1. -

    1. The ceiling is that of a garage or outbuilding which (regardless of whether it forms part of a building or is a building which is attached to another building or wholly detached) has a floor area not exceeding 40m2.

Explanations & Illustrations

Clause 3.13.5b.(4) : Where class of flame spread can be of any class not lower than Class 3

Figure 3.13.5b.(4) - 1
Figure 3.13.5b.(4) - 1

Finishes to ceilings in circulation space in the building shall have a surface flame spread rating of not lower than Class 0 as required for under Table 3.13A.

Finishes to ceiling of a room or compartment are permitted to have any class as permitted under Table 3.13A.

Figure 3.13.5b.(4) - 2
Figure 3.13.5b.(4) - 2
Figure 3.13.5b.(4) - 3
Figure 3.13.5b.(4) - 3
Figure 3.13.5b.(4) - 4
Figure 3.13.5b.(4) - 4

A garage or outbuilding can have ceiling not lower than Class 3 flame spread, provided the accessible floor area does not exceed 40m².

3.13.6

Exception

Wall and ceiling finishes in the form of thin sheet of not more than 1.0mm thickness mounted to a non-combustible substrate will not be subject to the requirement of surface spread of flame provisions, except for exit staircases and passageways.

Explanation

The above clause grants relaxation on the control of wall and ceiling finishes which are not more than 1.0mm thick mounted on non-combustible substrate, provided these finishes are not used in exit staircases and exit passageways. The main concern is that all protected routes meant for escape of occupants shall be kept free of combustible finishes. The above finishes include material such as gypsum board.

Non-combustible boards, for example gypsum boards, which meet the requirements of Cl.1.4.71 are allowed to be used for the construction of smoke-stop lobbies, exit staircases and exit passageways.

3.13.7

Composite panel

Composite panel used as wall, ceiling or finishes shall comply with Cl.3.15.13.

3.14

Roofs

3.14.1

Roof construction

  1. The surface of materials for roof covering and roof construction shall have a surface spread of flame rating not lower than Class 1, or Class A when tested in accordance with ASTM E108, except in the case of PG I and PG II, and in buildings that are protected throughout with automatic sprinkler system.

  2. Composite panel used as roof covering shall comply with Cl.3.15.13.

  3. Roof covering containing plastic shall comply Cl.3.15.19c.(7).

Explanations & Illustrations

Clause 3.14.1a. : Roof construction

Figure 3.14.1a. - 1
Figure 3.14.1a. - 1

Roof construction to buildings under PG I usually use timber rafters and purlins for tiled roofs. Rooflights of combustible materials are usually used for lighting purposes. Generally, buildings under PG I are small in area and low-rise. For semi-detached and terraced houses, the separating walls would be brought right-up to the underside of or above the roof coverings to prevent spread of fire.

Figure 3.14.1a. - 2
Figure 3.14.1a. - 2

Roofs of building under PG II may consist of dome, flat, pitched roof and other types. Roof covering may include mixture of combustible and non-combustible materials, e.g. slate, clay tiles, glass, rigid plastic. It is quite common to find hardwood timber trusses, purlins etc. being used in the roof construction. The term “roof covering” is used to describe construction which may consist of one or more layers of material, but does not refer to the roof structure as a whole. Roofs which may have different construction can be broadly grouped under the following:

  1. Roofs over common corridors and means of escape. As these areas are meant for escape, it would be preferable that they be constructed totally of non-combustible materials.

  2. Roof over apartment/maisonette or penthouse units.

  3. Roof over linkway between buildings.

  4. Roof used as terrace or floor open-to-sky. The roof covering should be of non-combustible materials to eliminate any fire risk arising from a fire involving the covering.

  5. Roof over balconies

Roof can also perform two functions:

  1. to contain a fire or prevent its penetration from an external source; and

  2. to ensure that the external covering does not contribute to spreading of fire so that an adjoining roof might be in danger.

RC roof would be able to satisfy the above functions. However, traditional roof coverings such as tile, slates, metal roofing sheets etc., combined with timber trusses/purlins and combustible insulation materials would have a greater tendency to allow spread of flame. Rigid plastic or thermoplastic materials such as polycarbonate shall not be used. Similarly, thatched roof shall also not be used. Traditionally, tile roof construction requires timber battens and purlins for securing the tiles. However, the risk of fire spread via such timber members is taken care of by the provision of separating wall between residential units.

3.14.2

Provision for buildings not exceeding four storeys

Combustible material can be used for roof construction for PG III, IV, V and VII buildings which satisfy the following requirements: 

  1. the building shall not exceed four storeys;

  2. the roof space between the roof and the ceiling shall be sub-divided by cavity barriers where required to comply with the relevant provisions of Cl.3.11, and openings in cavity barriers shall be fire-stopped to comply with the requirements of Cl.3.12; and

  3. if the underside of the roof serves as the ceiling to a room or space, the elements of the underside of the roof shall comply with the relevant provisions of Cl.3.13 for restriction of spread of flame.

Explanations & Illustrations

Clause 3.14.2b. : Provision for buildings not exceeding four storeys

Figure 3.14.2b.
Figure 3.14.2b.

The provision of cavity area barrier is to prevent the spread of fire in the roof spaces. Any service penetration to the cavity barrier shall be fire-stopped.

The cavity barrier shall have minimum ½-hr fire resistance rating.

Clause 3.14.2c. : Provision for buildings not exceeding four storeys

Figure 3.14.2c.
Figure 3.14.2c.

Where false ceiling is not provided, the underside of the roof would be considered as the ceiling to the space below. Hence, there is a need to control the surface flame spread of the exposed underside of the roof construction.

3.14.3

Roof junction with separating wall and compartment wall

At junctions where the roof meets with a separating wall or compartment wall, the roof construction shall comply with the relevant requirements under Cl.3.6.3 and Cl.3.7.4 respectively.

Explanations & Illustrations

Section Figure 3.14.3
Section
Figure 3.14.3
3.15

Materials for Construction

3.15.1

General

Materials used in the construction of building elements shall comply with the provisions stated under this section in addition to the performance requirements, such as fire resistance rating and limit to spread of flame, stipulated in other relevant sections of this Code.

3.15.2

Intumescent paint

Intumescent paint is allowed to be used for protection of structural steel members of all buildings provided all of the following requirements are complied with:

  1. The paint shall be of a proprietary system that has been demonstrated to achieve the fire resistance performance as required in BS 476 Part 20/ 21 or its equivalent, together with the specified weathering tests as specified in the BS 8202: Part 2.

  2. Coating of intumescent paint onto structural steels, and subsequent maintenance shall conform to BS 8202: Part 2. Fire test for fire resistance performance shall be conducted on the specimens after the weather tests. The fire resistance rating of the tested specimen shall not diminish more than 25%, post- weathering tests.

  3. A signage depicting the below minimum information shall be affixed at a conspicuous location:

    1. Name of supplier

    2. Fire resistance rating of the intumescent paint

    3. Date of painting

    4. Expected date of re-painting

    5. Caution note: “Caution – No other paint/coating shall be applied to the surfaces of the structural steel members protected by the intumescent paint system"

  4. In buildings under PG VI and VIII, where there can be presence of corrosive atmosphere that can affect the effectiveness of intumescent paints for protection to structural steel members of buildings, such proposal shall be subjected to evaluation of the SCDF.

Note to QP

  1. For building exceeds 24m in habitable height, a Fire Safety Report shall be submitted together with the plan.

  2. A separate set of plans indicating the locations of the structural steel members coated with intumescent paint shall be included in the Fire Safety Report and Building Owner Fire Safety manual, where applicable.

Rationale

Intumescent paint is permissible for use as a passive fire protection system on structural steel. It is not applicable to industrial buildings as these buildings may contain harsh and/or adverse environment conditions that may affect the effective performance of intumescent paint applied on the structural steel.

3.15.3

Flame retardant chemicals

Flame retardant chemicals can be used for upgrading of fire resistance rating or surface spread of flame of timber or any combustible materials, subject to the following:

  1. the chemical treatment process is part of the manufacturing process to produce the finished product;

  2. the chemical treatment is by means of pressure impregnation conforming to SS 572, or the manufacturer’s specification in accordance to the prototype test, for timber and other combustible materials, respectively; and

  3. the treated materials/products have been subjected to a fire test, as required under Cl 3.4.1 or Cl 3.13.1.

Explanations & Illustrations

  1. It is recognised as an alternative means to protecting timber construction in buildings.

  2. However, we have to understand the limitations on the use of flame retardant chemicals for upgrading of fire resistance and/or surface spread of flame rating of combustible materials. The limitations are as follows:

    1. The chemicals may deteriorate after exposing to the environment for a long duration. After such, the fire resistance performance or the surface spread of flame rating may be adversely affected over time.

    2. The inherent property of the flame-retardant chemical to resist fire spread may be affected when cleaning agent is constantly applied to the surface of the combustible material.

    3. There is no specific method and control of treatment of the flame- retardant chemical. This would lead to poor performance as a result of shoddy construction of the materials.

    4. There is no certainty on the duration for which the fire property in a material applied with such a chemical can last.

  3. For buildings which are not under Conservation, the use of timber materials should be carefully considered and should be avoided where possible.

  4. Building owners and occupiers should be made aware of the above mentioned limitations on the use of flame retardant chemicals. In the course of using the premises, building owners and occupiers shall not do anything to cause the retardant treatment to timber members to deteriorate.

  5. For lining of walls and ceilings, and construction of mezzanine floor, flame retardant chemicals shall not be used to treat the timber members or other combustible materials to meet surface flame spread and fire resistance rating requirements respectively.

Note

The QP is responsible to inform the building owner and occupiers of the limitations on the use of flame retardant chemicals. In the course of using the premises, the building owner and occupiers shall not do anything to cause the retardant treatment to timber members to deteriorate.

3.15.4

Elements of structure

All elements of structure shall be constructed of non-combustible materials in addition to the relevant provisions as follows:

  1. Cl.3.3 for fire resistance of elements of structure

  2. Cl.3.5.1Cl.3.5.2 &  Cl.3.5.4 for external walls

  3. Cl.3.6.1a.(3)Cl.3.6.1b. Cl.3.6.5 for separating walls

  4. Cl.3.7.1c.Cl.3.7.1d.,  Cl.3.7.5 & Cl.3.7.6 for compartment walls and compartment floors

  5. Cl.3.8.2c.Cl.3.8.4Cl.3.8.7b.Cl.3.8.8b.Cl.3.8.8e. and  Cl.3.8.9a. for protected shafts

3.15.5

Protection of openings

Materials used for the protection of openings shall comply with the relevant provisions of Cl.3.9 of this Code for protection of openings.

3.15.6

Exit staircases

Exit staircases shall be constructed of non-combustible materials to comply with the provisions of Cl.3.10.1.

3.15.7

Raised floors

Materials used for the construction of raised floors shall comply with the provisions of Cl.3.11.8a. and Cl.3.11.8e..

3.15.8

Ceiling and ceiling supports

  1. Materials used for construction of ceiling and its supports shall comply with Table 3.13B, except for supports that are required to comply with Cl.3.11.9b..

  2. Construction of ceilings and ceiling supports located within sprinkler-protected building shall comply with the provision of Cl.3.11.10b..

3.15.9

Fire-stopping

Materials used for fire-stopping shall comply with the relevant provisions of Cl.3.12.2 and Cl.3.12.3.

3.15.10

Surfaces of walls and ceilings

Materials used on the surfaces of walls and ceilings are required to meet the requirements for restriction of spread of flame, and shall comply with the performance requirements as stipulated under Cl.3.13.

3.15.11

Roof construction

Materials used for roof construction shall comply with the provisions of Cl.3.14.1 & Cl.3.14.2.

3.15.12

Internal non-load-bearing walls

Internal non-load-bearing walls in buildings shall comply with Table 3.13B and the materials for surface finishes of internal non-load-bearing walls shall not be treated as part of the wall and shall comply with the relevant provisions of Cl.3.13.

Explanations & Illustrations

All the internal non-load-bearing walls in the residential units shall be constructed of non-combustible materials. Materials for surface finishes of all the walls, non-loading-bearing, separating and compartment walls shall comply with Cl.3.13.5 and Cl.3.13.6.

3.15.13

Composite panel

Composite panels used for the construction of internal non-load-bearing walls, as cladding to external/ internal walls or as roof covering shall comply with all of the following criteria:

  1. The outer layers shall be constructed of non-combustible material.

  2. The core material (with aggregate thickness exceeding 1mm) of composite panel used for building interior shall meet the classification stipulated in Table 3.13B.

  3. The composite panel used for external wall cladding shall be mounted against 1-hr fire-rated wall and shall comply with any of the following:

    1. Its core material shall meet at least:

      1. BS 476 Part 4, or

      2. BS 476 Part 11, or

      3. Class 0 flame-spread rating when tested in accordance with BS 476 Part 6 & 7, or

      4. Class B classified under EN 13501-1.

    2. The panel assembly shall comply with NFPA 285.

  4. Composite panel containing plastic shall also comply with Cl.3.15.19.

3.15.14

Fire-rated glass

In buildings which are protected by an automatic sprinkler system, fire-rated glass can be used for the construction of compartment walls, compartment floors, enclosures of smoke-stop lobbies and fire lift lobbies, and protected shafts not containing exit staircase and fire lift, subject to the following:

  1. the walls shall have the necessary fire resistance, including insulation, when subject to test under BS 476 Part 20-23; and

  2. the doors shall have the necessary fire resistance, including insulation, when subject to test under SS 332 or EN 1634-1; and

  3. the walls and doors shall meet the requirement of Class A for Impact performance when tested under AS 2208 or Class 1 for Impact Level (drop height class) when tested under EN 12600.

3.15.15

Walls, ceilings, roof covering and finishes

Walls, ceilings, floor, roof and finishes shall not contain any plastic material, unless the plastic material complies with the requirements stipulated in Cl.3.15.19.

Exception: 

  1. Use of plastic materials as vertical screening/ divider of telecommunication equipment at non-habitable open-to-sky roof is permitted, provided the materials meet at least Class 2 rating classified under BS 476: Part 7 or equivalent.

Rationale

General plastic materials can readily ignite, hasten fire spread and emit toxic gases and significant amount of smoke.

3.15.16

Separation of areas undergoing A&A works

For additions and alterations to existing buildings, non-combustible partitions shall be used for separation of areas undergoing A&A works from other occupied areas of the building.

Explanations & Illustrations

To separate areas undergoing A/A works from other occupied spaces, non-combustible partition is permitted instead of fire rated construction. However, the non-combustible partition shall be brought to the underside of the floor slab to segregate both spaces. This will help to prevent spread of smoke and fire which may be originated from the A/A works.

3.15.17

Partition for toilet cubicles

Materials with surface flame spread rating of not lower than Class 2 shall be used for the construction of partition for toilet cubicles. If the material used is of Class 3 surface flame spread rating, total exposed surface area of the partitions within the toilet shall not be more than 60m².

3.15.18

Timber floors

The use of timber floors is allowed under the following situations, provided it is protected to achieve the fire resistance rating required of the element of structure or compartment:

  1. for an attic within residential units under PG I and II, or

  2. in buildings designated for conservation where the timber floors are required to be retained, but subject to compliance with requirements stipulated under Cl.9.9.1, or

  3. in buildings built before 1969 under Cl.9.9.1.

3.15.19

Use of plastics in building construction

  1. General

    1. Tables 3.15A3.15B and 3.15C list the relevant fire test standards and acceptance criteria concerning the use of plastics for various building applications. Tables 3.15D to 3.15K stipulate whether fire tests are exempted or required, depending on the situation, as well as the situations in which the use of plastics is disallowed regardless of the fire test results. The use plastics for wall, ceiling, roof covering, floor and related finishes is only allowed if the conditions stated are met.

    2. For each test category, only one fire test is needed to demonstrate the acceptable fire risk level.

    3. Fire retardants are also allowed to be used to enhance the fire performance of plastics for building construction provided the retardants are applied in suppliers’ factories according to the retardants’ respective standards. Accelerated weathering tests will also be required to assess the effect of weather on fire retardants applied on external building applications.

Explanations & Illustrations

Clause 3.15.19a.(1) : Use of plastics in building construction

Axonometric view Figure 3.15.19a.(1) : Air-supported structure
Axonometric view
Figure 3.15.19a.(1) : Air-supported structure
  1. There are various types of air supported or pneumatic building. Air supported structures are used for commercial and industrial applications, such as dining area, warehousing and manufacturing processes, for the agricultural and horticultural industries etc.

  2. The membranes used for the air supported structures are usually nylon, plastic, PVC or polythene sheet material, which are combustible in a fire.

  3. The main concerns are:

    1. the likelihood of the collapse of the roof owing to lack of pressure inside the structure or during times of emergency;

    2. the combustibility of the structure itself; and

    3. the collapse of the roof may cause panic and difficulties to occupants escaping during times of emergency.

  4. In view of the above, proposal for air supported structure shall be evaluated separately and SCDF’s consent shall be obtained before making building plan submission.

  1. Acceptable fire tests and corresponding acceptance criteria

    1. For plastic floor material/finishes, see Table 3.15A.

    2. For plastic wall and ceiling material/finishes, see Table 3.15B.

    3. For plastic roof covering, see Table 3.15C.

  2. Conditions for the use of plastics in various building applications

    1. For plastic floor finishes (uncovered), see Diagram 3.15.19c.(1) and  Table 3.15D.

    2. For plastic material cast into (embedded within) structural floor system, see Diagram 3.15.19c.(2) and  Table 3.15E.

    3. For plastic floor finishes (covered), see Diagram 3.15.19c.(3) and  Table 3.15F.

    4. For plastic wall or ceiling material/finishes, see Diagram 3.15.19c.(4) and   Table 3.15G.

    5. For composite panel containing plastic used as wall or ceiling material/ finishes, see Diagram 3.15.19c.(5) and  Table 3.15H.

    6. For plastic material embedded in masonry wall/ceiling, see Diagram 3.15.19c.(6) and  Table 3.15I.

    7. For plastic roof covering, see Table 3.15J.

    8. For composite panel containing plastic used as roof covering, see Table 3.15K.

3.15.20

UPVC window frame

Window frames made partly or wholly of UPVC are allowed to be used in buildings provided they are listed under the product listing scheme and comply with the requirements stipulated in Table 3.15.20.

TABLE 3.15.20 : CONDITIONS OF INSTALLATION OF UPVC WINDOW FRAME

Building type

Installation height (measured from the level of fire engine accessway/access road)

Length of window

Length of masonry wall break between windows

Non-sprinkler-protected

Sprinkler-protected

Horizontal

Vertical

PG I

No restriction

PG II

≤ 60m

No restriction

≤ 3m

≥ 1m

≥ 1.5m

PG III & VII

≤ 15m

≤ 24m

≤ 3m

≥ 1m

≥ 1.5m

PG IV, V, VI & VIII

≤ 15m

≤ 24m

≤ 5m

≥ 1m

≥ 1.5m

Related tables of Chapter 3

TABLE 3.2A : SIZE LIMITATION OF BUILDING & COMPARTMENT

TABLE 3.2A : SIZE LIMITATION OF BUILDING & COMPARTMENT

Compartments

Maximum Floor Area

Maximum Cubical Extent

(1)

(2)

(3)

Compartment below ground level
(No compartment shall comprise more than one storey)

2000m2

7500m³

Compartments between average ground level and a height of 24m
(No compartment shall comprise more than 3 storeys)

4000m2

15000m³

Compartments above a height of 24m from average ground level
(No compartment shall comprise more than one storey)

2000m2

7500m³

TABLE 3.3A: Minimum Periods of Fire Resistance

TABLE 3.3A: Minimum Periods of Fire Resistance

Note:

In this Table -

“cubical extent” means the cubical extent of the building or, if the building is divided into compartments, the compartment of which the elements of structure forms part;

“floor area” means the floor area of each storey in the building or, if the building is divided into compartments, of each storey in the compartment of which the element of structure forms part;

“height” has the meaning assigned to that expression by Cl.3.3.1b.;

“NL” means No limit applicable.

“NR” means Not Relevant.

PART I : BUILDINGS OTHER THAN SINGLE STOREY BUILDINGS

Purpose Group

Maximum Dimensions

Minimum period of fire resistance for elements of structure (*)/external wall/ compartment wall forming part of:

(1)

Height** (m)

(2)

Floor Area (m²)

(3)

Cubical Extent (m³)

(4)

Above ground Storey (hrs)(5)

Basement Storey (hrs)

(6)

PG I - Small residential

House having not more than 3 storeys

NL

NL

NL

1

1

House having 4 storeys

NR

250

NR

1

1

NL

NL

NL

1

2

House having more than 4 storeys

NL

NL

NL

1

2

PG II - Other residential

Building or part (+) having not more than 2 storeys

NL

500

NR

1

1

NL

NL

NL

1

2

Building or part (+) 3 storeys

NR

250

NR

1

1

NL

NL

NL

1

2

Building having more than 3 storeys

28

3000

8500

1

2

NL

NL

NL

2

2

PG III - Institutional

28

2000

NL

1

1

NL

NL

NL

2

2

PG IV - Office

15

NL

3500

1

1

28

5000

14000

1

2

NL

NL

NL

2

2

PG V - Shop

15

NR

3500

1

1

28

1000

7000

1

2

NL

NL

NL

2

4

PG VI - Factory

15

NR

4250

1

1

28

NR

8500

1

2

NL

NL

NL

2

4

PG VII - Place of public resort

15

NR

3500

1

1

28

1000

7000

1

2

NL

NL

NL

2

2

PG VIII - Storage and general

15

NR

1700

1

1

15

NR

3500

1

2

28

NR

7000

2

4(b)

NL

NL

NL

4(a)

4(b)

Note to Part I:

For the purpose of Cl 3.3.2 the period of fire resistance to be taken as being relevant to an element of structure is the period included in columns (5) or (6) in the line of entries which specifies the floor area with which there is conformity or, if there are two or more such lines, in the topmost of those lines
(*) - A floor which is immediately over a basement storey shall be deemed to be an element of structure forming part of a basement storey.
(**) - Height for elements of structure referred to building height including basement. In the case of compartment wall/external wall, the height shall be based on the height of the wall between compartment floors.
(+) - The expression “part” means a part which is separated as described in Cl.3.3.1b..
(a) - This period is reduced to 2-hrs for:

(1) non-sprinkler-protected, open-sided standalone car park buildings
(2) sprinkler-protected, above-ground car park floors in standalone car park building or sprinkler- protected mixed-use building

(b) - Single basement car park storey, which is sprinkler-protected, the element of structure can be reduced to half the minimum period of fire resistance

PART 2: SINGLE STOREY BUILDINGS

Purpose Group

(1)

Maximum Floor Area

(m2)

(2)

Minimum period of fire resistance for elements of structure, external wall/ compartment wall

(hrs)

(3)

PG I - Small residential

NL

1

PG II - Other residential

NL

1

PG III - Institutional

NL

1

PG IV - Office

NL

1

PG V - Shop

3000

1

NL

2

PG VI - Factory

3000

1

NL

2

PG VII - Place of public resort

3000

1

NL

2

PG VIII - Storage and general

1000

1

3000

2

NL

4(a)

Note to Part 2:

For the purpose of Cl.3.3.2 the period of fire resistance to be taken as being relevant to an element of structure is the period included in column (3) in the line of entries which specifies the floor area with which there is conformity or, if there are two or more such lines, in the topmost of those lines

(a) - This period is reduced to 2-hr for open-sided buildings which are used solely for car parking

TABLE 3.3B: REQUIREMENTS FOR SUSPENDED CEILING

TABLE 3.3B: REQUIREMENTS FOR SUSPENDED CEILING

Height of Building

(1)

Type of Floor

(2)

Required Fire Resistance of Floor

(3)

Description of Suspended Ceiling

(4)

Less than 15m

Non-compartment

1-hr or less

Surface of ceiling exposed within the cavity not lower than Class I surface flame spread rating.

Compartment

Less than 1-hr

Compartment

1-hr

Surface of ceiling exposed within the cavity not lower than Class 0 surface flame spread rating; supports and fixing for the ceiling non-combustible.

Any

More than 1-hr

Ceiling of non-combustible con- struction and jointless; supports and fixings for the ceiling non- combustible.

15m or more

Any

1-hr or less

Surface of ceiling exposed within the cavity not lower than Class 0 surface flame spread rating and jointless; supports and fixing for the ceiling non-combustible.

Any

More than 1-hr

Ceiling of non-combustible con- struction and jointless; supports and fixings for the ceiling non- combustible

Note:

References to classes in the above table are to classes as specified in Cl.3.13

Where the space above a suspended ceiling is protected by an automatic sprinkler system it shall be exempted from the requirements for non-combustibility and surface spread of flame classification as specified in the above table provided the ceiling is not situated over an exit passageway, protected lobby or other required protected means of escape

TABLE 3.4A: SPECIFIC PROVISIONS OF TEST FOR FIRE RESISTANCE OF ELEMENTS OF STRUCTURE ETC.

TABLE 3.4A: SPECIFIC PROVISIONS OF TEST FOR FIRE RESISTANCE OF ELEMENTS OF STRUCTURE ETC.

Part of Building

Minimum Provisions when Tested to BS 476: Part 20-23 (mins)

Method of Exposure

Stability

Integrity

Insulation

1. Structural frame, beam or column

*

No requirement

No requirement

exposed faces

2. Load-bearing wall, Load-bearing wall which is not also an external wall, separating wall, compartment wall or protecting structure (See 4, 5, 6 or 7)

*

No requirement

No requirement

each side separately

3. Floors

(a) floor in upper storey of a 2-storey dwelling house (but not over a garage)

30

15

15

from underside (Note 1)

(b) any other floor (including a compartment floor)

*

*

*

from underside (Note 1)

4. External walls

(a) any part less than 1m from point on relevant boundary

*

*

*

each side separately

(b) any part of the wall of a building used for Assembly purposes which is 1m or more from the relevant boundary and is described in Note 2

*

*

15

from inside

* (max. 60)

* (max. 60)

* (max. 60)

from outside

(c) any part 1m or more from the relevant boundary and is not a part de- scribed in (b) above

*

*

15

from inside

5. Separating wall

*

(min. 60)

*

(min. 60)

*

(min. 60)

each side separately

6. Compartment wall

*

*

*

each side separately

7. Protecting structure (any part)

*

*

*

each side separately

8. Wall separating an attached or integral garage from a dwelling house

*

*

*

from garage side

9. Doors

a. in a separating wall

No provision

+

(min. 60)

No provision***

each side separately when fitted in its frame

b. in a compartment wall, if it separates a flat or maisonette from a space in common use

No provision

30

No provision***

each side separately

c. in a compartment wall or compartment floor not described in (b) above

No provision

+

No provision***

each side separately

d. in a protecting structure situated wholly or partly above the level of the adjoining ground in a building used for flats, other residential, assembly or office purposes

No provision

30

No provision***

each side separately

e. in a protecting structure not described in (d) above

No provision

**

(min. 30)

No provision***

each side separately

f. any other door (including a door in a cavity barrier and a door between a dwelling house and garage)

No provision

30

No provision***

each side separately when fitted in its frame

10. Casing around a drainage system

30

30

30++

from outside

11. Cavity barriers

a. cavity barrier 1m x 1m or larger

30

30

15

each side separately

b. any other cavity barrier

30

30

No provision

each side separately

c. ceiling

30

30

30

from underside

Modifications

++ - No provision for insulation if the casing is more than 50mm from any pipe in the enclosure (except a pipe passing through the casing)

Note:

* - Period of fire resistance as specified

** - Half the period of fire resistance for the wall or floor in which the door is situated

*** = This exemption does not apply to fire-rated glass door.

+ - Period of fire resistance for the wall or floor in which the door is situated
++ - No provision for insulation if the casing is more than 50mm from any pipe in the enclosure (except a pipe passing through the casing)
1 - A suspended ceiling should only be relied on to contribute to the fire resistance of the floor if the ceiling meets the appropriate provisions given in Table 3.3B

2 - Any part of the wall which is 7.5m or less above the ground, or above a roof or any other part of the building to which people have access, if the building has 2 or more storeys

TABLE 3.9A: MAXIMUM NOMINAL DIAMETER OF PIPES

TABLE 3.9A: MAXIMUM NOMINAL DIAMETER OF PIPES

Situation

Pipe material and maximum nominal diameter (mm)

Non-combustible

material (1)

Lead, aluminium or aluminium alloy, or UPVC (2)

Any other material

When the pipes (include pipe supports) penetrate the structure enclosing a protected shaft which is not an exit stairway or lift shaft

150

100

40

Any other situation

150

100 (stack pipe) (3),(4),(5)

75 (branch pipe) (3),(4),(5)

40

Note:

(1) =  A non-combustible material (such as for cast iron or steel pipes and the pipe supports with melting point of at least 1200°C) which if exposed to a temperature of 750°C will not soften nor fracture to the extent that flame or gases will pass through the wall of the pipe

(2) = UPVC pipes complying with BS 4514 or EN 1329-1

(3) = Within toilets, washrooms or external corridors, maximum diameter of UPVC pipes can be increased to double the size given in the above table

(4) = Within areas of fire risk, such as kitchens, and adjacent to escape routes, UPVC pipes shall be enclosed by construction having fire resistance rating of at least ½ hr

(5) = Where the size of UPVC pipes exceeds that specified under this clause, approved fire collar shall be fitted at all positions where such pipes pass through constructions required to act as a barrier to fire spread

TABLE 3.11A: MAXIMUM DIMENSIONS OF CAVITIES

TABLE 3.11A: MAXIMUM DIMENSIONS OF CAVITIES

Location of cavity

Purpose Group of building or compartment

*Class of surface exposed in cavity

Max. dimension in any direction

Between roof and ceiling

I & II

any

no limit

others

any

20m

Any other cavity

any

Class 0

20m+

any

any

8m+

Note:

* - excluding surface of any pipe, cable, conduit or insulation of any pipe

+ - shall not apply to raised floor under Cl.3.11.8

TABLE 3.13A: MINIMUM FLAME-SPREAD CLASSIFICATION OF FINISHES TO WALL, COLUMN, BEAM AND CEILING

TABLE 3.13A: MINIMUM FLAME-SPREAD CLASSIFICATION OF FINISHES TO WALL, COLUMN, BEAM AND CEILING

Building Type

Non-sprinkler-protected Building

Sprinkler-protected Building

Room, compartment

Circulation space

Smoke- free /fire lift lobby

Exit stair- case & exit passageway

Room, compartment

Circulation space

Smoke- free /fire lift lobby

Exit stair- case & exit passageway

BS(2)

EN(2)

BS(2)

EN(2)

BS(2)

EN(2)

BS(2)

EN(2)

BS(2)

EN(2)

BS(2)

EN(2)

BS(2)

EN(2)

BS(2)

EN(2)

PG I - Small residential

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

2

C

0

B

PG II - Other residential

NA

NA

0

B

0

B

NC

A2

NA

NA

NA

NA

2

C

0

B

PG III - Institutional

1

C

0

B

0

B

NC

A2

3

D(1)

3

D(1)

2

C

0

B

PG IV - Office

1

C

0

B

0

B

NC

A2

NA

NA

NA

NA

2

C

0

B

PG V - Shop

1

C

0

B

0

B

NC

A2

NA

NA

NA

NA

2

C

0

B

PG VI - Factory

1

C

0

B

0

B

NC

A2

NA

NA

NA

NA

2

C

0

B

PG VII - Place of public resort

1

C

0

B

0

B

NC

A2

NA

NA

NA

NA

2

C

0

B

PG VIII - Storage

1

C

0

B

0

B

NC

A2

NA

NA

NA

NA

2

C

0

B

Note:

NC = Non-combustible to comply with BS 476 Pt 4

NA = Not Applicable

(1) = Applies to detention facilities and healthcare, including hospital, old-aged homes, nursing homes for mentally or physically disabled patients

(2) = BS/ EN refers to the following test standards. Meeting an EN standard implies that the corresponding BS standard is complied with but not vice-versa

EN 13501-1

EN 13501-1

Classification

Test Standards

Classification

Test Standards

Class A1

EN ISO 1182 + EN ISO 1716

Non-combustibility (NC)

BS 476 Part 4

Class A2

[EN ISO 1182 or EN ISO 1716] + EN 13823

Limited combustibility (LC)

BS 476 Part 11

Class B

EN 13823 + EN ISO 11925-2

Class 0

BS 476 Part 6 & 7

Class C

EN 13823 + EN ISO 11925-2

Class 1

BS 476 Part 7

Class C

EN 13823 + EN ISO 11925-2

Class 2

BS 476 Part 7

Class D

EN 13823 + EN ISO 11925-2

Class 3

BS 476 Part 7

Class F

EN ISO 11925-2

Class 4

BS 476 Part 7

TABLE 3.13B: MINIMUM FLAME-SPREAD CLASSIFICATION OF MATERIAL CONSTRUCTION (HOMOGENOUS)*

TABLE 3.13B: MINIMUM FLAME-SPREAD CLASSIFICATION OF MATERIAL CONSTRUCTION (HOMOGENOUS)*

Building Type

Non-sprinkler-protected Building

Sprinkler-protected Building

Internal Non-load-bearing Wall and Ceiling

Roof(5) Covering, including Supports

Internal Non-load-bearing Wall and Ceiling

 

Roof(5) Covering, including Supports

Within Room, Compartment

Within Circulation Spaces(6)

Within Room, Compartment

Within Circulation Spaces(6)

BS(7)

EN(7)

BS(7)

EN(7)

BS(7)

EN(7)

BS(7)

EN(7)

BS(7)

EN(7)

BS(7)

EN(7)

PG I - Small residential

NA

NA

NA

NA

NA(2)

NA(2)

NA

NA

NA

NA

NA

NA

PG II - Other residential

NA

NA

LC(3)

A2

NA(2)

NA(2)

NA

NA

1

C

NA

NA

PG III - Institutional

0

B

LC(3)

A2

1

C(4)

1

C(1)

0

B(1)

2

C(1)(4)

PG IV - Office

0

B

LC(3)

A2

1

C(4)

2

C

1

C

2

C(4)

PG V - Shop

0

B

LC(3)

A2

1

C(4)

2

C

1

C

2

C(4)

PG VI - Factory

0

B

LC(3)

A2

1

C(4)

2

C

1

C

2

C(4)

PG VII - Place of public resort

0

B

LC(3)

A2

1

C(4)

2

C

1

C

2

C(4)

PG VIII - Storage

0

B

LC(3)

A2

1

C(4)

2

C

1

C

2

C(4)

Note:

(1)  =  Applies to detention facilities and healthcare, including hospital, nursing homes for handicapped, disabled, aged or persons with mental and/ or mobility impairment

(2) = Roof support can be of timber construction. Any use of plastic material for roof shall comply with the requirements in Cl.3.15.19c.(8)

(3) = Limited combustibility tested under BS 476 Part 11 or non-combustibility tested under BS 476 Part 4

(4) =  Composite panel complying with ASTM E108 Class A is also acceptable

(5) = Applicable to composite panel roofing only. Refer to Cl.3.14.1 for other roofing materials

(6) = Including common corridor, passageway etc.

(7) = BS/EN refers to the test standards shown in the Note to Table 3.13A. Meeting an EN standard implies that the corresponding BS standard is com- plied with but not vice-versa

NA = Not Applicable

LC = Limited combustibility

* = When composite panels are used for the construction, the minimum flame-spread classification shall be applicable to the core material of the panels

a.

FIRE TESTS AND ACCEPTANCE CRITERIA FOR CONSTRUCTION MATERIALS CONTAINING PLASTIC: TABLE 3.15A

TABLE 3.15A: PLASTIC FLOOR MATERIAL/ FINISHES

Test Category

Fire Risk

Applicable Fire Test Standards

Acceptance Criteria

A

Toxicity

emission

EN 45545-2

CIT < 0.75

EN 17084 Method 1 (25kw/m2)

CIT < 0.75

B

Smoke

density

EN 13501-1

Smoke classification : s1 rating.

EN 14041

EN ISO 9239-1

ASTM E662

Smoke density, Ds,max < 450

NFPA 258

EN ISO 5659-2

Smoke density, Ds,max < 150

C

Flame spread

EN 13501-1

1. Sprinkler-protected premises

(a) Sleeping occupancy : Class Cfl or better

(b) Non-sleeping occupancy : Class Dfl or better

 

2. Non-sprinkler-protected premises

(a) Sleeping occupancy : Class Bfl or better

(b) Non-sleeping occupancy : Class Cfl or better

EN 14041

EN ISO 9239-1

ASTM E648

Critical Radiant Flux (CRF) > 0.45 W/cm2

NFPA 253

 

b.

FIRE TESTS AND ACCEPTANCE CRITERIA FOR CONSTRUCTION MATERIALS CONTAINING PLASTIC: TABLE 3.15B

TABLE 3.15B: PLASTIC WALL/ CEILING MATERIAL/ FINISHES

Test Category

Fire Risk

Applicable Fire Test Standards

Acceptance Criteria

D

Toxicity emission

EN 45545-2

CIT < 0.75

EN 17084 Method 1 (50kw/m2)

CIT < 0.75

E

Smoke density

EN 13501-1

1. Smoke classification to be of s1 rating

 

2. Flaming droplet classification to be d0 rating

EN ISO 5659-2

VOF < 300 min

F

Flame spread

EN 13501-1

1. Internal wall finishes: to comply with Cl 3.13

 

2. External wall finishes: to comply with Cl 3.5

BS 476-6/7

NFPA 285

To pass criteria in NFPA 285

Note:

Test categories D and E are not required for external wall finishes

c.

TABLE 3.15C : PLASTIC ROOF COVERING MATERIAL

TABLE 3.15C : PLASTIC ROOF COVERING MATERIAL

Test Category

Fire Risk

Applicable Fire Test Standards

Acceptance Criteria

G

Toxicity

emission

Not critical. Generally exposed to external.

H

Smoke

density

EN 13501-1

1. Generally not critical if exposed to external

2. If exposed as ceiling on the underside, then must meet requirements for ceiling (achieve s1-d0 rating)

J

Flame spread

EN 13501-5

Class BROOF

BS 476-3

Class AA/AB/AC

BS 476-7

Class 1

ASTM E108

Class A

CONDITIONS FOR THE USE OF PLASTIC FLOOR FINISHES (UNCOVERED)

Diagram 3.15.19c.(1) : Plastic floor finishes overlaid on structural floor
Diagram 3.15.19c.(1) : Plastic floor finishes overlaid on structural floor
a.

TABLE 3.15D: UNCOVERED PLASTIC FLOOR FINISHES

TABLE 3.15D: UNCOVERED PLASTIC FLOOR FINISHES

S/N

Material Construction

Assessment

Remarks

1

Non-combustible material

Allowed

No further fire test is required

2

Material thickness not exceeding 10mm

Allowed

1. No further fire test is required

2. For sprinkler-protected premises, material not exceeding 20mm can be exempted from the tests in Table 3.15A

3

Use in open-to-sky conditions

Allowed

No further fire test is required

4

Use in exit staircase/ exit passageways

Not allowed

Key escape routes shall be protected

5

Material thickness exceeding 10mm

Allowed with conditions

Allowed if pass test categories A, B and C in Table 3.15A

b.

CONDITIONS FOR THE USE OF PLASTIC MATERIAL CAST INTO (EMBEDDED WITHIN) STRUCTURAL FLOOR SYSTEM

Diagram 3.15.19c.(2) : Plastic material embedded within masonry floor
Diagram 3.15.19c.(2) : Plastic material embedded within masonry floor
c.

TABLE 3.15E : PLASTICS EMBEDDED WITHIN MASONRY FLOOR

TABLE 3.15E : PLASTICS EMBEDDED WITHIN MASONRY FLOOR

S/N

Material construction

Assessment

Remarks

1

Non-combustible material

Allowed

No further fire test is required

2

Material thickness not exceeding 10mm

Allowed

1. No further fire test is required

2. For sprinkler-protected premises, material not exceeding 20mm can be exempted from the tests in Table 3.15A

3

Use in open-to-sky conditions

Allowed

No further fire test is required

4

Use in exit staircase/exit passageways

Not allowed

Key escape routes shall be protected

5

Material thickness exceeding 10mm

Allowed with conditions

1. If masonry cover is less than 25mm thick, the material shall pass test categories A, B and C in Table 3.15A.

2. If masonry cover is at least 25mm thick all around the embedded plastic, tests in Table 3.15A are exempted.

3. The locations where embedded plastics are installed shall be clearly indicated on the plans


d.

CONDITIONS FOR THE USE OF PLASTIC FLOOR FINISHES (COVERED)

Diagram 3.15.19c.(3) : Plastic floor finishes laid on structural floor, and covered by a non-combustible overlay
Diagram 3.15.19c.(3) : Plastic floor finishes laid on structural floor, and covered by a non-combustible overlay
e.

TABLE 3.15F: COVERED PLASTIC FLOOR FINISHES

TABLE 3.15F: COVERED PLASTIC FLOOR FINISHES

S/N

Material Construction

Assessment

Remarks

1

Non-combustible material

Allowed

No further fire test is required

2

Material thickness not exceeding 10mm

Allowed

1. No further fire test is required

2. For sprinkler-protected premises, material not exceeding 20mm can be exempted from the tests in Table 3.15A

3

Use in open-to-sky conditions.

Allowed

No further fire test is required

4

Use in exit staircase / exit passageways

Not allowed

Key escape routes shall be protected

5

Material thickness exceeding 10mm

Allowed with conditions

1. Allowed if pass test categories A, B and C in Table 3.15A

2. If the overlay is non-combustible and at least 25mm thick, test category C in Table 3.15A is exempted

CONDITIONS FOR THE USE OF PLASTIC WALL FINISHES OR CEILING FINISHES

Diagram 3.15.19c.(4) : Plastic wall or ceiling material/ finishes installed internally/ externally
Diagram 3.15.19c.(4) : Plastic wall or ceiling material/ finishes installed internally/ externally
a.

TABLE 3.15G: PLASTIC WALL OR CEILING MATERIAL/ FINISHES

TABLE 3.15G: PLASTIC WALL OR CEILING MATERIAL/ FINISHES

S/N

Material Construction

Assessment

Remarks

1

Non-combustible material

Allowed

No further fire test required

2

Material thickness not exceeding 1mm

Allowed

No further fire test required

3

Use in exit staircase/exit passageways

Not allowed

Key escape routes shall be protected

4

Material thickness exceeding 1mm

Allowed with conditions

Allowed if pass test categories D, E and F in Table 3.15B, unless specifically exempted for external building applications

b.

TABLE 3.15H: COMPOSITE PANEL WITH PLASTIC USED AS WALL OR CEILING MATERIAL/ FINISHES

TABLE 3.15H: COMPOSITE PANEL WITH PLASTIC USED AS WALL OR CEILING MATERIAL/ FINISHES

S/N

Material Construction

Assessment

Remarks

1

Non-combustible plastic material

Allowed

No further fire test required

2

Plastic material thickness not exceeding 1mm

Allowed

No further fire test required

3

Use in exit staircase/ exit passageways

Not allowed

Key escape routes shall be protected

4

Plastic material thickness exceeding 1mm

Allowed with conditions

Allowed if pass test categories D, E and F in Table 3.15B, unless specifically exempted for external building applications

c.

CONDITIONS FOR THE USE OF PLASTIC MATERIAL EMBEDDED IN MASONRY WALL/ CEILING

Diagram 3.15.19c.(6) : Plastic material embedded within wall/ ceiling
Diagram 3.15.19c.(6) : Plastic material embedded within wall/ ceiling
d.

TABLE 3.15I: PLASTIC MATERIAL EMBEDDED IN MASONRY WALL/ CEILING

TABLE 3.15I: PLASTIC MATERIAL EMBEDDED IN MASONRY WALL/ CEILING

S/N

Material Construction

Assessment

Remarks

1

Non-combustible material

Allowed

No further fire test required

2

Material thickness not exceeding 1mm

Allowed

No further fire test required

3

Use in exit staircase/ exit passageways

Not allowed

Key escape routes shall be protected

4

 

Material thickness exceeding 1mm

 

Allowed with conditions

1. If masonry cover is less than 25mm thick, the material shall pass test categories D, E and F in Table 3.15B

2. If masonry cover is at least 25mm thick all around the embedded plastic, tests in Table 3.15B are exempted

3. The locations where embedded plastics are installed shall be clearly indicated on the plans

e.

CONDITIONS FOR THE USE OF PLASTIC ROOF COVERING

TABLE 3.15J : PLASTIC ROOF COVERING

S/N

Material Construction

Assessment

Remarks

1

Non-combustible material

Allowed

No further fire test required

2

Material thickness not exceeding 1mm

Allowed

No further fire test required

3

Use in exit staircase/ exit passageways

Not allowed

Key escape routes shall be protected

4

Material thickness exceeding 1mm

Allowed with conditions

1. Allowed if  pass  test category J in Table 3.15C, as well as test category H in Table 3.15C if exposed on underside

2. Exempted from test categories H and if the requirements specified for skylights in Cl.3.13.5b.

f.

CONDITIONS FOR THE USE OF COMPOSITE PANEL CONTAINING PLASTIC AS ROOF COVERING

TABLE 3.15K: COMPOSITE PANEL WITH PLASTIC USED AS ROOF COVERING

S/N

Material Construction

Assessment

Remarks

1

Non-combustible plastic material

Allowed

No further fire test required

2

Plastic material thickness not exceeding 1mm

Allowed

No further fire test required

3

Use in exit staircase/ exit passageways

Not allowed

Key escape routes shall be protected

4

Plastic material thickness exceeding 1mm

Allowed with conditions

1. Allowed if  pass  test category J in Table 3.15C, as well as test category H in Table 3.15C if exposed on underside

2. Exempted from test categories H and J if the requirements specified for skylights in Cl.3.13.5b.

g.

CONDITIONS FOR THE USE OF COMPOSITE PANEL WITH PLASTIC USED AS WALL FINISHES OR CEILING FINISHES

Diagram 3.15.19c.(5) : Composite panel with plastic used as wall or ceiling material/ finishes installed internally/ externally
Diagram 3.15.19c.(5) : Composite panel with plastic used as wall or ceiling material/ finishes installed internally/ externally

Annex 3A - Notional Periods of Fire Resistance

A1.0 General

In this Annex:

  1. “Class 1 aggregate” means foamed slag, pumice, blast furnace slag, pelleted fly ash, crushed brick and burnt clay products (including expanded clay) well-burnt clinker and crushed limestone.

  2. “Class 2 aggregate” means flint gravel, granite, and all crushed natural stones other than limestones.

  3. Any reference to plaster means:

    1. in the case of an external wall 1m or more from the relevant boundary, plaster applied on the internal face only;

    2. in the case of any other wall, plaster applied on both faces;

    3. if to plaster of a given thickness on the external face of a wall, except in the case of a reference to vermiculite-gypsum plaster, rendering on the external face of the same thickness; and

    4. if to vermiculite-gypsum plaster, vermiculite-gypsum plaster of a mix within the range of 1½ to 2:1 by volume.

  4. In the case of a cavity wall, the load is assumed to be on inner leaf only except for fire resistance period of 4-hrs.

  5. Any material or type of construction and its method of preparation or application as referred to in the table, shall conform with the relevant provisions of the Building Control Act (Chapter 29) and the relevant Singapore Standard or Singapore Standard Code of Practice. In the absence of the aforementioned Standard or Code of Practice, the relevant British equivalent or other accepted standard or codes of practice shall be applicable.

A2.0 : WALLS

A2.0 : WALLS

Construction and Materials

Minimum thickness excluding plaster (in mm) for period of fire resistance of

Load-bearing

Non-load-bearing

4 hrs

3 hrs

2 hrs

1½ hrs

1 hr

½ hr

4 hrs

3 hrs

2 hrs

1½ hrs

1 hr

½ hr

A2.1 -- Mansonry Construction

1. Reinforced concrete, minimum concrete cover to main reinforcement of 25mm:

(a) Unplastered (to comply with SS EN 1992–1–2)

-

-

-

-

-

-

-

-

-

-

-

-

(b) 12.5mm cement-sand plaster

180

-

100

100

75

75

-

-

-

-

-

-

(c) 12.5mm gypsum-sand plaster

180

-

100

100

75

75

-

-

-

-

-

-

(d) 12.5mm vermiculite-gypsum plaster

125

-

75

75

63

63

-

-

-

-

-

-

2. No-fines concrete of Class 2 aggregate:

(a) 13mm cement-sand plaster

-

-

-

-

-

-

150

150

150

150

150

150

(b) 13mm gypsum-sand plaster

-

-

-

-

-

-

150

150

150

150

150

150

(c) 13mm vermiculite-gypsum plaster

-

-

-

-

-

-

150

150

150

150

150

150

3. Bricks of clay, concrete or sand-lime:

(a) Unplastered

200

200

100

100

100

100

170

170

100

100

75

75

(b) 13mm cement-sand plaster

200

200

100

100

100

100

170

170

100

100

75

75

(c) 13mm gypsum-sand plaster

200

200

100

100

100

100

170

170

100

100

75

75

(d) 13mm vermiculite-gypsum or perlite-gypsum* plaster

100

-

100

100

100

100

100

-

100

100

75

75

4. Concrete blocks of Class 1 aggregate:

(a) Unplastered

150

-

100

100

100

100

150

-

75

75

75

50

(b) 12.5mm cement-sand plaster

150

-

100

100

100

100

150

-

75

75

75

50

(c) 12.5mm gypsum-sand plaster

150

-

100

100

100

100

150

-

75

75

75

50

(d) 12.5mm vermiculite-gypsum plaster

100

-

100

100

100

100

75

-

75

62

50

50

5. Concrete blocks of Class 2 aggregate:

(a) Unplastered

-

-

100

100

100

100

150

-

100

100

75

50

(b) 12.5mm cement-sand plaster

-

-

100

100

100

100

150

-

100

100

75

50

(c) 12.5mm gypsum-sand plaster

-

-

100

100

100

100

150

-

100

100

75

50

(d) 12.5mm vermiculite-gypsum plaster

100

-

100

100

100

100

100

-

75

75

75

50

6. Autoclaved aerated concrete blocks, density 475 - 1200 kg/m3

180

140

100

100

100

100

100

-

62

62

50

50

7. Hollow concrete blocks, one cell in wall thickness, of Class 1 aggregate:

(a) Unplastered

-

-

100

100

100

100

150

-

100

100

100

75

(b) 12.5mm cement-sand plaster

-

-

100

100

100

100

150

-

100

75

75

75

(c) 12.5mm gypsum-sand plaster

-

-

100

100

100

100

150

-

100

75

75

75

(d) 12.5mm vermiculite-gypsum plaster

-

-

100

100

100

100

150

-

75

75

62

62

8. Hollow concrete blocks, one cell in wall thickness, of Class 2 aggregate:

(a) Unplastered

-

-

-

-

-

-

150

-

150

125

125

125

(b) 12.5mm cement-sand plaster

-

-

-

-

-

-

150

-

150

125

125

100

(c) 12.5mm gypsum-sand plaster

-

-

-

-

-

-

150

-

150

125

125

100

(d) 12.5mm gypsum-sand plaster

-

-

-

-

-

-

125

-

100

100

100

75

9. Cellular clay blocks not less than 50% solid

(a) 12.5mm cement-sand plaster

-

-

-

-

-

-

-

-

-

-

100

75

(b) 12.5mm gypsum-sand plaster

-

-

-

-

-

-

-

-

-

-

100

75

(c) 12.5mm vermiculite-gypsum plaster

-

-

-

-

-

-

200

-

100

100

100

62

10. Cavity wall with outer leaf of bricks or blocks of clay, composition, concrete or sand-lime, not less than 100mm thick and;

 

 

 

 

 

 

 

 

 

 

 

 

(a) inner leaf of bricks or blocks of clay, composition, concrete or sand lime

100

100

100

100

100

100

75

-

75

75

75

75

(b) inner leaf of solid or hollow concrete bricks or blocks of Class 1 aggregate

100

100

100

100

100

100

75

-

75

75

75

75

11. Cavity wall with outer leaf of cellular clay blocks as 9 above and inner leaf of autoclaved aerated concrete blocks, density 480-1200 kg/m3

150

140

100

100

100

100

75

75

75

75

75

75

Note:

* - Perlite-gypsum plaster to clay bricks only

A2.0 : WALLS

Construction and Materials

Period of Fire Resistance

hrs

A2.2 - Framed and Composite Construction (non-load-bearing)

1. Steel frame with external cladding of 16mm rendering on metal lathing and internal lining of autoclaved aerated concrete blocks, density 480-1120 kg/m3 of thickness of –

 

(a) 50mm

2

(b) 62mm

3

(c) 75mm

4

2. Steel frame with external cladding of 100mm concrete blocks and internal lining of 16mm gypsum plaster on metal lathing

4

3. Steel frame with external cladding of 16mm rendering on metal lathing and internal lining of 16mm gypsum plaster on metal lathing

1

4. Steel or timber frame with facings on each side of -

 

(a) metal lathing with cement-sand or gypsum plaster of thickness of-

 

(1) 19mm

1

(2) 12.5mm

½

(b) metal lathing with vermiculite-gypsum or perlite-gypsum plaster of thickness of-

 

(1) 25mm

2

(2) 19mm

(3) 12.5mm

1

(c) 9.5mm plasterboard with gypsum plaster of thickness of 5mm

½

(d) 9.5mm plasterboard with vermiculite-gypsum of thickness of-

 

(1) 25mm

2

(2) 16mm

(3) 10mm

1

(4) 5mm

½

(e) 12.5mm plasterboard

 

(1) unplastered

½

(2) with gypsum plaster of thickness of 12.5mm

1

(f) 12.5mm plasterboard with vermiculite-gypsum plaster of thickness of-

 

(1) 25mm

2

(2) 16mm

1 ½

(3) 10mm

1

(g) 19mm plasterboard (or two layers of 9.5mm fixed to break joint) without finish

1

(h) 19mm plasterboard for two layers of 9.5mm with vermiculite-gypsum plaster of thickness of-

 

(1) 16mm

2

(2) 10mm

1 ½

(i) 12.5mm fibre insulating board with gypsum plaster of thickness of 12.5mm

½

(j) 25mm wood wool slabs with gypsum plaster of thickness of 12.5mm

1

5. Compressed straw slabs in timber frames finished on both faces with gypsum plaster of thickness of 5mm

1

6. Plasterboard 9.5mm cellular core partition-

 

(a) unplastered

½

(b) 12.5mm gypsum plaster

½

(c) 22mm vermiculite-gypsum plaster

2

7. Plasterboard 12.5mm cellular core partition-

 

(a) unplastered

½

(b) 12.5mm gypsum plaster

1

(c) 16mm vermiculite-gypsum plaster

2

8. Plasterboard 19mm finished on both faces with 16mm gypsum plaster

1

9. Plasterboard 12.5mm bonded with neat gypsum plaster to each side of 19mm plasterboard

1

10. Three layers of 19mm plasterboard bonded with heat gypsum plaster

2

11. Wood wool slab with 12.5mm rendering or plaster of thickness of-

 

(a) 75mm

2

(b) 50mm

1

12. Compressed straw slabs, with 75mm by 12.5mm wood cover strips to joints, of thickness of 50mm

½

Note :

* - The presence of a combustible vapour barrier within the thickness of these constructions shall not be regarded as affecting these periods of fire resistance

A2.0 : WALLS

Construction and Materials

Period of Fire Resistance

hrs

A2.3 - External walls (non-loadbearing) more than 1m from the relevant boundary

1. Steel frame with external cladding of non-combustible sheets and internal lining of-

(a) 12.5mm cement-sand or gypsum plaster on metal lathing

4

(b) two layers of 9.5mm plasterboard

½

(c) 9.5mm plasterboard finished with gypsum plaster of thickness of 12.5mm

½

(d) 12.5mm plasterboard finished with 5mm gypsum plaster

½

(e) 50mm compressed straw slabs

½

(f) 50mm compressed straw slabs finished with 5mm gypsum plaster

2

2 *Timber frame with external cladding of 10mm cement-sand or cement-lime rendering and internal lining of-

(a) 16mm gypsum plaster on metal lathing

1

(b) 9.5mm plasterboard finished with12.5 mm gypsum plaster

1

(c) 12.5mm plasterboard finished with 5mm gypsum plaster

1

(d) 50mm compressed straw slabs

1

(e) aerated concrete blocks

1

(1) 50mm

3

(2) 62mm

4

(3) 75mm

4

(4) 100mm

4

3 Timber frame with external cladding of 100mm clay, concrete or sand-lime bricks of blocks, finished internally with 16mm gypsum plaster on metal lathing

4

4. *Timber frame with external cladding of weather boarding or 9.5 mm plywood and internal lining of-

(a) 16mm gypsum plaster on metal lathing

½

(b) 9.5mm plasterboard finished with 12.5mm gypsum plaster

½

(c) 12.5mm plasterboard finished with 5mm gypsum plaster

½

(d) 50mm compressed straw slabs

½

(e) aerated concrete blocks-

 

(1) 50mm

3

(2) 62mm

4

(3) 75mm

4

(4) 100mm

4

Note:

* - The presence of a combustible vapour barrier within the thickness of these constructions shall not be regarded as affecting these periods of fire resistance

A3.0: REINFORCED CONCRETE BEAMS

A3.0: REINFORCED CONCRETE BEAMS

Description

Minimum Dimension (mm) of Concrete to give a Fire Resistance of:-

4 hrs

3 hrs

2 hrs

1 ½ hrs

1 hr

½ hr

1 Siliceous aggregate concrete:

(a) average concrete cover to main reinforcement

65*

55*

45*

35

25

15

(b) beam width

280

240

180

140

110

80

2. As (1) with cement or gypsum plaster 15mm thick on light mesh reinforcement

(a) average concrete cover to main reinforcement

50*

40

30

20

15

15

(b) beam width

250

210

170

110

85

70

3. As (1) with vermiculite/ gypsum plaster+ 15mm thick:

(a) average concrete cover to main reinforcement

25

15

15

15

15

15

(b) beam width

175

145

125

85

60

60

4. Light weight aggregate concrete:

(a) average concrete cover to main reinforcement

50

45

35

30

20

15

(b) beam width

250

200

160

130

100

80

Note:

* - Supplementary reinforcement, to hold the concrete cover in position, may be necessary

+ - Vermiculite/ gypsum plaster should have a mix ratio in the range of 1 ½ - 2: 1 by volume

A4.0: PRESTRESSED CONCRETE BEAMS

A4.0: PRESTRESSED CONCRETE BEAMS

Description

Minimum Dimension (mm) of Concrete to give a Fire Resistance of:-

4 hrs

3 hrs

2 hrs

1 ½ hrs

1 hr

½ hr

1 Siliceous aggregate concrete:

(a) average concrete cover to tendons

100*

85*

65*

50*

40

25

(b) beam width

280

240

180

140

110

80

2. As (1) with vermiculite concrete slabs 15mm thick , used as permanent shuttering:

(a) average concrete cover to tendons

75*

60

45

35

25

15

(b) beam width

210

170

125

100

70

70

3. As (2) but with 25mm thick slabs:

(a) average concrete cover to tendons

65

50

35

25

15

15

(b) beam width

180

140

100

70

60

60

4. As (1) with 15mm thick gypsum plaster with light mesh reinforcement:

(a) average concrete cover to tendons

90*

75

50

40

30

15

(b) beam width

250

210

170

110

85

70

5. As (1) with vermiculite/gypsum plaster+ 15m thick:

(a) average concrete cover to tendons

75*

60

45

30

25

15

(b) beam width

170

145

125

85

60

60

6. As (5) but with 25mm thick coating:

(a) average concrete cover to tendons

50

45

30

25

15

15

(b) beam width

140

125

85

70

60

60

7. Lightweight aggregate concrete:

(a) average concrete cover to tendons

80

65

50

40

30

20

(b) beam width

250

200

160

130

100

80

Note:

* - Supplementary reinforcement, to hold the concrete cover in position, may be necessary

+ - Vermiculite/gypsum plaster should have a mix ratio in the range of 1 ½ - 2: 1 by volume

A5.0: REINFORCED CONCRETE COLUMNS

A5.0: REINFORCED CONCRETE COLUMNS

Description

Minimum Dimension (mm) of Concrete to give a Fire Resistance of:-

4 hrs

3 hrs

2 hrs

1½ hrs

1 hr

½ hr

A5.1 - All Face Exposed

1. Siliceous aggregate concrete:

(a) without additional protection

450

400

300

250

200

150

(b) with cement or gypsum plaster 15mm thick on light mesh reinforcement

300

275

225

150

150

150

(c) with vermiculite/ gypsum plaster*

275

225

200

150

120

120

2. Limestone aggregate concrete or siliceous aggregate:

(a) concrete with supplementary reinforcement in concrete cover

300

275

225

200

190

150

3. Lightweight aggregate concrete

300

275

225

200

150

150

A5.2 - One Face Exposed

1. Siliceous aggregate concrete

(a) without additional protection

180

150

100

100

75

75

(b) with vermiculite/ gypsum plaster* 15mm thick on exposed faces

125

100

75

75

65

65

Note:

+ - Vermiculite/gypsum plaster should have a mix ratio in the range of 1 ½ - 2: 1 by volume

A6.0: STRUCTURAL STEEL

A6.0: STRUCTURAL STEEL

A6.1 - Encased Steel Stanchions (Mass per metre not less than 45kg)

Description

Minimum Thickness (mm) of Protection for a Fire Resistance of:

4 hrs

3 hrs

2 hrs

1 ½ hrs

1 hr

½hr

A. Solid Protection* (Unplastered)

1. Concrete not leaner than 1:2:4 mix with natural aggregates-

(a) concrete not assumed to be load- bearing reinforced+

50

-

25

25

25

25

(b) concrete assumed to be load-bearing, reinforced in accordance with SS EN 1992 and SS EN 1994

75

-

50

50

50

50

2. Solid bricks of clay, composition or sand-lime

100

75

50

50

50

50

3. Solid blocks of foamed slag or pumice concrete reinforced+ in every horizontal joint

75

60

50

50

50

50

4. Sprayed vermiculite-cement

-

-

38

32

19

12.5

B. Hollow Protection++

1. Solid bricks of clay, composition or sandlime reinforced in every horizontal joint, unplastered

115

-

50

50

50

50

2. Solid blocks of foamed slag or pumice concrete reinforced+ in every horizontal joint, unplastered

75

-

50

50

50

50

3. Metal lathing with gypsum or cement- lime plaster of thickness of -

-

-

38§

25

19

12.5

4. Metal lathing:-

 

 

 

 

 

 

(a) with vermiculite-gypsum or perlite-gypsum plaster of thickness of

50§

-

19

16

12.5

12.5

(b) spaced 25mm from flanges with vermiculite-gypsum or perlite-gypsum plaster of thickness of

44

-

19

12.5

12.5

12.5

5. Gypsum plasterboard with 1.6mm wire binding at 100mm pitch -

(a) 9.5mm Plasterboard with gypsum plaster of thickness of

-

-

-

-

12.5

12.5

(b) 19mm Plasterboard with gypsum plaster of thickness of

-

-

12.5

10

7

7

6. Gypsum plasterboard with 1.6mm wire binding at 100mm pitch-

(a) 9.5mm plasterboard with vermiculite-gypsum plaster of thickness of

-

-

16

15

10

10

(b) 19mm plasterboard with vermiculite-gypsum plaster of thickness of

38§

-

20

13

10

10

7. Vermiculite-cement slabs of 4:1 mix reinforced with wire mesh and finished with plaster skim. Slabs of thickness of

63

-

25

25

25

25

Note:

* - Solid protection means a casing which is bedded close to the steel without intervening cavities and with all joints in that casing made full and solid

+ - Reinforcement shall consist of steel binding wire not less than 2.3mm in thickness, or a steel mesh weighing not less than 0.48 kg/m2. In concrete protection, the spacing of that reinforcement shall not exceed 150mm in any direction

++ - Hollow protection means that there is a void between the protective material and the steel. All hollow protection to columns shall be effectively sealed at each floor level

§ - Light mesh reinforcement required 12.5mm to 19mm below surface unless special corner beads are used

A6.2 - Encased Steel Beams (Mass per metre not less than 30kg)

A6.2 - Encased Steel Beams (Mass per metre not less than 30kg)

Description

Minimum Thickness (mm) of Protection for a Fire Resistance of :

4 hrs

3 hrs

2 hrs

1½ hrs

1 hr

½ hr

A. Solid Protection+ (Unplastered)

1. Concrete not leaner than 1:2:4 mix with natural aggregates-

(a) concrete not assumed to be load- bearing, reinforced++

75

50

25

25

25

25

(b) concrete assumed to be load-bearing, reinforced in accordance with SS EN 1992 and SS EN 1994

75

75

50

50

50

50

2. Sprayed vermiculite - cement

-

-

38

32

19

12.5

B. Hollow Protection++

1. Metal lathing -

(a) with cement-lime plaster of thickness of

-

-

38

25

19

12.5

(b) with gypsum plaster of thickness of

-

-

22

19

16

12.5

(c) with vermiculite-gypsum or perlite-gypsum plaster of thickness of

32

-

12.5

12.5

12.5

12.5

2. Gypsum plasterboard with 1.6mm wire binding at 100mm pitch-

(a) 9.5mm plasterboard with gypsum plaster of thickness of

-

-

-

-

12.5

12.5

(b) 19 mm plasterboard with gypsum plaster of thickness of

-

-

12.5

10

7

7

3. Plasterboard with 1.6mm wire at 100m pitch -

(a) 9.5mm plaster nailed to wooden cradles finished with gypsum plaster of thickness of

-

-

-

-

-

12.5

(b) 9.5mm plasterboard with vermiculite -gypsum plaster of thickness of

-

-

16

15

10

10

(c) 19mm plasterboard with vermiculite-gypsum plaster of thickness of

32

-

10

10

7

7

(d) 19mm plasterboard with gypsum plaster of thickness of

-

-

20

13

10

10

4. Vermiculite-cement slabs of 4:1 mix reinforced with wire mesh and finished with plaster skim. Slabs of thickness of

63

-

25

25

25

25

5. Gypsum-sand plaster 12.5mm thick applied to heavy duty (Type B as designated in EN 13168) Wood wool slabs of thickness of

-

-

50

38

38

38

Note:

* - Hollow protection means that there is a void between the protective materials and the steel. All hollow protection to columns shall be effectively sealed at each floor level

+ - Solid protection means a casing which is bedded close to the steel without intervening cavities and with all joints in that casing made full and solid

++ - Reinforcement shall consist of steel binding wire not less than 2.3mm in thickness, or a steel mesh weighing not less than 0.48 kg/m2. In concrete protection, the spacing of that reinforcement shall not exceed 150mm in any direction

§ - Light mesh reinforcement required 12.5mm to 19mm below surface unless special corner beads are used

A7.0: STRUCTURAL ALUMINIUM

A7.0: STRUCTURAL ALUMINIUM

Description

Minimum Thickness (mm) of Protection for a Fire Resistance of :

4 hrs

3 hrs

2 hrs

1½ hrs

1 hr

½ hr

A7.1 - Solid Protection*

1. Sprayed vermiculite-cement

-

-

-

-

44

19

A7.2 - Hollow Protection+

1. Metal lathing with vermiculite-gypsum or perlite-gypsum plaster of thickness of

-

-

32

22

16

12.5

2. Metal lathing finished with neat gypsum plaster of thickness of

-

-

-

-

19

12.5

3. Gypsum plasterboard 19mm thick with 1.6 mm wire binding at 100mm pitch finished with gypsum-vermiculite plaster of thickness of

-

-

22

16

10

10

Note:

* - Solid protection means a casing which is bedded close to the alloy without intervening cavities and with all joints in that casing made full and solid

+ - Hollow protection means that there is a void between the protected material and the alloy. All hollow protection to columns shall be effectively sealed at each floor level

A8.0: TIMBER FLOORS

A8.0: TIMBER FLOORS

Construction and materials

Minimum Thickness (mm) of Protection for a Fire Resistance of:

1 hr

½ hr

modified++ ½ hr

1. Plain edge boarding on timber joists not less than 38mm wide with ceiling of -

(a) timber lath and plaster - thickness of plaster

-

16

16

(b) timber lath and plaster with plaster of minimum thickness of 16mm covered on underside with plasterboard of thickness

-

12.5

-

(c) metal lathing and plaster - thickness of plaster

 

 

 

(1) gypsum

-

16

-

(2) vermiculite

-

12.5

-

(d) one layer of plasterboard of thickness

-

-

12.5

(e) one layer of plasterboard of minimum thickness of 9.5mm finished with gypsum plaster of thickness

-

-

12.5

(f) one layer of plasterboards of minimum thickness of 12.5mm finished with gypsum plaster of thickness

-

12.5

-

(g) two layers of plasterboard of total thickness

-

25

19

(h) one layer of fibre insulating board of minimum thickness of 9.5mm finished with gypsum plaster of thickness

-

5

-

(i) one layer of fibre insulating board of minimum thickness of 12.5mm finished with gypsum plaster of thickness

-

-

12.5

(j) wood wool slab 25mm thick finished with gypsum plaster of thickness

-

5

-

2. Tongued and grooved boarding of not less than 16mm (finished) thickness* on timber joists not less than 38 mm wide ceiling of -

(a) timber lath and plaster - thickness of plaster

-

-

16

(b) timber lath and plaster with plaster of minimum thickness of 16mm covered on underside with plasterboard of thickness

-

9.5

-

(c) metal lathing and plaster - thickness of plaster

 

 

 

(1) gypsum

22

16

-

(2) vermiculite

12.5

12.5

-

(d) one layer of plasterboard of thickness

 -

-

9.5

(e) one layer of plasterboard of minimum thickness of 9.5mm finished with-

(1) gypsum plaster of thickness

 -

12.5

-

(2) vermiculite-gypsum plaster of thickness

12.5

-

-

(f) one layer of plasterboards of minimum thickness of 12.5mm finished with gypsum plaster of thickness

-

5

-

(g) two layers of plasterboard of total thickness

-

22

-

(h) one layer of fibre insulating board of minimum thickness of 9.5mm finished with gypsum plaster of thickness

-

-

5

(i) wood wool slab 25mm thick finished with -

(1) gypsum plaster of thickness

 -

5

-

(2) vermiculite - gypsum plaster of thickness

10

-

-

3. Tongued and grooved boardings of not less than 21mm (finished) thickness* on timber joists not less than

(a) timber lath and plaster - thickness of plaster

 -

16

-

(b) metal lathing and plaster - thickness of plaster

-

16

-

(c) one layer of plasterboard of thickness

-

-

9.5

(d) one layer of plasterboard of minimum thickness of 9.5mm finished with -

(1) gypsum plaster of thickness

 -

12.5

-

(2) vermiculite-gypsum plaster of thickness

12.5

-

-

(e) one layer of plasterboard of minimum thickness of 12.5mm finished with gypsum plaster of thickness 

-

5

-

(f) two layers of plasterboard of total thickness

 -

19

-

(g) one layer of fibre insulating board of thickness

 -

-

12.5

(h) one layer of fibre insulating board of minimum thickness of 12.5mm finished with gypsum plaster of thickness

-

12.5

-

(i) wood wool slab 25mm thick finished with -

(1) gypsum plaster of thickness

 -

5

-

(2) vermiculite-gypsum plaster of thickness

10

-

-

Note:

* - Or an equivalent thickness of wood chipboard

++ - The term “modified ½ hour” refers to the requirements specified in item 3(a) of Table 3.4A

A9.0: REINFORCED CONCRETE FLOORS (SILICEOUS OR CALCAREOUS AGGREGATE)

A9.0: REINFORCED CONCRETE FLOORS (SILICEOUS OR CALCAREOUS AGGREGATE)

Floor Construction

Minimum Dimension (mm) to give Fire Resistance of :

4 hrs

3 hrs

2 hrs

1 ½ hrs

1 hr

½ hr

Solid slab

Average cover to reinforcement

25

25

20

20

15

15

Depth, overall+

150

150

125

125

100

100

Cored slabs in which the cores are circular or are higher than wide. Not less than 50% of the gross across section of the floor should be solid material

Average cover to reinforcement

25

25

20

20

15

15

Thickness under cores

50

40

40

30

25

20

Depth, overall+

190

175

160

140

110

100

Hollow box section with one or more longitudinal cavities which are wider than high

Average cover to reinforcement

25

25

20

20

15

15

Thickness of bottom flange

50

40

40

30

25

20

Depth, overall+

230

205

180

155

130

105

Ribbed floor with hollow infill blocks of clay, or inverted T-section beams with hollow infill blocks of concrete or clay. A floor in which less than 50% of the gross cross section is solid material must be provided with a 15mm plaster coating on soffit

Average cover to reinforcement

25

25

20

20

15

15

Width or rib, or beam, at soffit

125

100

90

80

70

50

Depth, overall+

190

175

160

140

110

100

Upright T-section

Average bottom cover to reinforcement

65*

55*

45*

35

25

15

Side cover to reinforcement

65

55

45

35

25

15

Least width or down-standing leg

150

140

115

90

75

60

Thickness of flange+

150

150

125

125

100

90

Inverted channel sections with radius at intersection of soffits with top of leg not exceeding depth of section

Average bottom cover to reinforcement

65*

55*

45*

35

25

15

Side cover to reinforcement

40

30

25

20

15

10

Least width or down-standing leg

75

70

60

45

40

30

Thickness at crown+

150

150

125

125

100

90

Inverted channel sections or U-sections with radius at intersection of soffits with top of leg exceeding depth of section

Average bottom cover to reinforcement

65*

55*

45*

35

25

15

Side cover to reinforcement

40

30

25

20

15

10

Least width or down-standing leg

70

60

50

40

35

25

Thickness at crown+

150

150

100

100

75

65

Note:

* -  Supplementary reinforcement, to hold the concrete cover in position, may be necessary

+ - Non-combustible screeds and finishes may be included in these dimensions

A10.0: PRESTRESSED CONCRETE FLOORS (SILICEOUS OR CALCAREOUS AGGREGATE)

A10.0: PRESTRESSED CONCRETE FLOORS (SILICEOUS OR CALCAREOUS AGGREGATE)

Floor Construction

Minimum Dimension (mm) to give Fire Resistance of :

4 hrs

3 hrs

2 hrs

1 ½ hrs

1 hr

½ hr

Solid slab

Average cover to reinforcement

65*

50*

40

30

25

15

Depth, overall+

150

150

125

125

100

90

Cored slabs in which the cores are circular or are higher than wide. Not less than 50% of the gross across section of the floor should be solid material

Average cover to reinforcement

65*

50*

40

30

25

15

Thickness under cores

50

40

40

30

25

20

Depth, overall+

190

175

160

140

110

100

Hollow box section with one or more longitudinal cavities which are wider than high

Average cover to reinforcement

65*

50*

40

30

25

15

Thickness of bottom flange

65

50

40

30

25

25

Depth, overall+

230

205

180

155

130

105

Ribbed floor with hollow infill blocks of clay, or inverted T-section beams with hollow infill blocks of concrete or clay. A floor in which less than 50% of the gross cross section is solid material must be provided with a 15mm plaster coating on soffit

Average cover to reinforcement

65*

50*

40

30

25

15

Width or rib, or beam, at soffit

125

100

90

80

70

50

Depth, overall+

190

175

160

140

110

100

Upright T-section

Average bottom cover to reinforcement

100*

85*

65*

50*

40

25

Side cover to reinforcement

100

85

65

50

40

25

Least width or down-standing leg

250

200

150

110

90

60

Thickness of flange+

150

150

125

125

100

90

Inverted channel sections with radius at intersection of soffits with top of leg not exceeding depth of section

Average bottom cover to reinforcement

100*

85*

65*

50*

40

25

Side cover to reinforcement

50

45

35

25

20

10

Least width or down-standing leg

125

100

75

55

45

30

Thickness at crown+

150

150

125

125

100

90

Inverted channel sections or U-sections with radius at intersection of soffits with top of leg exceeding depth of section

Average bottom cover to reinforcement

100*

85*

65*

50*

40

25

Side cover to reinforcement

50

45

35

25

20

15

Least width or down-standing leg

110

90

70

50

45

30

Thickness at crown+

150

150

125

125

100

90

Note:

* -  Supplementary reinforcement, to hold the concrete cover in position, may be necessary

+ - Non-combustible screeds and finishes may be included in these dimensions

A11.0: GLAZING

A11.0: GLAZING

Construction and materials

Minimum Thickness (mm) of Glazing for a Period of:-

1 hr

½ hr

1. Glass, in direct combination with metal, the melting point of which is not lower than 982.2°C, in square not exceeding 0.015m2 in area

Thickness of glass

-

6.35

2. Glass reinforced with wire not less than 0.46mm in diameter laid to a square mesh measuring 12.70mm from centre to centre of wire, and electrically welded at the intersections, or laid to a hexagonal mesh measuring 25.40mm across the flat side

Thickness of glass

-

6.35

In windows, doors , borrowed lights, lanterns and skylights, glass complying with paragraphs 1 or 2 of this Table shall be fixed with wood or metal beads or with a glazing compound in conjunction with sprigs or clips in panels not exceeding 0.372m 2 in area in timber frames (fixed shut) having a minimum width and thickness of 44.45mm clear of rebates

3. Glass reinforced with wire as in paragraph 2 of this Table, in windows, doors, borrowed lights, lanterns and skylights, fixed with metal beads in panels not exceeding 1.115m2 in metal frames (fixed shut) all metal having a melting point not lower than 982.2oC, the thickness of glass

6.35

6.35

4. Glass bricks or blocks in walls

Laid in cement / lime / sand mortar with light wire reinforcing mesh in every third horizontal joint in a panel not exceeding 2.438m in width or height set along the sides and head into recesses in the surrounding non-combustible construction. The depth of such recessed shall be not less than 25.40mm, the glass blocks extending into the recesses to a depth of 12.70mm and bedded upon layer of glass fibre. A non-hardening mastic shall be used to fill the spaces between the sides of the recesses and the faces of the panels

-

98.43

Note:

In this Table the absence of a figure in a period column indicated that glazing described is not acceptable for the period applicable to that column

Limits of Unprotected Openings

B1.0 CALCULATION OF PERMITTED LIMITS OF UNPROTECTED AREAS

B1.1 The permitted limit of unprotected areas in any side of a building or compartment shall be calculated by reference to the requirements of B2.0.

B1.2 For the purposes of this Annex, the expression "unprotected area" has the meaning ascribed to it by Cl.1.4.110, but in calculating the size of unprotected areas or the permitted limit of unprotected areas, the following provisions shall apply -

  1. where any area of an external wall is an unprotected area, only because it has combustible material attached to it as cladding, the area of that unprotected area shall be deemed to be half the area of such cladding;

  2. when unprotected openings in the same compartment are recessed at a distance or an angle to the plane of reference, the width of the unprotected opening can be reduced accordingly when projected to the plane of reference based on Table 3 and Table 4. However, such reduction is not applicable to the following:

    1. Concave building profile or the like where a specific point on the receiving panel receives radiation from more than one source. 

    2. When the unprotected opening is along a continuous circular profile where its size and angle cannot be determined.

  3. no account shall be taken of any of the following:

    1. an unprotected area which does not exceed 0.1m2 and which is not less than 1.5m from any other unprotected area in the same side of the building or compartment (unless that other falls within (3) below);

    2. one or more unprotected areas having an area (or, if more than one, the aggregate area) not exceeding 1m2 and not less than 4m from any other unprotected area in the same side of the building or compartment (except any such area as is specified in (1) above);

    3. an unprotected area in any part of an external wall which forms part of a protected shaft;

    4. an unprotected area in the side of a building not divided into compartments, if the area is not less than 28m above any ground adjoining that side of the building.

B2.0 Rules of calculation by reference to an enclosing rectangle

B2.1 The conditions of this Part of this Annex shall be satisfied if a building or compartment is so situated that no point on the relevant boundary is either between the relevant plane of reference and the side of the building or compartment or at a distance from the relevant plane of reference which is less than the distance specified in the Tables to this Part of this Annex, according to the purpose group of the building or compartment, the dimensions of the enclosing rectangle and the unprotected percentage. Linear interpolation to determine the setback distance using Table 1 & 2 is permitted, provided the unprotected percentage falls between 20% and 100%. 

B2.2 For the purpose of this Part of this Annex:

  1. “relevant boundary” means as defined in Cl.1.4.89 and for the purpose of this calculation is either parallel to the side of the building under consideration or at an angle of not more than 80° with that side;

  2. “plane of reference” means any vertical plane which touches the side or some part of the side of a building or compartment but which (however far extended) does not pass within the structure of such building or compartment (and for this purpose, any balcony, coping or similar projection shall be deemed not to be part either of that side or of the structure); and the relevant plane of reference shall in each case be taken as that most favourable in that respect to the person erecting the building;

  3. “enclosing rectangle” means the smallest rectangle on the relevant plane of reference which would:

    1. enclose all the outer edge of any unprotected area of the building or, if the building is divided into compartments, of the compartment (other than any of an unprotected area which is at an angle of more than 80° to the plane of reference the outer edges being for this purpose projected on the plane of reference by line perpendicular to such plane;

    2. have two horizontal sides; and

    3. have height and width falling within those listed in the Tables to this Part of this Annex.

  4. “unprotected percentage” means the percentage of the area of the enclosing rectangle which is equal to the aggregate of the unprotected areas taken into account in calculating the enclosing rectangle and as projected on it.

TABLE 1: BUILDINGS OR COMPARTMENTS OF PG I, PG II, PG III, PG IV, PG VII & PG VIII (for Open-sided Car Parking Decks only)

TABLE 1: BUILDINGS OR COMPARTMENTS OF PG I, PG II, PG III, PG IV, PG VII & PG VIII (for Open-sided Car Parking Decks only)

Enclosing Rectangle

Distance (m) from Relevant Boundary for Unprotected Percentage not exceeding

Ht.

Width

20%

30%

40%

50%

60%

70%

80%

90%

100%

3 metres

3m

1.0

1.0

1.0

1.5

1.5

1.5

2.0

2.0

2.0

6m

1.0

1.0

1.5

2.0

2.0

2.0

2.5

2.5

3.0

9m

1.0

1.0

1.5

2.0

2.5

2.5

3.0

3.0

3.5

12m

1.0

1.5

2.0

2.0

2.5

3.0

3.0

3.5

3.5

15m

1.0

1.5

2.0

2.5

2.5

3.0

3.5

3.5

4.0

18m

1.0

1.5

2.0

2.5

2.5

3.0

3.5

4.0

4.0

21m

1.0

1.5

2.0

2.5

3.0

3.0

3.5

4.0

4.5

24m

1.0

1.5

2.0

2.5

3.0

3.5

3.5

4.0

4.5

27m

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.0

4.5

30m

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.0

4.5

40m

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.0

5.0

No limit

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.0

5.0

6 metres

3m

1.0

1.0

1.5

2.0

2.0

2.0

2.5

2.5

3.0

6m

1.0

1.5

2.0

2.5

3.0

3.0

3.5

4.0

4.0

9m

1.0

2.0

2.5

3.0

3.5

4.0

4.5

4.5

5.0

12m

1.5

2.5

3.0

3.5

4.0

4.5

5.0

5.0

5.5

15m

1.5

2.5

3.0

4.0

4.5

5.0

5.5

5.5

6.0

18m

1.5

2.5

3.5

4.0

4.5

5.0

5.5

6.0

6.5

21m

1.5

2.5

3.5

4.0

5.0

5.5

6.0

6.5

7.0

24m

1.5

2.5

3.5

4.5

5.0

5.5

6.0

7.0

7.0

27m

1.5

2.5

3.5

4.5

5.0

6.0

6.5

7.0

7.5

30m

1.5

2.5

3.5

4.5

5.0

6.0

6.5

7.0

8.0

40m

1.5

2.5

3.5

4.5

5.5

6.5

7.0

8.0

8.5

50m

1.5

2.5

3.5

4.5

5.5

6.5

7.5

8.0

9.0

60m

1.5

2.5

3.5

5.0

5.5

6.5

7.5

8.5

9.5

80m

1.5

2.5

3.5

5.0

6.0

7.0

7.5

8.5

9.5

100m

1.5

2.5

3.5

5.0

6.0

7.0

8.0

8.5

10.0

No limit

1.5

2.5

3.5

5.0

6.0

7.0

8.0

8.5

10.0

9 metres

3m

1.0

1.0

1.5

2.0

2.5

2.5

3.0

3.0

3.5

6m

1.0

2.0

2.5

3.0

3.5

4.0

4.5

4.5

5.0

9m

1.5

2.5

3.5

4.0

4.5

5.0

5.5

5.5

6.0

12m

1.5

3.0

3.5

4.5

5.0

5.5

6.0

6.5

7.0

15m

2.0

3.0

4.0

5.0

5.5

6.0

6.5

7.0

7.5

18m

2.0

3.5

4.5

5.0

6.0

6.5

7.0

8.0

8.5

21m

2.0

3.5

4.5

5.5

6.5

7.0

7.5

8.5

9.0

24m

2.0

3.5

5.0

5.5

6.5

7.5

8.0

9.0

9.5

27m

2.0

3.5

5.0

6.0

7.0

7.5

8.5

9.5

10.0

30m

2.0

3.5

5.0

6.0

7.0

8.0

9.0

9.5

10.5

40m

2.0

3.5

5.5

6.5

7.5

8.5

9.5

10.5

11.5

50m

2.0

4.0

5.5

6.5

8.0

9.0

10.0

11.5

12.5

60m

2.0

4.0

5.5

7.0

8.0

9.5

11.0

11.5

13.0

80m

2.0

4.0

5.5

7.0

8.5

10.0

11.5

12.5

13.5

100m

2.0

4.0

5.5

7.0

8.5

10.0

11.5

12.5

14.5

120m

2.0

4.0

5.5

7.0

8.5

10.0

11.5

12.5

14.5

No limit

2.0

4.0

5.5

7.0

8.5

10.5

12.0

12.5

15.0

12 metres

3m

1.0

1.5

2.0

2.0

2.5

3.0

3.0

3.5

3.5

6m

1.5

2.5

3.0

3.5

4.0

4.5

5.0

5.0

5.5

9m

1.5

3.0

3.5

4.5

5.0

5.5

6.0

6.5

7.0

12m

1.5

3.5

4.5

5.0

6.0

6.5

7.0

7.5

8.0

15m

2.0

3.5

5.0

5.5

6.5

7.0

8.0

8.5

9.0

18m

2.5

4.0

5.0

6.0

7.0

7.5

8.5

9.0

10.0

21m

2.5

4.0

5.5

6.5

7.5

8.5

9.0

10.0

10.5

24m

2.5

4.5

6.0

7.0

8.0

8.5

9.5

10.5

11.5

27m

2.5

4.5

6.0

7.0

8.0

9.0

10.5

11.0

12.0

30m

2.5

4.5

6.5

7.5

8.5

9.5

10.5

11.5

12.5

40m

2.5

5.0

6.5

8.0

9.5

10.5

12.0

12.0

14.0

50m

2.5

5.0

7.0

8.5

10.0

11.0

13.0

14.0

15.0

60m

2.5

5.0

7.0

9.0

10.5

12.0

13.5

14.5

16.0

80m

2.5

5.0

7.0

9.0

11.0

13.0

14.5

16.0

17.0

100m

2.5

5.0

7.5

9.5

11.5

13.5

15.0

16.5

18.0

120m

2.5

5.0

7.5

9.5

11.5

13.5

15.0

17.0

18.5

No limit

2.5

5.0

7.5

9.5

12.0

14.0

15.5

17.0

19.0

15 metres

3m

1.0

1.5

2.0

2.5

2.5

3.0

3.5

3.5

4.0

6m

1.5

2.5

3.0

4.0

4.5

5.0

5.5

5.5

6.0

9m

2.0

3.0

4.0

5.0

5.5

6.0

6.5

7.0

7.5

12m

2.0

3.5

5.0

5.5

6.5

7.0

8.0

8.5

9.0

15m

2.0

4.0

5.5

6.5

7.0

8.0

9.0

9.5

10.0

18m

2.5

4.5

6.0

7.0

8.0

8.5

9.5

10.5

11.0

21m

2.5

5.0

6.5

7.5

8.5

9.5

10.5

11.0

12.0

24m

3.0

5.0

6.5

8.0

9.0

10.0

11.0

12.0

13.0

27m

3.0

5.5

7.0

8.5

9.5

10.5

11.5

12.5

13.5

30m

3.0

5.5

7.5

8.5

10.0

11.0

12.0

13.5

14.0

40m

3.0

6.0

8.0

9.5

11.0

12.5

13.5

15.0

16.0

50m

3.5

6.0

8.5

10.0

12.0

13.5

15.0

16.5

17.5

60m

3.5

6.5

8.5

10.5

12.5

14.0

15.5

17.0

18.0

80m

3.5

6.5

9.0

11.0

13.5

15.0

17.0

18.5

20.0

100m

3.5

6.5

9.0

11.5

14.0

16.0

18.0

19.5

21.5

120m

3.5

6.5

9.0

11.5

14.0

16.5

18.5

20.5

22.5

No limit

3.5

6.5

9.0

12.0

14.5

17.0

19.0

21.0

23.0

18 metres

3m

1.0

1.5

2.0

2.5

2.5

3.0

3.5

4.0

4.0

6m

1.5

2.5

3.5

4.0

4.5

5.0

5.5

6.0

6.5

9m

2.0

3.5

4.5

5.0

6.0

6.5

7.0

8.0

8.5

12m

2.5

4.0

5.0

6.0

7.0

7.5

8.5

9.0

10.0

15m

2.5

4.5

6.0

7.0

8.0

8.5

9.5

10.5

11.0

18m

2.5

5.0

6.5

7.5

8.5

9.5

11.0

11.5

13.0

21m

3.0

5.5

7.0

8.0

9.5

10.5

11.5

12.5

13.0

24m

3.0

5.5

7.5

8.5

10.0

11.0

12.0

13.0

14.0

27m

3.5

6.0

8.0

9.0

10.5

11.5

12.5

13.5

14.5

30m

3.5

6.5

8.0

9.5

11.0

12.0

13.5

14.5

15.5

40m

4.0

7.0

9.0

11.0

12.0

13.5

15.0

16.5

17.5

50m

4.0

7.0

9.5

11.5

13.0

15.0

16.5

18.0

19.0

60m

4.0

7.5

10.0

12.0

14.0

16.0

17.5

19.5

20.5

80m

4.0

7.5

10.0

13.0

15.0

17.0

19.0

21.0

22.5

100m

4.0

7.5

10.0

13.5

16.0

18.0

20.5

22.5

24.0

120m

4.0

7.5

10.0

14.0

16.5

19.0

21.0

23.5

25.5

No limit

4.0

8.0

10.0

14.0

17.0

19.5

22.0

24.0

26.5

21 metres

3m

0.5

1.5

2.0

2.5

3.0

3.0

3.5

4.0

4.5

6m

1.5

2.5

3.5

4.0

5.0

5.5

6.0

6.5

7.0

9m

2.0

3.5

4.5

5.5

6.5

7.0

7.5

8.5

9.0

12m

2.5

4.0

5.5

6.5

7.5

8.5

9.0

10.0

10.5

15m

2.5

5.0

6.5

7.5

8.5

9.5

10.5

11.0

12.0

18m

3.0

5.5

7.0

8.0

9.5

10.5

11.5

12.5

13.0

21m

3.0

6.0

7.5

9.0

10.5

11.0

12.5

13.5

14.0

24m

3.5

6.0

8.0

9.5

10.5

12.0

13.0

14.0

15.0

27m

3.5

6.5

8.5

10.0

11.5

13.0

14.0

15.0

16.0

30m

4.0

7.0

9.0

10.5

12.0

13.0

14.5

16.0

16.5

40m

4.5

7.5

10.0

12.0

13.5

15.0

16.5

18.0

19.0

50m

4.5

8.0

11.0

13.0

14.5

16.5

18.0

20.0

21.0

60m

4.5

8.5

11.5

13.5

15.5

17.5

19.5

21.0

22.5

80m

4.5

8.5

12.0

14.5

17.0

19.0

21.0

23.5

25.0

100m

4.5

9.0

12.0

15.5

18.0

20.5

22.5

25.0

27.0

120m

4.5

9.0

12.0

16.0

18.5

21.5

23.5

26.5

28.5

No limit

4.5

9.0

12.0

16.0

19.0

22.0

25.0

26.5

29.5

24 metres

3m

0.5

1.5

2.0

2.5

3.0

3.5

3.5

4.0

4.5

6m

1.5

2.5

3.5

4.5

5.0

5.5

6.0

7.0

7.0

9m

2.0

3.5

5.0

5.5

6.5

7.5

8.0

9.0

9.5

12m

2.5

4.5

6.0

7.0

8.0

8.5

9.5

10.5

11.5

15m

3.0

5.0

6.5

8.0

9.0

10.0

11.0

12.0

13.0

18m

3.0

5.5

7.5

8.5

10.0

11.0

12.0

13.0

14.0

21m

3.5

6.0

8.0

9.5

10.5

12.0

13.0

14.0

15.0

24m

3.5

6.5

8.5

10.0

11.5

12.5

14.0

15.0

16.0

27m

4.0

7.0

9.0

11.0

12.5

13.5

15.0

16.0

17.0

30m

4.0

7.5

9.5

11.5

13.0

14.0

15.5

17.0

18.0

40m

4.5

8.5

11.0

13.0

14.5

16.0

18.0

19.0

20.5

50m

5.0

9.0

12.0

14.0

16.0

17.5

19.5

21.0

22.5

60m

5.0

9.5

12.5

15.0

17.0

19.0

21.0

23.0

24.5

80m

5.0

10.0

13.5

16.5

18.5

21.0

23.5

25.5

27.5

100m

5.0

10.0

13.5

17.0

20.0

22.5

25.0

27.5

29.5

120m

5.5

10.0

13.5

17.5

20.5

23.5

26.5

29.0

31.0

No limit

5.5

10.0

13.5

18.0

21.0

24.0

27.5

30.0

32.5

27 metres

3m

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.0

4.5

6m

1.5

2.5

3.5

4.5

5.0

6.0

6.5

7.0

7.5

9m

2.0

3.5

5.0

6.0

7.0

7.5

8.5

9.5

10.0

12m

2.5

4.5

6.0

7.0

8.0

9.0

10.5

11.0

12.0

15m

3.0

5.5

7.0

8.5

9.5

10.5

11.5

12.5

13.5

18m

3.5

6.0

8.0

9.0

10.5

11.5

12.5

13.5

14.5

21m

3.5

6.5

8.5

10.0

11.5

13.0

14.0

15.0

16.0

24m

3.5

7.0

9.0

11.0

12.5

13.5

15.0

16.0

17.0

27m

4.0

7.5

10.0

11.5

13.0

14.0

16.0

17.0

18.0

30m

4.0

8.0

10.0

12.0

13.5

15.0

17.0

18.0

19.0

40m

5.0

9.0

11.5

14.0

15.5

17.5

19.0

20.5

22.0

50m

5.5

9.5

12.5

15.0

17.0

19.0

21.0

22.5

24.0

60m

5.5

10.5

13.5

16.0

18.5

20.5

22.5

24.5

26.5

80m

6.0

11.0

14.5

17.5

20.5

22.5

25.0

27.5

29.5

100m

6.0

11.0

15.5

19.0

21.5

24.5

27.0

30.0

32.0

120m

6.0

11.5

15.5

19.5

22.5

26.0

28.5

32.0

34.0

No limit

6.0

11.5

15.5

20.0

23.5

27.0

29.5

33.0

35.0

TABLE 2: BUILDINGS OR COMPARTMENTS OF PG V, PG VI, & PG VIII (see Table 1 for Open-sided Car Parking Decks)

TABLE 2: BUILDINGS OR COMPARTMENTS OF PG V, PG VI, & PG VIII (see Table 1 for Open-sided Car Parking Decks)

Enclosing Rectangle

Distance (m) from Relevant Boundary for Unprotected Percentage not exceeding

Ht.

Width

20%

30%

40%

50%

60%

70%

80%

90%

100%

3 metres

3m

1.0

1.5

2.0

2.0

2.5

2.5

2.5

3.0

3.0

6m

1.5

2.0

2.5

3.0

3.0

3.5

3.5

4.0

4.0

9m

1.5

2.5

3.0

3.5

4.0

4.0

4.5

5.0

5.0

12m

2.0

2.5

3.0

3.5

4.0

4.5

5.0

5.5

5.5

15m

2.0

2.5

3.5

4.0

4.5

5.0

5.5

6.0

6.0

18m

2.0

2.5

3.5

4.0

5.0

5.0

6.0

6.5

6.5

21m

2.0

3.0

3.5

4.5

5.0

5.5

6.0

6.5

7.0

24m

2.0

3.0

3.5

4.5

5.0

5.5

6.0

7.0

7.5

27m

2.0

3.0

4.0

4.5

5.5

6.0

6.5

7.0

7.5

30m

2.0

3.0

4.0

4.5

5.5

6.0

6.5

7.5

8.0

40m

2.0

3.0

4.0

5.0

5.5

6.5

7.0

8.0

8.5

50m

2.0

3.0

4.0

5.0

6.0

6.5

7.5

8.0

9.0

60m

2.0

3.0

4.0

5.0

6.0

7.0

7.5

8.5

9.5

80m

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

9.5

No limit

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

6 metres

3m

1.5

2.0

2.5

3.0

3.0

3.5

3.5

4.0

4.0

6m

2.0

3.0

3.5

4.0

4.5

5.0

5.5

5.5

6.0

9m

2.5

3.5

4.5

5.0

5.5

6.0

6.5

7.0

7.0

12m

3.0

4.0

5.0

5.5

6.5

7.0

7.5

8.0

8.5

15m

3.0

4.5

5.5

6.0

7.0

7.5

8.0

9.0

9.0

18m

3.5

4.5

5.5

6.5

7.5

8.0

9.0

9.5

10.0

21m

3.5

5.0

6.0

7.0

8.0

9.0

9.5

10.0

10.5

24m

3.5

5.0

6.0

7.0

8.5

9.5

10.0

10.5

11.0

27m

3.5

5.0

6.5

7.5

8.5

9.5

10.5

11.0

12.0

30m

3.5

5.0

6.5

8.0

9.0

10.0

11.0

12.0

12.5

40m

3.5

5.5

7.0

8.5

10.0

11.0

12.0

13.0

14.0

50m

3.5

5.5

7.5

9.0

10.5

11.5

13.0

14.0

15.0

60m

3.5

5.5

7.5

9.5

11.0

12.0

13.5

15.0

16.0

80m

3.5

6.0

7.5

9.5

11.5

13.0

14.5

16.0

17.5

100m

3.5

6.0

8.0

10.0

12.0

13.5

15.0

16.5

18.0

120m

3.5

6.0

8.0

10.0

12.0

14.0

15.5

17.0

19.0

No limit

3.5

6.0

8.0

10.0

12.0

14.0

16.0

18.0

19.0

9 metres

3m

1.5

2.5

3.0

3.5

4.0

4.0

4.5

5.0

5.0

6m

2.5

3.5

4.5

5.0

5.5

6.0

6.5

7.0

7.0

9m

3.5

4.5

5.5

6.0

6.5

7.5

8.0

8.5

9.0

12m

3.5

5.0

6.0

7.0

7.5

8.5

9.0

9.5

10.5

15m

4.0

5.5

6.5

7.5

8.5

9.5

10.0

11.0

11.5

18m

4.5

6.0

7.0

8.5

9.5

10.0

11.0

12.0

12.5

21m

4.5

6.5

7.5

9.0

10.0

11.0

12.0

13.0

13.5

24m

5.0

6.5

8.0

9.5

11.0

12.0

13.0

13.5

14.5

27m

5.0

7.0

8.5

10.0

11.5

12.5

13.5

14.5

15.0

30m

5.0

7.0

9.0

10.5

12.0

13.0

14.0

15.0

16.0

40m

5.5

7.5

9.5

11.5

13.0

14.5

15.5

17.0

17.5

50m

5.5

8.0

10.0

12.5

14.0

15.5

17.0

18.5

19.5

60m

5.5

8.0

11.0

13.0

15.0

16.5

18.0

19.5

21.0

80m

5.5

8.5

11.5

13.5

16.0

17.5

19.5

21.5

23.0

100m

5.5

8.5

11.5

14.5

16.5

18.5

21.0

22.5

24.5

120m

5.5

8.5

11.5

14.5

17.0

19.5

21.5

23.5

26.0

No limit

5.5

8.5

11.5

15.0

17.5

20.0

22.5

24.5

27.0

12 metres

3m

2.0

2.5

3.0

3.5

4.0

4.5

5.0

5.5

5.5

6m

3.0

4.0

5.0

5.5

6.5

7.0

7.5

8.0

8.5

9m

3.5

5.0

6.0

7.0

7.5

8.5

9.0

9.5

10.5

12m

4.5

6.0

7.0

8.0

9.0

9.5

11.0

11.5

12.0

15m

5.0

6.5

8.0

9.0

10.0

11.0

12.0

13.0

13.5

18m

5.0

7.0

8.5

10.0

11.0

12.0

13.0

14.0

14.5

21m

5.5

7.5

9.0

10.5

12.0

13.0

14.0

15.0

16.0

24m

6.0

8.0

9.5

11.5

12.5

14.0

15.0

16.0

16.5

27m

6.0

8.0

10.5

12.0

13.5

14.5

16.0

17.0

17.5

30m

6.5

8.5

10.5

12.5

14.0

15.0

16.5

17.5

18.5

40m

6.5

9.5

12.0

14.0

15.5

17.5

18.5

20.0

21.0

50m

7.0

10.0

13.0

15.0

17.0

19.0

20.5

23.0

23.0

60m

7.0

10.5

13.5

16.0

18.0

20.0

21.5

23.5

25.0

80m

7.0

11.0

14.5

17.0

19.5

21.5

23.5

26.0

27.5

100m

7.5

11.5

15.0

18.0

21.0

23.0

25.5

28.0

30.0

120m

7.5

11.5

15.0

18.5

22.0

24.0

27.0

29.5

31.5

No limit

7.5

12.0

15.5

19.0

22.5

25.0

28.0

30.5

34.0

15 metres

3m

2.0

2.5

3.5

4.0

4.5

5.0

5.5

6.0

6.0

6m

3.0

4.5

5.5

6.0

7.0

7.5

8.0

9.0

9.0

9m

4.0

5.5

6.5

7.5

8.5

9.5

10.0

11.0

11.5

12m

5.0

6.5

8.0

9.0

10.0

11.0

12.0

13.0

13.5

15m

5.5

7.0

9.0

10.0

11.5

12.5

13.5

14.5

15.0

18m

6.0

8.0

9.5

11.0

12.5

13.5

14.5

15.5

16.5

21m

6.5

8.5

10.5

12.0

13.5

14.5

16.0

16.5

17.5

24m

6.5

9.0

11.0

13.0

14.5

15.5

17.0

18.0

19.0

27m

7.0

9.5

11.5

13.5

15.0

16.5

18.0

19.0

20.0

30m

7.5

10.0

12.0

14.0

16.0

17.0

18.5

20.0

21.0

40m

8.0

11.0

13.5

16.0

18.0

19.5

21.0

22.5

23.5

50m

8.5

12.0

15.0

17.5

19.5

21.5

23.0

25.0

26.0

60m

8.5

12.5

15.5

18.0

21.0

23.5

25.0

27.0

28.0

80m

9.0

13.5

17.0

20.0

23.0

25.5

28.0

30.0

31.5

100m

9.0

14.0

18.0

21.5

24.5

27.5

30.0

32.5

34.5

120m

9.0

14.0

18.5

22.5

25.5

28.5

31.5

34.5

37.0

No limit

9.0

14.5

19.0

23.0

27.0

30.0

34.0

36.0

39.0

18 metres

3m

2.0

2.5

3.5

4.0

5.0

5.0

6.0

6.5

6.5

6m

3.5

4.5

5.5

6.5

7.5

8.0

9.0

9.5

10.0

9m

4.5

6.0

7.0

8.5

9.5

10.0

11.0

12.0

12.5

12m

5.0

7.0

8.5

10.0

11.0

12.0

13.0

14.0

14.5

15m

6.0

8.0

9.5

11.0

12.5

13.5

14.5

15.5

16.5

18m

6.5

8.5

11.0

12.0

13.5

14.5

16.0

17.0

18.0

21m

7.0

9.5

11.5

13.0

14.5

16.0

17.0

18.0

19.5

24m

7.5

10.0

12.0

14.0

15.5

16.5

18.5

19.5

20.5

27m

8.0

10.5

12.5

14.5

16.5

17.5

19.5

20.5

21.5

30m

8.0

11.0

13.5

15.5

17.0

18.5

20.5

21.5

22.5

40m

9.0

12.0

15.0

17.5

19.5

21.5

23.5

25.0

26.0

50m

9.5

13.0

16.5

19.0

21.5

23.5

26.0

27.5

29.0

60m

10.0

14.0

17.5

20.5

23.0

26.0

27.5

29.5

31.0

80m

10.0

15.0

19.0

22.5

26.0

28.5

31.0

33.5

35.0

100m

10.0

16.0

20.5

24.0

28.0

31.0

33.5

36.0

38.5

120m

10.0

16.5

21.0

25.5

29.5

32.5

35.5

39.0

41.5

No limit

10.0

17.0

22.0

26.5

30.5

34.0

37.0

41.0

43.5

21 metres

3m

2.0

3.0

3.5

4.5

5.0

5.5

6.0

6.5

7.0

6m

3.5

5.0

6.0

7.0

8.0

9.0

9.5

10.0

10.5

9m

4.5

6.5

7.5

9.0

10.0

11.0

12.0

13.0

13.5

12m

5.5

7.5

9.0

10.5

12.0

13.0

14.0

15.0

16.0

15m

6.5

8.5

10.5

12.0

13.5

14.5

16.0

16.5

17.5

18m

7.0

9.5

11.5

13.0

14.5

16.0

17.0

18.0

19.5

21m

7.5

10.0

12.5

14.0

15.5

17.0

18.5

20.0

21.0

24m

8.0

10.5

13.0

15.0

16.0

18.0

20.0

21.0

22.0

27m

8.5

11.5

14.0

16.0

18.0

19.0

21.0

22.5

23.5

30m

9.0

12.0

14.5

16.5

18.5

20.5

22.0

23.5

25.0

40m

10.0

13.5

16.5

19.0

21.5

23.0

25.5

27.0

28.5

50m

11.0

14.5

18.0

21.0

23.5

25.5

28.0

30.0

31.5

60m

11.5

15.5

19.5

22.5

25.5

28.0

30.5

32.5

33.5

80m

12.0

17.0

21.0

25.0

28.5

31.5

34.0

36.5

38.5

100m

12.0

18.0

22.5

27.0

31.0

34.5

37.0

40.0

42.0

120m

12.0

18.5

23.5

28.5

32.5

36.5

39.5

43.0

45.5

No limit

12.0

19.0

25.0

29.5

34.5

38.0

41.5

45.5

48.0

24 metres

3m

2.0

3.0

3.5

4.5

5.0

5.5

6.0

7.0

7.5

6m

3.5

5.0

6.0

7.0

8.5

9.5

10.0

10.5

11.0

9m

5.0

6.5

8.0

9.5

11.0

12.0

13.0

13.5

14.5

12m

6.0

8.0

9.5

11.5

12.5

14.0

15.0

16.0

16.5

15m

6.5

9.0

11.0

13.0

14.5

15.5

17.0

18.0

19.0

18m

7.5

10.0

12.0

14.0

15.5

16.5

18.5

19.5

20.5

21m

8.0

10.5

13.0

15.0

16.5

18.0

20.0

21.0

22.0

24m

8.5

11.5

14.0

16.0

18.0

19.5

21.0

22.5

24.0

27m

9.0

12.5

15.0

17.0

19.0

20.5

21.5

24.0

25.5

30m

9.5

13.0

15.5

18.0

20.0

21.5

23.5

25.0

26.5

40m

11.0

14.5

18.0

20.5

23.0

25.0

27.5

29.0

30.5

50m

12.0

16.0

19.5

22.5

25.5

27.5

30.0

32.0

33.5

60m

12.5

17.0

21.0

24.5

27.5

30.0

32.5

35.0

36.5

80m

13.5

18.5

23.5

27.5

31.0

34.5

37.0

39.5

41.5

100m

13.5

20.0

25.0

29.5

33.5

37.0

40.0

43.0

45.5

120m

13.5

20.5

26.5

31.0

36.0

39.5

43.0

46.5

49.0

No limit

13.5

21.0

27.5

32.5

37.5

42.0

45.5

49.5

52.0

27 metres

3m

2.0

3.0

4.0

4.5

5.5

6.0

6.5

7.0

7.5

6m

3.5

5.0

6.5

7.5

8.5

9.5

10.5

11.0

12.0

9m

5.0

7.0

8.5

10.0

11.5

12.5

13.5

14.5

15.0

12m

6.0

8.0

10.5

12.0

13.5

14.5

16.0

17.0

17.5

15m

7.0

9.5

11.5

13.5

15.0

16.5

18.0

19.0

20.0

18m

8.0

10.5

12.5

14.5

16.5

17.5

19.5

20.5

21.5

21m

8.5

11.5

14.0

16.0

18.0

19.0

21.0

22.5

23.5

24m

9.0

12.5

15.0

17.0

19.0

20.5

22.5

24.0

25.5

27m

10.0

13.0

16.0

18.0

20.0

22.0

24.0

25.5

27.0

30m

10.0

13.5

17.0

19.0

21.0

23.0

25.0

26.5

28.0

40m

11.5

15.5

19.0

22.0

24.5

26.5

29.0

30.5

32.5

50m

12.5

17.0

21.0

24.0

27.0

29.5

32.0

34.5

36.0

60m

13.5

18.5

22.5

26.5

29.5

32.0

35.0

37.0

39.0

80m

14.5

20.5

25.0

29.5

33.0

36.5

39.5

42.0

44.0

100m

15.5

21.5

27.0

32.0

36.5

40.5

43.0

46.5

48.5

120m

15.5

22.5

28.5

34.0

39.0

43.0

46.5

50.5

53.0

No limit

15.5

23.5

29.5

35.0

40.5

44.5

48.5

52.0

55.5

TABLE 3: Percentage of the Width of the Unprotected Openings upon their Projection onto the Plane of Reference (in view of distance of the openings from the place of reference)

Table 3
Table 3
Illustration A
Illustration A
Illustration A (Enlarged)
Illustration A (Enlarged)
Table 3 (Cont)
Table 3 (Cont)

TABLE 4: Percentage of the Width of the Unprotected Openings upon their Projection onto the Plane of Reference (in view of distance of the openings from the plane of reference)

TABLE 4

Percentage of the Width of the Unprotected Openings upon their Projection onto the Plane of Reference (in view of distance of the openings from the plane of reference)

Angle of unprotected opening to reference plane*

10°

15°

20°

25°

30°

35°

40°

45°

50°

55°

60°

65°

70°

75°

80°

85°

90°

Actual percentage of unprotected opening width on reference plane

96%

91%

87%

83%

78%

74%

70%

66%

62%

58%

54%

50%

46%

43%

39%

36%

32%

29%

Table 4 Diagram
Table 4 Diagram