ECM Self-declaration Criteria

Self–Declaration Scheme to Shorten Approval Process

Phase 2 – 19 Dec 2022

Phase 3 – 1 Jan 2024

  • Development works (Total area ≤ 0.2 Ha)

  • Linear works (Max exposed area ≤ 0.05 Ha)

  • Carpark improvement works

  • Drainage works (width ≤ 2m, length ≤40m)

  • Development works (Total area ≤ 0.5 Ha)

  • Linear works (Max exposed area ≤ 0.2 Ha)

  • Carpark improvement works

  • Drainage works (width ≤ 2m, length ≤40m)

*Examples of Linear works are road improvement works, footpath/PCN/cycling path & trench works

Expansion of ECM Self Declaration Scheme(Phase 3)

Type of Work

Description

Criteria for Self declaration (Phase 3)

Building (with or without basement)

New building / A&A works. Covers commercial, residential, industrial, Mixed (commercial/residential), institutional, etc. Includes new bus interchanges, underpasses

Total site area ≤ 0.5 Ha

Building improvement works (minor)

Lift upgrading, drop off porches, overhead bridges, pavilions

Total site area ≤ 0.5 Ha

Demolition Work

Demolition of building / structures. (Note: Does not include demolition of existing house and building a new structure)

Total site area ≤ 0.5 Ha

Road improvement works

Widening of minor roads, construction of bus stop

Max exposed area ≤ 0.2 Ha

Footpath/ Linkway/ PCN/ Cycling path

New / modification of linear pedestrian, cycling paths, PCN, sheltered linkway

Max exposed area ≤ 0.2 Ha

Trench works, Underground Works

Cable, sewer, water/gas pipe laying, shafts, pipe-jacking

Max exposed area ≤ 0.2 Ha

Carpark improvement works

Modification works

All

Drainage Work

New / modification of drains, ABC projects in drains

Width ≤2m, length≤40m

Categories Not Eligible for ECM Self-Declaration Scheme

Type of Work

Description

Criteria for Self declaration

MRT / Rail projects

Stations, depots, rail (tunnels, viaducts)

Not Eligible

Earth Works / Site Clearance

Vegetation removal, cut and fill works, land preparation, new parks

Road works (Major)

New / modifications to expressways, viaducts or tunnels. Road works that involve retaining walls, earthworks, drainage diversions

Others (please specify)

Other type of works that do not fall into the abovementioned categories

How to submit for self-declared submissions?

  • QECPs and contractors are responsible for the design and implementation of effective ECM on site

  • “Total Site Area (Ha)” and “Max Exposed Area (Ha)” need to be correctly stated in the E-forms and ECM submissions

  • PUB will not hesitate to rescind approvals issued and take enforcement actions for non-compliances